Whitney Bank v. Triangle Construction Company, Inc.
Whitney Bank v. Triangle Construction Company, Inc.
Opinion of the Court
¶ 1. In this lien priority case, a property owner defaulted on his obligations, and the construction lender foreclosed the property. The general contractor had a materialman's lien on the property. At the foreclosure sale, the purchase price for the property was significantly lower than the total amounts owed. The sole issue before the chancery court was which lien had priority-that of the construction lender, or that of the contractor. The chancery court found that the contractor's lien had priority. Because the chancery court did not abuse its discretion, this Court affirms.
FACTS AND PROCEDURAL
HISTORY
¶ 2. Knight Properties purchased a piece of property on which it planned to build a residential development. In February 2007, Hancock Bank issued a line of credit
¶ 3. The first draw on the loan was made on February 19, 2007, in the amount of $966, 872.71, and was used to pay off the balance of the existing purchase loan on the land. Hancock Bank had financed the original purchase of the property, so it used the line of credit to pay off the existing balance to itself. The remaining draws occurred sporadically through May 11, 2009, with Hancock distributing a total of nine draws, in the total amount of $1,704,660.42. For each distribution, Hancock's attorney, George Murphy, checked the chancery court for liens on the property and obtained an owner and/or contractor affidavit from Chad Knight. The affidavit attested that all subcontractors, materialmen, and other such laborers had been paid in full any amounts owed. The affidavit also had the contractor waive any claim to a lien and affirmed that "[t]he owner has no interest or ownership in the contracting firm or firms and the contractor has no interest in the real property described above[.]" Chad Knight then signed each affidavit twice for Reunion, as both the owner and the contractor. Murphy testified that Hancock had not informed him that Triangle was the contractor, and that information would have changed the way he did things in that he "certainly" would have had the contractor sign the affidavit. Hancock asserted that the information that Triangle was the contractor was sent to Murphy at some point via fax. Hancock also had the site inspected by an engineer to ensure that the progress matched the requested disbursement amount.
¶ 4. On March 31, 2008, Reunion and Triangle entered into a contract for Triangle to be the contractor on the project.
¶ 5. In December 2008, Henry Knue and Donna Smith, Hancock Bank employees assigned to the Reunion loan, had a conversation about Triangle. Knue emailed Chad Knight with a subject line "Draw Pending-Triangle Construction" and stated "Please email or fax invoice due Triangle construction so that I may accurately instruct attorney for disbursement." Chad Knight replied that he was faxing the invoice, "However, I'm not sure what you mean regarding the disbursement instructions to the attorney. The draw needs to be disbursed to Reunion Development as all draws have been. We will pay our contractors and vendors." Knue forwarded this to Smith as an "fyi," and Smith responded that "All of our attorney letters that support the disbursement instruct the attorney to disburse any outstanding invoices, etc. that may be out there. I know he is aware of this." Knue replied that the fax he had received from Knight was not a Triangle invoice, but a Reunion invoice. He stated that he "delivered the check so as not to delay the draw given the urgency in posting before end of day on Wednesday. Attorney has historically disbursed to them and executing an affidavit stating no outstanding invoices. Maybe we can address this in Tuesday's meeting with them as well?" Smith replied that "I think that is fine .... As long as there are no liens outstanding to Triangle and they are continuing to do the work, then we should be fine. But be sure that your instructions letter to the attorney states that any outstanding liens are paid for."
¶ 6. On April 27, 2009, Chad Knight emailed Smith with a draw request, and stated "FYI, we plan to send payment from this draw and our funds directly to the subcontractor (Warren Paving), as our last payment to the Triangle construction apparently did not end reach the sub. We've taken steps to protect against this happening again."
¶ 7. Triangle filed a construction and materialmen's lien on the property on December 16, 2009, in the amount of $214,314.18. After Reunion defaulted on the construction loan, Hancock filed a complaint against Chad Knight, Reunion, and Triangle, among others, and also moved for foreclosure. The chancery court authorized Hancock to foreclose on the property. A third party purchased the property at the foreclosure sale for $800,000. Triangle filed a counterclaim against Hancock for the $214,314.18 it was owed. Hancock filed a motion for summary judgment as to Triangle, which the chancery court denied.
¶ 8. After a bench trial on the matter,
ANALYSIS
1. Standard of Review
¶ 9. "Findings of fact made by a chancellor may not be disturbed or set aside on appeal unless manifestly wrong."
Cotton v. McConnell
,
2. Lien Law
¶ 10. "The lien of a deed of trust securing a construction loan has priority over mechanics' and materialmen's liens only to the extent that[:] (a) the funds disbursed actually went into the construction, or (b) to the extent that the construction lender used reasonable diligence in disbursing the construction loan."
Guaranty Mortg. Co. of Nashville v. Seitz
,
3. Whether the funds went into the construction.
¶ 11. Hancock argues that because the first disbursement went to pay off itself for the existing loan on the land, those funds actually went into the construction, because construction is impossible without the land, a so-called "purchase-money" rule within the construction funds test. The chancellor rejected this argument. Triangle argues that money advanced to purchase undeveloped land is clearly not money that went into the construction project.
¶ 12. This Court has noted that " '[a] lender advancing construction funds must use reasonable diligence to see that these funds are actually used in payment for
materials or other cost of construction
. Such a construction mortgagee has preference over materialmen and laborers only to the extent that its funds actually go into the construction.' "
Deposit Guaranty Nat'l Bank v. E.Q. Smith Plumbing & Heating, Inc.
,
¶ 13. As to the priority of construction lender versus materialmen, the Court noted the principle that the equities favor the materialmen.
A materialman, a mechanic or other similar parties ... typically furnishes supplies, materials or services which are indispensible to the successful prosecution of the construction project. That these potential lienors render their services and perform their work, generally on credit, is to everyone's benefit, including the construction lender. For as these parties give value, the value of the construction lender's collateral is enhanced.
If, as here, the materialmen are not paid, quite likely the construction lender will be unjustly enriched at their expense. For in this situation, if the construction lender were allowed a priority over the materialmen, it would have received the enhancement to the value of its collateral while the materialmen, without whose services the bank cannot expect the secured construction loan transaction to succeed, would as a practical matter be without security, and, most likely, with little prospect of getting paid.
We emphasize the ease with which the construction lender may protect itself. Construction lenders may make advances in the form of drafts or checks payable directly to materialmen or payable to materialmen and the builder jointly. Such a practice, of course, would render the present fiasco impossible. Even where such tight controls are not exercised, many construction lenders require affidavits to the effect that all materialmen and potential construction lienors have been paid. Without doubt in this sort of situation the bank/construction lender is in a far better situation than is the materialman to protect itself and police the use of the construction loan funds and thereby avoid the predicament which has in fact ensued.
¶ 14. The Court then discussed the materialmen's priority versus the seller who financed the purchase of the land, and who knew that the undeveloped land was bought with an aim toward construction. In affirming the trial court's decision that the materialmen's liens had priority over L & T Developers's (as original landowner/seller and the party providing the financing for the land purchase) liens, the Court noted that the materialmen
are parties who supplied materials and labor to the improvements on the two lots, thereby enhancing the value of these projects. Through sweat and elbow grease, these two construction lienors in a very real sense created value which previously was not there. The landowner, on the other hand, has made no similar contribution. The landowner had the far greater capacity to protect his interest, and, further, the landowner profits directly from the success of the overall construction project to which the materialmen so materially contribute.
Peoples Bank
,
4. Whether Hancock exercised reasonable diligence.
¶ 15. Hancock argues that it used reasonable diligence in disbursing the construction funds by obtaining an owner/contractor affidavit, checking the chancery court records for liens, and inspecting the property before disbursements. To be sure, Hancock dotted the "i's" and crossed the "t's." Yet, the chancery court rejected this argument because Hancock knew or should have known that materialmen and contractors were not being paid. Hancock may not cloak its actual knowledge of the issues that were occurring by simply doing the "proper" paperwork.
¶ 16. First, the affidavits stating that no payments were outstanding were suspect. Chad Knight signed as both owner and contractor, despite averring that the owner and contractor had no financial interest in one another in the same affidavit, and despite the evidence indicating that Chad Knight was not indeed the general contractor,
5. Whether eight percent interest was appropriate .
¶ 17. Hancock argues that an interest rate of one percent over prime would be fair in "today's financial world." Triangle argues that Hancock waived this argument by failing to make a contemporaneous objection and, in any event, that the award is fair.
¶ 18. The statute providing for interest gives the trial judge wide discretion.
6. Whether the chancery court erred in awarding attorney's fees and expenses in the amount of $106,350.48 .
¶ 19. Hancock argues that the chancery court's award of attorney's fees is unreasonable. It argues that the chancery court did not consider the appropriate factors, but that all it "required as proof was that the former governor lay his bill on the table." Triangle argues that Hancock waived any objection to the award of attorney's fees by failing to make a contemporaneous objection, and in the alternative, argues that the chancery court did not commit manifest error, as the chancellor went through the appropriate factors and found that the fees were reasonable and warranted.
¶ 20. While Hancock did not object to the reasonableness of the attorney's fees at the moment the chancellor made the award, it did vociferously object to the reasonableness of the fees at the time Triangle placed the attorney's bill into evidence. Thus, Hancock preserved this argument for appeal.
¶ 21. The chancery court has wide discretion in awarding attorney's fees.
Armstrong v. Armstrong
,
With respect to the attorney's fees, they're higher than what lawyers on the Coast get, but we are used to seeing lawyers come in here from other places that do get much higher fees.
I went through the whole first round of casinos failures and junk bonds and all that, and all the-everybody that came down here from anywhere else-they had a lot of lawyers from New York and they charge a whole lot more than you lawyers from Jackson do.
But I would assume that the-and I would think that the fees are consistent with what could be demanded by Governor Musgrove. Obviously, by calling him Governor, I know that he was a former Governor of the State of Mississippi, and as such, is able to attract good clients and able to get a lot of business that maybe someone else wouldn't.
And not just because of that, but because he's done an excellent job of presenting all of this, as has Mr. Henderson. I would say that the attorney's fees were fair and reasonable and just and should be awarded.
Now, with our domestic cases we have here, we go through something we call the McKee Factors, which is an explanation of why the attorneys should get those fees. And among the things that you-that the Court looks at is, what is the normal and reasonable fee for someone of that similar experience in that kind of a case, what is reasonable in the community where that attorney practices, that attorney's particular practice experience, and the complexity of the case, the amount of time they have to spend, you know, working on the case.
And in this one, I looked at-I guess we're getting close to 200 exhibits. There were a lot of depositions taken and an awful lot of work done to prepare this case so that it could tried [sic] in two days or two and a half days, instead of two weeks. And so I think that you all did an excellent job with that. And so I think that the attorney's fees should be awarded, and they are granted.
The exhibit that the chancellor examined was a six-page, single-spaced itemization of tasks completed regarding this case.
CONCLUSION
¶ 22. Because the chancellor did not abuse his discretion in determining that Triangle's lien took priority over Hancock's lien, and because Hancock's loan for the undeveloped land did not go into construction, this Court affirms the judgment of the chancery court. Moreover, Hancock waived its argument that the eight percent interest award was error. The chancery court likewise did not abuse its discretion in its award of attorney's fees.
¶ 23. AFFIRMED.
WALLER, C.J., RANDOPLH AND KITCHENS, P.JJ., COLEMAN AND BEAM, JJ., CONCUR. CHAMBERLIN, J., DISSENTS WITH SEPARATE WRITTEN OPINION JOINED BY MAXWELL, J. ISHEE, J., NOT PARTICIPATING.
During the time at issue in this case, Chad Knight, the owner of Knight Properties, transferred ownership of the property to Reunion of Biloxi Development, LLC, which was also owned by Chad Knight. After the events at issue, the lender, Hancock Bank, changed to Whitney Bank. This opinion will refer to the entities as Reunion and Hancock, as those are the names on the documents at issue.
The promissory note simply describes the loan as a line of credit, and does not specify that it is a construction loan.
Hancock argues that Reunion was the general contractor and Triangle was a subcontractor. Ample evidence in the record disputes this, such as the contract between Reunion and Triangle indicating that Triangle was the general contractor; statements in emails by Hancock indicating that Triangle was "the" contractor; Chad Knight's deposition testimony that Triangle was the general contractor on the project; communications between Triangle and Reunion regarding Triangle, and not Reunion, paying subcontractors; and communications between Chad Knight and Hancock indicating that Triangle had the responsibility to pay subcontractors. The chancery court specifically found that Triangle was the general contractor on the project, and under an abuse of discretion standard, we cannot find that the chancery court erred in making this factual finding, given the abundance of evidence indicating that Triangle was the general contractor.
Regardless of the veracity of Chad Knight's statement, he certainly put Hancock on notice that he had outstanding, unpaid invoices to contractors and/or materialmen. And it appears that he acknowledged to Hancock Bank that Triangle was the contractor.
Several of the witnesses to the transactions testified, as well as both sides' experts, who testified as to whether Hancock's actions were against or compliant with banking standards regarding reasonable diligence.
The dissent claims that this holding will stifle construction loans that include purchase money for land. Yet, as this Court has already noted, allowing errant construction lenders to automatically trump materialmen stifles development, as materialmen are less willing to work on credit, an arrangement that benefits everyone. Allowing a chancery court to perform its duties by finding facts and balancing equities ensures that the proper lien will receive priority under the specific facts of each case.
If a portion of a construction loan for undeveloped land automatically and always trumps materialmen, it would be antithetical to ever give materialmen priority. To be sure, the current statute regarding contractor's liens (which was not in effect at the time Triangle's lien was filed) requires that, to maintain priority, a construction mortgagee must obtain either an affidavit from the owner stating that no work has been done and no materials delivered to the property, or it must obtain "an affidavit or sworn statement from the contractor, or owner if there is no contractor, ... regarding payment for work, materials or services provided."
Certainly, it would have been more prudent for Triangle to file a lien earlier in this case. However, that does not change the fact that Hancock had knowledge of the issues of nonpayment.
The chancellor noted that "there was not one shred of evidence anywhere that the owner did any contracting. There was some-there was some indication from Compton that he shouldn't, and then there were steps taken to ensure that he didn't. But for him to say that he's the contractor and did zero contracting. It didn't show that he did anything." He noted that "the idea that Mr.-that Chad Knight was the contractor was an absolute fiction from the get-go, and that should never have been allowed. Therefore, there is no affidavit from the contractor that the-that the bills were paid."
The chancellor clearly examined the detailed bill, as he did subtract from the award the amount that Triangle expended opposing Hancock's motion for summary judgment, because he determined that the motion was not unreasonable, even though he did deny it.
Dissenting Opinion
¶ 24. Because I believe that the majority opinion goes against good policy and, more importantly, almost seventy years of precedent, I dissent.
¶ 25. As a preliminary matter, our caselaw is clear that the construction lender is entitled to priority over the materialmen in the amount that went into the construction of the project.
Riley Building Supplies, Inc. v. First Citizens Nat'l Bank
,
¶ 26. The main issue is whether the amounts used in the first draw to pay off the existing purchase loan on the land constituted funds that went into construction. The answer is yes, as confirmed by
cases dating back to 1950. This Court addressed a substantially similar case in
Virden
.
Virden
,
¶ 27. The
Virden
case is on point and dispositive. Further, other cases have addressed the issue subsequently and confirmed lien priority to include the purchase price of the property.
See
Deposit Guaranty
,
¶ 28. The logic behind these holdings is clear. We want banks to make construction loans. The bank, in general, is not going to make a construction loan unless its lien has priority. Therefore, it includes funds to pay off the existing mortgage as a part of the construction loan, thus ensuring its priority. In our case, although the bank was the same, Whitney was able to place its construction loan in a superior position by extinguishing the first mortgage. To hold otherwise would stifle such loans unless the purchase-money mortgage holder is willing to subrogate its priority.
¶ 29. The majority cites two cases which are held forth as supporting the proposition that such funds are not funds that went into construction. Alternatively, they state that it is a fact question subject to an abuse-of-discretion analysis that the chancellor got right in our case. I disagree on both counts.
¶ 30. The majority cites
Peoples Bank
,
¶ 31. The majority, likewise, submits
Wortman
,
The testimony shows that of the total sum advanced by the Loan Company, only $12,011.69 was actually used as payment for labor and materials that went into the construction of the two residences on lots Nos. 49 and 73. This sum does not include the purchase price of the two lots in the sum of $4,300.
¶ 32. The majority also deems the issue to be a finding of fact subject to an abuse-of-discretion standard. The issue of whether funds used to pay off the existing purchase loan on the land constitutes money going into the construction project is a question of law. That is not to say that there will not be circumstances where a fact finding is necessary when there is some question as to the purpose of the loan, whether the money was used to pay off the existing mortgage, diversion of the money, etc. The majority states that this dissent advocates adoption of "a bright-line legal rule that the purchase money for the land in a construction loan automatically is a cost of construction." Maj. Op. at ¶ 14. Where the issue is a question of law, my dissent merely upholds our precedent on the status of the purchase money. However, as stated above, where there are circumstances in which fact finding is necessary, my dissent does not hinder that in any way. In this case, however, the issue is one of law. All parties agree that the first draw went to pay off the balance of the existing purchase loan on the land, and no evidence has been submitted that this was anything other than the intention of the parties. Therefore, as all parties agreed to the status of the first draw, unlike the Majority states, I dissent to state that this Court should affirm the findings of the trial court but reverse the application of the law to the facts, as was done in Deposit Guaranty (and in Wortman on the issue of reasonable diligence).
¶ 33. The amount used to pay off the existing purchase loan on the land constitutes funds that went into construction. The determination of whether the monies used to pay off the balance of the existing purchase loan on the land is dispositive in that it consumes the entire amount obtained at the foreclosure sale. (The payoff was $966, 872.71 and the foreclosure purchase price was $800,000). Therefore, it is not necessary to get to a reasonable-diligence analysis.
¶ 34. For these reasons, I dissent.
MAXWELL, J., JOINS THIS OPINION.
Reference
- Full Case Name
- WHITNEY BANK F/K/A Hancock Bank, a Mississippi State Chartered Bank D/B/A Hancock Bank v. TRIANGLE CONSTRUCTION COMPANY, INC.
- Status
- Published