State Ex Rel. Utilities Commission v. North Carolina Textile Manufacturers Ass'n
State Ex Rel. Utilities Commission v. North Carolina Textile Manufacturers Ass'n
Opinion of the Court
All three of the appellants have excepted to the failure of the Commission to combine the fuel adjustment clause proceeding (Docket No. E-2, Sub 402, our No. 8110UC392) with the general rate case, and all three have assigned this as error and have brought the exceptions forward and argued them. They argue here, as they did in No. 8110UC392, that to allow an increase in rates based on increased fuel costs in an expedited proceeding under G.S. 62434(e) where there is no provision for inquiry into the reasonableness of the increased fuel costs rather than in a general rate case wherein inquires into the reasonableness of CP&L’s management practices are required constitutes reversible error. Intervenors also argue here, as they did in 8110UC392, that it was reversible error for the Commission to incorporate the increase allowed in Docket No. E-2, Sub 402 resulting from increased fuel costs in the final order in this case because to do so precluded any inquiry into the reasonableness of the increased fuel costs even in the general rate case.
The first of these positions was answered adversely to in-tervenors, and we affirm that position here without further discussion. The second position was not answered because it was not necessary for decision. See State of North Carolina ex rel Utilities Comm., et al v. Public Staff — North Carolina Utilities Comm., et al 58 N.C. App. 480, 293 S.E. 2d 880 (1982).
The Commission is bound by law to recognize the right of CP&L to avail itself of the mechanism provided by the legislature in G.S. 62434(e) and apply for an increase in rates to offset the increased cost of fuel in an expedited proceeding totally separate
G.S. 62434(e) did not roll back electric power rates. On the contrary, it authorized the Commission, after hearing, to incorporate into the basic rates of the utility, chargeable on and after 1 September 1975, an increase determined by the then cost of coal
Id. at 466. We find no error in this portion of the Commission’s order.
The Utilities Commission was, of course, created by the General Assembly. In fixing rates to be charged by utilities, it exercises a legislative function and has no authority other than that given to it by the Legislature. Utilities Comm. v. Edmisten, supra, and cases there cited. G.S. 62430(a) places upon the Com
The burden of showing the impropriety of rates established by the Commission lies with the party alleging such error. See Utilities Commission v. Light Co. and Utilities Commission v. Carolinas Committee, 250 N.C. 421, 109 S.E. 2d 253 (1959). The rate order of the Commission will be affirmed if upon consideration of the whole record we find that the Commission’s decision is not affected by error of law and the facts found by the Commission are supported by competent, material and substantial evidence, taking into account any contradictory evidence or evidence from which conflicting inferences could be drawn. See Utilities Comm. v. Springdale Estates Assoc., 46 N.C. App. 488, 265 S.E. 2d 647 (1980).
Utilities Commission v. Duke Power Co., 305 N.C. 1, 10, 287 S.E. 2d 786, 792 (1982).
Adhering to those fundamental legal principles in applying the statutory provisions to the issues brought forward in this appeal, we are unable to find reversible error.
The Commission included the Roxboro Unit No. 4 at $123,565,000. CP&L’s evidence placed cost of construction at $204,619,000. The Public Staffs witness Lam recommended that the unit be valued at $194,447,880. His value was reduced because, in his opinion, if the higher value were used, the plant should be able to produce 720 MW reliably, whereas the evidence is that it is a 650 MW plant. Appellant TMA concedes in its brief
As is usually the case in proceedings of this type, the evidence is, of course, voluminous. The record and briefs comprise more than 700 pages. Our examination of the evidence leads us to the conclusion that a real effort was made properly to match all items in the cost of service study. There was no specific evidence with respect to how much, if any, the revenues of the Company would be increased by reason of inclusion of Roxboro Unit No. 4. There was testimony that the plant would not produce new customers. While Intervenor’s expert witnesses seemed to agree that matching should apply to Roxboro No. 4, there was simply no specific evidence with respect to figures to rebut the evidence of CP&L. With respect to the decreased fuel cost, obviously under the statutory scheme of rate setting in effect at the time, any savings in fuel cost would be taken into account in a fuel cost adjustment proceeding.
Kudzu and TMA contend that the Commission made insufficient findings with respect to the Construction Work in Progress (CWIP) included in rate base. TMA argues, in the alternative, that if CWIP was properly included in rate base in this case, the 1977 CWIP Amendment [G.S. 62-133(b)(l) and (c) ] is unconstitutional because so lacking in standards as to be in excess of the limitations on legislative power contained in the Due Process Clause of the Fourteenth Amendment to the Constitution of the United States and Article I, Section 19 of the Constitution of North Carolina.
With respect to the first argument (Kudzu assignments of error 1, 2, 3, 4, 5 and 6 and TMA’s assignment of error 2), appellants contend that the 1977 revision to G.S. 62-133 requires detailed,
G.S. 62-133(b)(l) provides that, in fixing rates which will be fair both to the public utility and the consumer, the Commission shall
Ascertain the reasonable original cost of the public utility’s property used and useful, or to be used and useful within a reasonable time after the test period, in providing the service rendered to the public within this State, less that portion of the cost which has been consumed by previous use recovered by depreciation expense plus the reasonable original cost of investment in plant under construction (construction work in progress). In ascertaining the cost of the public utility’s property, construction work in progress as of the effective date of this subsection shall be excluded until such plant comes into service but reasonable and prudent expenditures for construction work in progress after the effective date of this subsection shall be included subject to the provisions of sub-paragraph (b)(5) of this section.
G.S. 62433(c) provides:
The original cost of the public utility’s property, including its construction work in progress, shall be determined as of the end of the test period used in the hearing and the probable future revenues and expenses shall be based on the plant and equipment in operation at that time. The test period shall consist of 12 months’ historical operating experience prior to the date the rates are proposed to become effective, but the Commission shall consider such relevant, material and competent evidence as may be offered by any party to the proceeding tending to show actual changes in costs, revenues or the cost of the public utility’s property used and useful, or to be used and useful within a reasonable time after the test period, in providing the service rendered to the public within this State, including its construction work in progress, which is based upon circumstances and events occurring up to the time the hearing is closed.
There can be no question but the Legislature mandates that the only expenditures for CWIP which can properly be included in rate base are reasonable expenditures. The Commission so found in Finding No. 8:
That the reasonable original cost of CP&L’s property used and useful, or to be used and useful within a reasonable time after the test period, in providing the service rendered to the public within this State, less that portion of the cost which has been consumed by previous use recovered by depreciation expense, plus the reasonable original cost of investment in plant under construction (construction work in progress or CWIP) is $1,544,143,000.
and again in Finding No. 10:
That CP&L’s reasonable original cost rate base is $1,630,739,000. This amount consists of net utility plant in service and construction work in progress of $1,544,143,000, plus a reasonable allowance for working capital and deferred debits and credits of $86,596,000.
Our review of the record leads us to the conclusion that the finding is amply supported by the evidence. Without going into great detail we simply note a few examples which we think will suffice to demonstrate that the finding is supported by the evidence. Mr. Smith, on cross examination by TMA, testified from Exhibit H, filed with the Commission, with respect to the $213,792,201 reflected in the exhibit as CWIP. He testified further that an inventory by groups of property could be supplied. Counsel for TMA responded that he wasn’t asking that that information be supplied. There was testimony from both Mr. Smith and Mr. Bradshaw that the Public Staff of the Utilities Commission had audited the amount included. There was testimony the
Where the property has been purchased from a stranger, ordinarily the price actually paid by the utility would be considered its reasonable cost, though it would not necessarily be so. Even in such a case the Commission may find the management of the utility acted improvidently or carelessly and paid a price greater than reasonable.
Id. at 12 N.C. App. at 606, 189 S.E. 2d at 531. See also West Ohio Gas Co. v. Ohio Public Utilities Commission, 294 U.S. 63, 55 S.Ct. 316, 79 L.Ed. 761 (1935).
There has been no contention here that the Company acted improvidently or carelessly. Nor does the record before us reflect
Nor do we find merit in the argument that the statute is unconstitutional. In Utilities Comm. v. Edmisten, Attorney General, 294 N.C. 598, 610, 242 S.E. 2d 862, 870 (1978), the Court said:
Stimulation of the economy is an essential public and governmental purpose and the manner in which this purpose is to be accomplished is, within constitutional limits, exclusively a legislative decision. Mitchell v. North Carolina Industrial Development Financing Authority, 273 N.C. 137, 159 S.E. 2d 745 (1968). The authority to set rates to be charged by a public utility for its services rests in the Legislature and is delegated by it to the Utilities Commission under sufficient rules and standards to guide the Commission in exercising this power. Utilities Commission v. State, 239 N.C. 333, 80 S.E. 2d 133 (1954).
See also Utilities Comm. v. Intervenor Residents, 52 N.C. App. 222, 278 S.E. 2d 761, rev’d on other grounds, 305 N.C. 62 (1981). The 1977 amendment including CWIP in rate base did not lessen the rules and standards. Reasonableness remains the standard.
Appellant Public Staff argues that the Commission erred by failing to adjust properly CP&L’s accumulated deferred federal income tax balance in light of the decrease in the federal corporate income tax rate. The tax rate was decreased from 48 percent to 46 percent after the end of the 12-month test period but prior to the hearings in this matter. The Public Staff contends that CP&L’s continuation of its use of a normalization policy in which future taxes will be credited for book purposes at the 48 percent rate, even though a different rate may be in effect at that time, is discriminatory because the ratepayers who benefit from the reduction in tax rate may not be the ratepayers who existed at the time of the deferral. The Public Staff recommends adoption
Flow-through and normalization are alternative ratemaking policies for determining the cost component of a regulated utility’s cost of service. Under flow-through, ratepayers realize the tax benefits of expenses at the time those expenses are used as tax deductions by the utility. Normalization defers this tax benefit until the expense is recovered through the rates.
The Public Staff presented the expert testimony of two accountants in support of their recommendation that the Commission employ flow-through. Their testimony indicated that CP&L will continue to receive a tax reduction every year for items which are capitalized for book purposes but are expensed for tax purposes, resulting in an ongoing tax savings. Normalization results in higher rates to consumers than would exist under flow-through. The Public Staff argued that the tax effect of an expense should be recognized in the same period as the expense itself to achieve equity between present and future ratepayers.
CP&L’s accounting experts rebutted this testimony by stating that over the life of a transaction, the total amount of the transaction recognized for ratemaking will equal the total amount recognized for tax purposes. CP&L argued that over the life of an asset which generates deferrals, the total revenue requirement is greater under flow-through than under normalization. When viewed on a present-worth basis, the revenue requirement between normalization and flow-through is virtually equal before any allowance is made for the adverse impact flow-through has on such factors as debt coverage and cash flow. Since plant items which generate deferrals are used to provide service over a useful life period, normalization properly allocates the annual benefit of the deferral to the consumer using the service which created the deferral. CP&L witness Utley testified that Congress, the accounting profession and many federal administrative agencies endorse normalization accounting.
After hearing the testimony on this issue, the Commission found as a fact and concluded as a matter of law that normalization of the income tax effect of certain expenses is proper. The Commission found that the arguments in favor of normalization “clearly outweighed the arguments of the Public Staff in support
(1) Normalization as opposed to flow-through results in a better matching of revenues and costs.
(2) Normalization as opposed to flow-through results in the most equitable allocation of costs and benefits among present and future customers.
(3) Normalization as opposed to flow-through materially improves the Company’s financial position with respect to cash flow.
(4) Normalization as opposed to flow-through materially improves key financial ratios (e.g., fixed charge coverage rates, effective tax rates, etc.) used by the investment community in determining the rental rate its members will charge for the use of its capital — the more favorable the ratios the lower the capital costs.
(5) Normalization as opposed to flow-through results in more informative disclosure in financial reporting with respect to an entity’s potential future income tax liability.
(6) Normalization as opposed to flow-through when limiting one’s considerations solely to a present worth analysis (i.e., without considering advantages of normalization), when based upon realistic assumptions, results in economic advantages to both the Company and its customers.
Based upon our review of the record, we hold that the findings of fact made by the Commission on this issue (finding of fact No. 6) was supported by competent, material and substantial evidence and is, therefore, conclusive and binding on this Court. Utilities Comm. v. Telephone Co., supra. A finding of fact cannot be reversed or modified by a reviewing court merely because the court would have reached a different finding upon the evidence. Id. We, therefore, overrule this assignment of error.
CP&L recommended that a “peak and average” methodology be adopted, and this was accepted by the Commission, as its final order reflects. Appellants TMA and Kudzu assign as error the Commission’s adoption of the “peak and average” methodology for the allocation of production facility costs. The allocation proc
In its order the Commission described the extensive testimony of the expert witnesses concerning demand allocation and evaluated the advantages and disadvantages of each proposed method. While recognizing that each method had merit, the Commission concluded that “the peak and average method for making cost of service allocation is the most appropriate method for use in this proceeding.” Based upon our review of the testimony contained in the record, we find that the finding of fact on this issue is fully supported by competent, material and substantial evidence and is, therefore, conclusive. Utilities Comm. v. Telephone Co., supra.
The peak and average method separates demand-related costs to retail customers into two categories: one allocated according to demand at the time of the system peak and one allocated on the basis of respective cost responsibilities for the average annual demand as determined by the system load factor. These two portions reflect peak and average production costs and are based upon actual system load conditions. CP&L’s expert witness Nevil stated that this method promotes cost-based rates by better matching cost of production plant with each jurisdiction’s or class of customers’ use of specific types of plant. The peak and base method recommended by the Public Staff is very similar to the peak and average method. The only difference is the portion of
TMA advocated the use of a summer-winter average peak demand method in which the production costs are allocated in proportion to the usage of each class of customers at the time of the seasonal peaks. The Commission stated that this proposed method differs little from the traditional one-hour summer coincident peak formula and suffers some of the same weaknesses. Both methods assign a lesser portion of demand costs to general service customers than do either peak and average or peak and base methods.
The Commission concluded that:
. . . the CP [coincident peak] allocation method no longer properly allocates demand costs to the jurisdictions or customer classes creating the need for the type of generating facilities actually being constructed today. There is little difference between the Company’s P&A [peak and average] and the Public Staffs P&B [peak and base] method but, conceptually, the P&A method better recognizes the use of all base load production facilities through the use of the system load factor to determine the portion of the investment to be allocated by average demand, as opposed to the P&B method which uses the relationship of minimum weekday demands to the coincident peak demand. The minimum weekday demand is of short duration and is much less than the total base load capacity available, whereas the load factor better reflects the average use of production facilities — the use for which they were constructed — and therefore is an appropriate method of allocating the majority of the plant costs.
Appellants argue that the peak and average method unfairly benefits customers with lower load factors and penalizes customers with higher load factors. G.S. 62-140 prohibits public utilities from making or granting any unreasonable preference or advantage to any customer and from establishing “any unreasonable difference as to rates or services either as between localities or as between classes of service.” Utilities Com. v. Mead Corp., 238 N.C. 451, 78 S.E. 2d 290 (1953).
The evidence indicates that the use of the peak and average method would increase the cost of electricity for high load factor
The order of the Commission is, in all respects, affirmed.
. Intervenor Federal Government agencies, not an appellant in this appeal, supported continuation of the one-hour summer coincident peak method.
Dissenting Opinion
dissenting in part.
It appears from the order that the Commission derived CP&L’s cost of fuel in this general rate case by using the fuel cost found reasonable by the Commission in a separate fuel clause proceeding. The Commission accomplished this result by consolidating the record in Docket No. E-2, Sub. 402, the fuel clause proceeding, into the record of this case. As we held in Utilities Comm. v. Power Co., 48 N.C. App. 453, 269 S.E. 2d 657 (1980), cert. denied, 301 N.C. 531, 273 S.E. 2d 462 (1980), a fuel clause proceeding is an expedited one where the Commission may consider only the actual cost of fuel used. In that same opinion, we emphasized that in a general rate case, it is not only appropriate but necessary for the Commission to consider overall system efficiency in deriving the reasonable cost of fuel during the test year. The Commission used the fuel clause short-cut record to find the reasonable cost of fuel in this general rate case. In doing so, the Commission erred. The Commission’s findings of fact as to
Reference
- Full Case Name
- STATE OF NORTH CAROLINA, Ex Rel. UTILITIES COMMISSION; And CAROLINA POWER AND LIGHT COMPANY (Applicant); RUFUS L. EDMISTEN, Attorney General; EXECUTIVE AGENCIES OF THE UNITED STATES GOVERNMENT and UNION CARBIDE CORPORATION v. NORTH CAROLINA TEXTILE MANUFACTURERS ASSOCIATION, INC.; THE PUBLIC STAFF-NORTH CAROLINA UTILITIES COMMISSION; And KUDZU ALLIANCE
- Cited By
- 6 cases
- Status
- Published