Morton v. Washington Light & Water Co.
Opinion of the Court
Tbe principles announced in Gorrell v. Water Co., 124 N. C., 328, establish tbe liability of tbe defendant to tbe plaintiffs upon
It may be conceded, as contended by the defendant, that the weight of authority, measured by number, is against the decision in the Gorrell case, but this was known and considered at the time of its rendition, and since then, instead of receding from the position then taken, the doctrine has been affirmed in Fisher v. Water Co., 128 N. C., 375; Lacy v. Webb, 130 N. C., 546; Gastonia v. Engineering Co., 131 N. C., 368; Wadsworth v. Concord, 133 N. C., 594; Vorhees v. Porter, 134 N. C., 602; Kernodle v. Tel. Co., 141 N. C., 445; Holmes v. Tel. Co., 143 N. C., 393; Wood v. Kincaid, 144 N. C., 395; Clark v. Bonsal, 157 N. C., 275; Brady v. Randleman, 159 N. C., 436, and in Jones v. Water Co., 135 N. C., 554.
In the last case the contract was similar to the one now before us, and the Court said, upon the right'to sue: “There can be nó real contention that the plaintiff, a citizen and taxpayer, and one of the beneficiaries in the purview of this contract, cannot prosecute this action. He is the real party in interest. He is taxed with payment of his pro rata of the annual rental. The town cannot maintain this action for the loss sustained by him by reason of the defendant’s failure to perform the provisions of the contract above recited. For this injury the plaintiff alone can sue. This point was discussed and settled in Gorrell v. Water Co., 124 N. C., 328 (70 Am. St. Rep., 598; 46 L. R. A., 513), which has been followed in Fisher v. Water Co., 128 N. C., 375, and cited and approved in Lacy v. Webb, 130 N. C., 546, and Gastonia v. Engineering Co., 131 N. C., 368, in which last the doctrine is elaborated. The samé principle had been often affirmed prior to Gorrell's case, towit, that “the beneficiary of a contract, though not a party to it nor expressly named therein, can maintain an action for a breach of such contract causing injury to him, if the contract was made for his benefit.”
It also appears that the case has been followed in Mugge v. Tampa Water-works, 52 Fla., 371, and Springfield Ins. Co. v. Graves County Water Co., 120 Ky., 40; and in Guardian Trust Co. v. Fisher, 200 H. S., 57, the Court, affirming the principle, says: “It is true that a company contracting with a city to construct water-works and supply water may fail to commence performance. Its contractual obligations are then with the city only, which may recover damages, but merely for breach of contract. There would be no tort, no negligence, in the total failure on the part of the company. It may also be true that no citizen is a party to such a contract, and has no contractual or other right to recover for
Another reason for refusing to sustain the position-of the defendant is that it entered into the contract with the city of Washington in 1901, two years after the Gorrell case was decided, and as all laws relating to the subject-matter of a contract enter into and form a part of it as if expressly referred to or incorporated in its terms (Lehigh Water Co. v. Easton, 121 U. S., 391; Wooten v. Hill, 98 N. C., 53), it was within the contemplation of the parties at the time the contract was made that the defendant would be liable to the citizen for loss by fire caused by its negligent failure to perform the terms of the contract, as held in the Gorrell case, and to hold otherwise now would relieve the defendant of a responsibility which it knowingly assumed:
The other exceptions relied on by the defendant will be considered in the order in which they are discussed in the briefs.
(1) The amendment to the complaint, which was filed by permission of the court on the day before the trial, only added an additional item of damage, and did not change the issues raised by the pleadings, and it does not appear in the record that the time allowed the defendant to prepare its evidence was not ample.
The rule as to a continuance when new parties are made or amendments allowed is correctly stated in Watson v. R. R., 164 N. C., 180, where the Court says: “If new parties are made or amendments allowed, which change the issues, and a party is not prepared with his evidence to meet the changed conditions, he is entitled to a continuance as a matter of right (Dobson v. R. R., 129 N. C., 291); but ordinarily the ruling of the judge upon a motion for continuance is a matter of discretion, and not reviewable, and in this case it appears that there was no change in the pleadings or issues, and no suggestion that it would be more prejudicial to the defendant to try at that time than at any other.”
It does not appear that the defendant has been prejudiced, or that the discretion vested in the trial judge has been abused, and the exception to the refusal to continue must therefore be overruled.
The plaintiffs further introduced evidence, the defendant objecting thereto, that the defendant had failed to supply water according to its contract at other fires before the fire which destroyed the property of the plaintiffs.
This evidence does not fall under the condemnation of the rule which forbids the proof of other negligent acts as evidence of the negligence complained of, and was competent upon the question as to the condition and capacity of the plant at the time of the fire.
There were no exceptional circumstances connected with the other fires, and, so far as the evidence disclosed, the plant was in.its usual condition.
If so, and the capacity had decreased, as the plaintiffs contend, the fact that it did not furnish water according to the contract at other fires would be some proof that it could not do so at the time of the fire complained of. The evidence comes within the principle of the case of Blevins v. Cotton Mills, 150 N. C., 493.
(3) A witness for the plaintiff was asked a question by the defendant on-cross-examination, which the court refused to permit the witness to answer, but as there is nothing to indicate what the answer of the witness would have been, the exception to the action of the court cannot be considered. Wallace v. Barlow, 165 N. C., 676.
(4) The defendant introduced its president and superintendent, each of whom testified substantially that the plant of the defendant was at all times properly equipped and maintained, and the plaintiffs were permitted to prove upon cross-examination, and by other witnesses, declarations of the president and superintendent, made after the fire, tending to contradict their testimony.
This does not come within the principle excluding the declarations of an agent as to a past occurrence, and the evidence was properly admitted. The rule and the exception are applied in Pate v. Steamboat Co., 148 N. C., 573, as follows: “Of course, the declarations of the boat hand, made after the occurrence, are incompetent for the purpose of proving the dangerous condition of the bateau. Southerland v. R. R., 106 N. C., 100. But, having been examined by the defendant as its witness as to the condition of the bateau, it was competent to impeach or contradict his evidence upon that point by his declarations on that subject to Glover. To lay the foundation for offering such impeaching evidence, it was proper to ask the witness on cross-examination the question objected to.”
Authority can be found in support of the general proposition that the tax list is inadmissible upon the question of value, but in none of the cases was the fact present as in this, that the party against whom it was offered had alleged that the tax list showed the true value.
If the plaintiff had made a declaration as to value on the streets, no one would question the right to offer this declaration against him, nor would the right to look at the tax list to ascertain the value be denied if it had been attached to the complaint as an exhibit.
If so, it can make no difference, as to the competency of the evidence, that the true value appeared on the tax list in the office of the sheriff or of the register of deeds instead of attaching the list to his complaint, and in our opinion the evidence ought to have been received.
This entitles the defendant to a new trial, but it is restricted to the issue of damages.
Partial new trial.
Note to opinion of the Court by Mb. Justice Aulen, showing precedents to sustain the right of the plaintiff to recover under the contract made between the water company and the town:
Gorrell v. Water Co., 124 N. C., 328; Fisher v. Water Co., 128 N. C., 375; Lacy v. Webb, 130 N. C., 546; Gastonia v. Eng. Co., 131 N. C., 368; Wadsworth v. Concord, 133 N. C., 594; Voorhees v. Porter, 134 N. C., 602; Kernodle v. Tel. Co., 141 N. C., 445; Holmes v. Tel. Co., 143 N. C., 393; Wood v. Kincaid, 144 N. C., 395; Clark v. Bonsal, 157 N. C., 275; Brady v. Randleman, 159 N. C., 436; Jones v. Water Co., 135 N. C., 554; Mugge v. Tampa Water-works, 52 Fla., 371; Springfield Ins. Co. v. Graves County Water Co., 120 Ky., 40; Guardian Trust Co. v. Easton, 121 U. S., 391; Wooten v. Hill, 98 N. C., 53.
Concurring Opinion
concurring in result: I recognize the fact that the overwhelming weight of authority, including that of the Supreme Court of the United States, is against the decisions of this Court in the Gorrell,
Whether those eases were correctly decided or not, they were the accepted law of this State at that time, and upon well established principles entered into and formed a part of the contract under which the defendant operated, unless there is something to be found in the contract excluding such hypothesis.
In referring to this well settled rule of law, Mr. Justice Walker says,, in Hill v. R. R., 143 N. C., 576: “We adopted that rule in Long v. Walker, 105 N. C., 109, where it was held that a former adjudication of the Court in construing a statute or the organic law should stand, when it has been recognized for years, and in such case the principle settled or the meaning given to the statute becomes a rule for guidance in making-contracts, and also a rule of property, and that it should not be disturbed, even though the conclusion reached may not be satisfactory to the Court at the time the same matter is again presented.”
TJnder the decisions of this Court, the contract was made by the city for the benefit of its citizens, and they had a right to sue on it for a breach thereof.
It was perfectly competent for the defendant to have inserted a clause in the contract excluding such right or providing that the defendant would indemnify and hold harmless the city, or that the city only should sue.
It could easily have been made to - appear from the contract, if such was the agreement of the parties, that the defendant was dealing exclusively with the city, and was accountable only to it.
Taking this contract as a whole, there is nothing in it from which we can infer that tlie city alone must sue for its breach.
Dissenting Opinion
dissenting: The quotation from the contract between the town of "Washington and S. S. Spruks, predecessor of defendant, which appears in the opinion of the Court, was taken from the first preamble of the agreement, and is of no special significance, when viewed in the light of subsequent provisions, as it should be (Gudger v. White, 141 N. C., 507; Triplett v. Williams, 149 N. C., 394; Beacom v. Amos, 161 N. C., 357), and considered with reference to the principles of law recognized and applied by all the authorities. I have said all the authorities, because-it will be found, upon the most cursory examination, that the cases to which the Court refers in its opinion do not present the facts we have in this case, but those which are essentially different, as I will show. It is well, in the beginning of the discussion, to understand pre
1. “The commissioners for the town of Washington- agree to use the ' said hydrants for the extinguishment of fires only, except as hereinafter provided. It is expressly agreed that if said rent be not paid when due as above specified, then the water supply may be cut off without any liability to any one from said company.”
2. “A constant water pressure equal to 50 pounds per -inch for ordinary service shall be maintained, which upon the occasion of fires shall, if necessary, be increased by means of suitable pumps to 75 pounds per inch.” (In order to meet this requirement, a pump house, with machinery, fixtures, and power sufficient to supply 360,000 gallons of water per day and stand-pipe with a capacity of 50,000 are agreed to be maintained.)
3. “Water from the fire hydrants may be used for the extinguishment of fire and for the necessary fire practice only: Provided, that not more than two companies be allowed to practice on the same day without permission from the water company; and Provided further, that said practice shall not be oftener than once in each week, and not more than two hydrants shall be open at one time. The fire hydrants rented by the town of Washington shall constantly furnish effectual fire streams without the aid of portable engines. The said fire hydrants shall be kept constantly supplied with water for fire service, and shall be maintained in effectual working order.”
5. The owner, after the system shall be completed and in operation, “shall-not suffer the suspension of the supply of water, either for fire or domestic purposes, unless the same shall be caused by accident or cause beyond his control; and in ease of accident or other cause, said Spruks shall forthwith proceed with all possible diligence to repair and put the same in successful operation; and if sáid Spruks, his associates or assigns, suspend or fail to make such repairs as herein required, then the rights and privileges granted hereby shall be forfeited.”
6. The contract was evidenced by an ordinance of the town, which was accepted by S. S. Spruks, and with, reference thereto it is provided as follows: “This ordinance shall become binding upon the town of Washington in the event that the said S. S. Spruks, his associates or assigns, shall, within thirty days after the passage and publication of this ordinance, file with the town clerk of the said town of Washington its written
■ acceptance of the terms, obligations, and conditions of this ordinance, and upon the filing within thirty days thereafter of’ a bond, to be approved by the board of commissioners for the town of Washington, in the penal sum of $2,500, conditioned for the faithful performance of the erection of said plant as is herein provided for, and thereupon this ordinance shall constitute the contract, and shall be the measure of the rights and liabilities of the town of Washington and of the said S. S. Spruks, his associates and assigns.”
There is a provision in the contract that if S. S. Spruks or his assigns “cannot get a supply of water, such as is required by section 2 of this ordinance, at a reasonable expense, (he) shall have the right to surrender the franchise and the ordinance shall be void.”
Section 2 refers to the pure quality of the water for domestic purposes.
The plaintiffs allege that the alleged cause, of action accrued to them by reason of the defendant’s .negligent failure to furnish sufficient water and pressure at the hydrants.
In view of the above provisions of the contract now under consideration, it may be well to state, at the outset, that it bears no legal resemblance to those which were construed in Gorrell v. Water Co., 124 N. C., 328; Fisher v. Water Co., 128 N. C., 375; Mugge v. Tampa Water-works, 52 Fla., 371; Springfield Ins. Co. v. Graves County Water Co., 120 Ky., 40, and Guardian Trust Co. v. Fisher, 200 U. S., 57, the cases mainly
But a very luminous discussion of the question will be found in a ease recently decided by the Supreme Court-óf the United States, German Alliance Ins. Co. v. Home Water Co., 226 U. S., 220 (2 Dec., 1912) in which the opinion was written by Mr. Justice Lamar. It is of great practical value, as the matter is considered from the viewpoint of the difference betwéen the contracts passed upon in the Paducah, Gorrell, and Mugge cases, and those upon which a large number of the cases were decided. It also shows conclusively that the ease of Guardian Trust Co. v. Foster, 200 U. S., 571, opinion by Mr. Justice Brewer, which is much relied on in the opinion of the Court in the case at bar, is really no authority for the position now taken. The question in the Fisher case related entirely to the character of the cause of action therein, whether in contract or tort, and the Court simply followed the construction of our statute upon the subject by this Court. Referring to the Fisher case, the Court in G. A. Insurance Co. v. Home Water Co. says: “It was urged, among other things, by the bondholders that the suit in the State court was really for breach of contract, and that entering the judgment as for a tort did not change the nature of the action so as to entitle the plaintiff to the benefits of the North Carolina statute. It was that question alone, as to the character of the suit and judgment, which was before this Court. What was said in the opinion must be limited, under well-known rules, to the facts and issues involved in the particular record under investigation. The Fisher case could not have decided the primary question as to the right of the taxpayer to sue, for that issue had been finally settled by the State court. It raised no Federal question and was not in issue on the hearing in this Court. Neither did the Fisher case overrule the principle announced in National Bank v. Grand Lodge, 98 U. S., 123, 124, that a third person cannot sue for the breach of a contract to which he is a stranger unless he is in privity with the parties and is therein given a direct interest.” That disposes of the Fisher case (200 U. S., 57) as an authority against my view. Justice Lamar, in the later case of G. A. Ins. Co. v. Home Water Co., just cited by me, shows conclusively that the doctrine upon which the.plaintiff relies cannot be sustained. He says, at p. 230: “Before a stranger can avail himself of the exceptional privilege of suing for a breach of an. agreement to which he is not a party, he must at least show that it was intended for his direct benefit. For, as said by this Court, speaking of the right of bondholders to sue a third party who had made an agreement with the obligor to discharge the bonds, they ‘may have had an indirect interest in the performance of the undertakings; but that is a very different thing from
In Jones v. Water Co., 135 N. C., 553, the plaintiff appealed and a new trial was given because of an erroneous charge, of the judge in regard
Every cáse should be tried by the touchstone of its own facts, and there should be no other criterion by which to test the correctness of its decision and its scope and influence as a precedent. Expressed in homely phrase, “Every tub must stand upon its own bottom.” The contract in this case, when read as a whole and without severing any particular clause from its context, evidences a purpose on 'the part of the water company to avoid liability for such damages as are now claimed, and to so word the agreement as to confine the remedy for a breach to a forfeiture of the rents, or, if continued for the specified time of thirty days, to a forfeiture of all rights under the contract, or to restrict any damages for a breach to those recoverable by the town alone. The parties undoubtedly had the right to make such a contract, and it should be construed as they have written it, and the case should not be governed by precedents based upon an entirely different state of facts. We are not at liberty to make a contract for the parties, but can only enforce the one they have made for themselves.
In Ancrum v. Water Co., 82 S. C., 284, a case analogous to this one in its facts, the Court, by Justice Woods, in a well considered opinion, held: The obligations of a water company to a citizen of a city with which it has contracted to furnish water for fire protection for damage sustained by negligent failure of the company to supply sufficient water pressure during a fire are limited by the contract between the city and the company. The contract between the city of Camden and the water company, it was further held, did not create any liability on the part of the latter to an individual,.who was an inhabitant and taxpayer of the city, for a loss sustained by fire; which would have been extinguished if the water company had not neglected'to comply with its contract in keeping the proper pressure on its water pipes. The Court also stated that when the city employed the water company to construct and operate the water-works, instead of doing so itself, under the permission given in its
The cases in at least thirty out of thirty-four States of the Union which have passed upon the question hold that the water company is not liable:
1. Because there is no privity of contract where there is no obligation, except the general one to furnish water and pressure for the extinguish-, ment of fires, and 'no agreement of the comp'any to be directly responsible to the citizen for losses by failure to do so.
2. That the municipality is under no legal duty to contract for a supply of water for such a purpose, unless it is imposed by its charter, and therefore no liability to an inhabitant could arise out of such a contract when there is such a claim.
3. That the town has no power to make any such contract in behalf of its citizens, except collectively and in discharge of its public duty, as it is not within its corporate capacity to do so.
4. That where there is no special provision, as in the Gorrell, Paducah, and Mugge cases, creating a liability to each inhabitant, who suffers a loss from fire, the contract is restricted, in its operation, to damages suffered by the municipality itself, on account of a breach to supply the necessary quantity and pressure to protect property. “The violation of a contract entered into with the public, .the breach being by mere omission or nonfeasance, is no tort, direct or indirect, to private property of an individual, though he is a member of the community and a taxpayer to the Government. *We are unable to see how a contractor with the city to supply water to extinguish fires commits any tort by failure to comply with his undertaking, unless to the contract relation there is super-added a legal command by statute or express law.” Fowler v. A. C. Water-works, 83 Ga., 219.
There are other reasons assigned, but those stated are the principal ones. All will be found in the authorities cited in the note to this opinion, and especially in G. A. Ins. Co. v. Home Water Co., 226 U. S., 220; Hone v. P. I. Water Co., 104 Me., 217; Holloway v. M. G. and Water Co., 64 S. E. (Ga.), 330; Ancrum v. Water Co., 82 S. C., 284; Hull v. Passaic, 83 N. J. L., 771; Fitch v. S. Water Co., 139 Ind., 214, and Davis v. C. Water-works, 54 Ia., 57, where there is an elaborate discussion of the question, with a collation of all the cases, many of which have not been cited herein.
In view of the above reasons and the overwhelming weight of authority in the Federal and State courts supporting the view herein expressed, I am compelled, regretfully, to differ with my brethren of the majority, and to dissent from the opinion of the Court and its judgment, as I think there should be a nonsuit, instead of a new trial.
Note of Precedents Directly Sustaining Dissenting Opinion. — Boston Safe Dep. Co. v. Salem Water Co., (C. C.) 94 Fed., 238; Metropolitan Trust Co. v. Topeka Water Co., (C. C.) 132 Fed., 702; Lovejoy v. Bessemer Water-works Co., 146 Ala., 374; Collier v. Newport Water, L. and P. Co., 100 Ark., 47; Town of Uriah v. Uriah Water Co., 142 Cal., 173; Nickerson v. Bridgeport Hydraulic Co., 46 Conn., 24; Holloway v. Macon Gaslight and Water Co., (Ga.) 64 S. E., 330; Bush v. Artesian, etc., Water Co., 4 Idaho, 618; Davis v. Clinton Water-works Co., 54 Ia., 57; Becker v. Keokuk, 79 Ia., 419; Peck, v. Sterling Water Co., 118 Ill. App., 533; Rostan v. Chicago, 163 Ill. App., 63; Fitch v. Seymour Water Co., 139 Ind., 214; Mott v. Cherryvale Water and Mfg. Co., (48 Kan.) 15 L. R. A., 257; Allen & Curry Mfg. Co. v. Shreveport Water Co., 113 La. Ann., 1091; Hand v. Brookline, 126 Mass., 324; Hone v. Presque Isle Water Co., 104 Me., 217; Wilkinson v. Light, Heat and Water Co., 78 Miss., 389; Howsmon v. Trenton Water Co., 119 Mo., 304; Metz v. Cape Girardeau Water-works Co., 202 Mo., 324; Eaton v. Fairbury Water-works Co., 37 Neb., 546; Ferris v. Carson Water Co., 16 Nev., 44; Hull v. Passaic, 83 N. J. L., 771; Bush v. Great S. Bay Water Co., 82 App. Div. (N. Y.), 427; Wainwright v. Queens, 78 Hun. (N. Y.), 146; Akron Waterworks Co. v. Brownless, 10 Ohio Cir. Ct. R., 620; Blunk v. Dennison, 71 Ohio St., 250; Lutz v. Tahlequah Water Co., (Okla.) 36 L. R. A. (N. S.), 568; Thompson v. Springfield Water Co., 215 Pa., 275; Ancrum v. Camden Water, Light and Ice Co., 82 S. C., 284; Cooke v. Paris Mt. Water Co., (S. C.) 64 S. E., 157; Foster v. Lookout Water Co., (Tenn.) 3 Lea, 42; House v. Houston Water-works Co., 88 Tex., 233; Wilkins v. Rutland, 61 Vt, 336; Nichol v. Huntington Water Co., 53 W. Va., 348; Britton v. Green Bay Water-works Co., 81 Wis., 48; Kron v. Antigo, (Wis.) 140 N. W., 41. The cases cited in the note to the Court’s opinion are easily distinguishable from this case.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.