Gutschow v. Washington County
Gutschow v. Washington County
Opinion of the Court
This was an action brought by a taxpayer of the county of Washington, who was the owner of lands ad
His first argument is that the only power given to the board to relet a contract for the construction of the ditch is given by section 20, article I, chapter 89, Compiled Statutes 1903 (Ann. St. 5519), which provides that “any contract not completed within the time specified, shall be reestimated and relet to the lowest responsible bidder, but not for a sum greater than the estimate, nor a second time to the same party”; that a contract which
The next point urged is that, since there was only one bidder, the contract was not let to the “lowest responsible bidder.” State v. Board of County Commissioners, 13 Neb. 57, was a mandamus proceeding brought to compel the board of county commissioners of York county to <mter into a contract with the relator for the purchase of certain stationéry, on the ground that he was the loAvest competent bidder therefor. It appears that two bids were filed with the board, but one of the bids was filed out of time and was not in accordance with the advertisement. This left the relator the only bidder. The court held that he was the lowest competent bidder and the writ was awarded as prayed. See, also, Baum v. Sweeny, 5 Wash. 712, 32 Pac. 778. It may often happen from the character of the work to be performed, or of the supplies to be furnished, that in a given locality one person alone may have the facilities and appliances necessary to fulfill the terms of the contract. It is a matter of common knowledge that extensive, excavations, such as canals, ditches, or railway cuts, may be carried on much more cheaply and expedi
The third objection made is that the contract exceeds the estimated cost of construction, and that the bid did not comply Avith the terms of the notice Avhich called for bids for the construction of the ditch by working sections. The reestimate made under the direction of the board showed no change from the former estimate. .The estimate makes the total cost $42,705.84, the number of yards of earth to be excavated 388,344 cubic yards, and Brown’s bid at 9| cents a cubic yard makes the total $35,912.57, which is within the estimate. The petition alleges that the amount of $42,690.24 was adopted by the board of supervisors as the estimate of the cost of said improvement, after having ascertained all the expenses, compensation for land taken and damages; that the main item of cost in the estimate Avas for the excavation of the ditch, Avhieh under the bid of Callahan Bros. & Katz amounted to $32,536.78, Avliile Brown’s bid aggregated $35,912.57, Avhoreby the estimate Avould be exceeded by $3,375.79, which the board of supervisors had no authority to do. The petition, hoAvever, does not separate the items of the? estimate so. as to show Avhat was originally estimated as the cost of excavation and construction. Brown’s bid
As to the contention that the bid did not respond to the advertisement, because it was not made by each working section, this is a mistake, since the bidder proposed to “construct, excavate and complete by working sections” at and for the price of 9|: cents a cubic yard of earth. This means at 9J cents for each working section, or the same rate per yard -for all.
We think the judgment of the district court is correct, and recommend that it he affirmed.
By the Court: For the reason stated in the foregoing opinion, the judgment of the district court is
Affirmed.
Reference
- Full Case Name
- Joseph Gutschow v. Washington County
- Status
- Published