Farley & Loetscher Manufacturing Co. v. Methodist Episcopal Church
Farley & Loetscher Manufacturing Co. v. Methodist Episcopal Church
Opinion of the Court
The plaintiff brought this action against the Methodist Episcopal Church of Allen, Nebraska, and others, to foreclose a mechanic’s lien upon the church property. From a decree in favor of the defendants, the plaintiff appeals.
It appears that on September 10, 1917, the board of trustees of the church society entered into a contract with R. G. Roberts, a contractor and builder, to furnish the materials and do the work in the construction of a church building for a sum named in the contract; said building to be constructed in accordance with plans and specifications adopted by the board of trustees. On the same day the plaintiff entered into a contract with Roberts to furnish the mill-work in the construction of the church building, for the sum of $1,529. Pursuant to this contract the plaintiff shipped certain items of material to Roberts on September 26, 1917, February 13, 1918, February 27, 1918, March 23, 1918, and October 9, 1918. The last shipment .contained two window frames, a box of glass and a few window stops. The lien upon which the action is founded was filed November 14, 1918, so that the shipment of October 9, 1918, becomes a controlling factor in the case. This last shipment was sent by express, consigned to Roberts, and arrived at Allen on October 11. Roberts refused to accept the consignment, and later the material was sent to Omaha by direction of the plaintiff. The record further shows that no contractual relations existed between the plaintiff and the church society or its board of trustees.
Our mechanics’ lien law gives to a subcontractor the right
The items of this last shipment were never delivered to Roberts, or to the church or its board of trustees. They were never delivered on the church premises, and in fact were never out of the possession of the express company. Under these facts the case falls clearly within the rule announced in Ashford v. Iowa & Minnesota Lumber Co., 81 Neb. 561, wherein it was held: “A subcontractor who furnishes materials for a building, and whose contract is with the contractor alone, cannot acquire a lien under the statute for material that was neither used in the construction of said building, nor delivered on the premises for such use.”
The record shows that Roberts had complied with the terms of his contract, and a full settlement was made with him by the board of trustees on August 22, 1918, without any knowledge that the plaintiff had not been paid.
. From what has been said, it follows that the shipment of October 9, 1918, cannot be considered as a basis for the plaintiff’s lien. The judgment of the district court was right, and it is
Affirmed.
Note — See Mechanics’ Liens, 27 Cyc. p. 46.
Reference
- Full Case Name
- Farley & Loetscher Manufacturing Company v. Methodist Episcopal Church
- Status
- Published