Skinner Manufacturing Co. v. Carrier Engineering Corp.
Skinner Manufacturing Co. v. Carrier Engineering Corp.
Opinion of the Court
Skinner Manufacturing Company, plaintiff, brought this action against Carrier Engineering Corporation, defendant, to recover the amount paid by plaintiff to defendant on a written contract for the installation, in plaintiff’s macaroni factory, of a system for drying macaroni and kindred products; also to recover the cost of removal of the machinery and equipment from its factory, expense of storage, and for damages for macaroni spoiled in the process of testing the machinery.
A copy of the contract is made a part of the petition, •and among other things provides: That defendant shall install, on the fourth floor of plaintiff’s factory in Omaha, ;a system for drying macaroni and kindred products; warrants that the machinery, when installed, will handle and thoroughly and uniformly dry 40,000 pounds of macaroni and kindred products within 24 hours, the finished product to be free from checks, cracks, splits and molds. It further provides that, in the event the system installed fails to meet the contract requirements, the defendant shall remove the machinery and appliances at its own expense and restore plaintiff’s building as nearly as possible to its original condition, and that defendant shall return to plaintiff any sums that have been paid on the purchase price of the machinery.
Plaintiff alleges that the machinery installed failed to meet the requirements of the contract; that, although requested so to do, defendant failed to remove the machinery from the manufacturing plant, and that it was removed by plaintiff at its own cost. Plaintiff also alleges that it has paid to defendant $13,936.23 on the purchase price of the machinery; that it has sustained damages in the cost of its removal and storage, also for macaroni spoiled in the process of testing the drying system, and prays for judgment in the aggregate sum of $49,544.45.
Defendant in its answer admits the making of the contract; the installation of the machinery; that it failed to meet the contract requirements to dry 40,000 pounds of
Defendant filed a counterclaim for the reasonable value of the machinery, which it alleges to be in excess of $41,000, and asks for judgment therefor, less the amount that has been paid on the purchase price.
Plaintiff in its reply denies that the written contract was modified as alleged by defendant, and further alleges
' There are numerous assignments of error, but the only ones argued and relied upon are that the verdict is not supported by the evidence and is contrary to law; error in giving certain instructions, and error in excluding certain exhibits offered in evidence by plaintiff.
As to many of the facts in issue, the evidence is-in sharp conflict. Plaintiff’s evidence tends to show that it thoroughly tried and tested the machinery, and that at no time would it properly dry 40,000 pounds of macaroni in 24 hours, or even in 48 hours, and that a large percentage of the product checked and cracked to such an extent that it was unfit for market; that, after thorough trial and testing, plaintiff requested defendant to remove the machinery from the factory; that defendant failed so to do, and thereupon plaintiff removed the machinery at its own expense. The evidence tends to show that a very large amount of the product that was attempted to be dried by the machinery and equipment, installed by defendant, checked and
It is conceded by defendant that it was unable to make the machinery properly dry the macaroni within the 24-hour period, but its evidence tends very) strongly to show that it was able to and did properly dry the required amount of macaroni in 48 hours; that this product was used and marketed by the plaintiff, and that only a small amount of dried product was unfit for use, but that some macaroni was spoiled while defendant was endeavoring to make the plant operate on a 24-hour basis, and that plaintiff was allowed credit for the spoiled product, in accordance with statements of the amount thereof rendered by plaintiff. Defendant’s evidence further tends strongly to show that in the early part of 1919 there was a modification of the contract, substantially as alleged by defendant; that defendant agreed to install the cams, and that after they were installed the plaintiff should be allowed 60 days in which to test the system with its own employees, to ascertain if it would operate satisfactorily on the 48-hour basis, and, if so, that the price should be thereafter agreed to by the parties; that the cams were installed on the machinery, and that the system was turned over to plaintiff on the 1st of October, 1919, for the 60-day test by plaintiff with its own operatives, at the end of which time plaintiff was to determine whether or not it would keep the plant. . Defendant called a number of persons, who were employed by plaintiff at the time of making the test and subsequent thereto, and their evidence is to the effect that during all the 60-day test and for a long time thereafter the drying apparatus was used continuously; that it would properly dry 40,000 pounds of macaroni in 48 hours; that the product was of high quality, free from checks, cracks, splits and molds. The evidence further tends to show that shortly after the expiration of the 60-day test plaintiff’s manager or superintendent stated that the test had been satisfactory.
On December 10, 1919, defendant sent to plaintiff a bill for the machinery, allowing credit for the amount pre
The issues of fact as presented by the evidence were submitted to the jury, and its verdict, based on conflicting evidence, is conclusive.
Plaintiff argues that, even if it retained the machinery in its factory after the expiration of the specified time for testing and using it in making further tests, this fact would not constitute an acceptance. Had the. contract remained unmodified, the argument would be persuasive. Under the contract as modified, plaintiff was given a reasonable and definite time in which to fully and fairly test the machinery with its own operatives. This was in addition to the tests that had been made in its factory by the defendant and of which it had full knowledge. If it desired additional
Where a purchaser of warranted machinery asks for and is given a definite, reasonable time in which to make a full, fair test thereof, to enable him to determine whether the machinery is satisfactory and complies with the warranty, and who does make a full fair test for the specified time, and thereafter, without objection or complaint, continues to use the machinery, he will, ordinarily, be deemed to have accepted it. A purchaser of warranted machinery who accepts it, after a full, fair trial thereof, thereby renders himself liable for its fair and reasonable value, in the absence of an agreement as to the purchase price.
The rule here announced is, in a general way, supported by the following authorities: McCormick Harvesting Machine Co. v. Martin, 32 Neb. 723; Hercules Iron Works v. Dodsworth, 57 Fed. 556, on appeal Dodsworth v. Hercules Iron Works, 66 Fed. 483; Brown v. Foster, 108 N. Y. 387; Barber Mining & Fertilizing Co. v. Brown Hoisting Machinery Co., 258 Fed 1; Crescent Milling Co. v. Strait Mfg. Co. 227 Fed. 804; Thomas China Co. v. C. W. Raymond Co., 135 Fed. 25; Chambers v. Lancaster, 160 N. Y. 342.
Plaintiff complains of certain instructions given the jury. One of them apparently imposes on plaintiff the burden of proving the modification of the written contract. This modification was pleaded by defendant and denied by plaintiff in its reply. The burden of establishing it, therefore,, rested on defendant. However, the overwhelming weight of the evidence shows that the contract was modified, and
Complaint is made of certain rulings of the court excluding three exhibits, offered in evidence by plaintiff. We have examined these exhibits and in our opinion they have no bearing upon any of the issues involved. They tend neither to support nor to controvert any issue presented. There was no error in their exclusion.
We find no prejudicial error in the record. The judgment of the district court is
Affirmed.
Note—See Sales, 35 Cyc. 432, 580.
Reference
- Full Case Name
- Skinner Manufacturing Company v. Carrier Engineering Corporation
- Status
- Published