Acme Plumbing & Heating Co. v. Hirsch
Acme Plumbing & Heating Co. v. Hirsch
Opinion of the Court
The Acme Plumbing & Heating Company began this action in the district court for Lancaster county against Marie Hirsch to foreclose two mechanics’ liens for $1,025 and $1,200, respectively. These liens represent a charge
The defendant contends that the court erred in refusing to dismiss plaintiff’s petition on account of alleged variance between the liens which were filed of record and the amended pleadings. While there appears to have been a variance between the pleadings and the proofs, such variance was not exercised in bad faith nor was it prejudicial to the defendant. Plaintiff contends that the action was commenced tó recover the full amounts named in the contracts solely on the theory that the plaintiff was entitled to full reimbursement instead of only partial reimbursement for the material named in the contracts. We do not think the court erred in refusing to dismiss the plaintiff’s petition. Section 20-846, Comp. St. 1929, provides:
“No variance between the allegation in a pleading and the proof is to be deemed material unless it have actually misled the adverse party, to his prejudice, in maintaining his action or defense upon the merits.”
Shortly after the fire a member of the plaintiff company .presented an itemized statement of the cost of the material and the labor expended on the building, and this ■statement was used by the defendant in arriving at the amount due her under her insurance policy from an insurance company. The plaintiff alleges that the defendant agreed to pay the amount due on the two liens if plaintiff would furnish an itemized statement of the plumbing and heating material lost and destroyed in the fire to assist in reaching the amount due her from the insurance company. But plaintiff further alleged that the defendant refused payment on the two liens after the insurance had been paid.
In Matthews Construction Co. v. Brady, 104 N. J. Law, 438, the court made this observation:
> “Where under a contract for alterations and additions to an existing building performance depends on the continued existence of the structure, a condition is implied ■that impossibility of complete performance arising from its destruction without fault of the parties will absolve them from further liability, with the exception that the ■owner remains liable and the builder may recover for the value of the work done and materials delivered and accepted prior to such destruction.”
And in Angus v. Scully, 176 Mass. 357, it was held:
“Where one is to make repairs or do any other work •on the house of another under a,special contract, and his .contract becomes impossible of performance on account of the destruction of the house without any fault on his part, he may recover for what he has done, one of the .implied conditions of the contract being that the building should continue to exist.”
It appears to be established in cases of this character that, where the material instálled in the building is in ac
• ■ In view of the facts presented by the record and of the law applicable thereto, we conclude that the judgment must be and it hereby is
Affirmed.
Reference
- Full Case Name
- Acme Plumbing & Heating Company v. Marie Hirsch
- Status
- Published