New Cingular Wirelss v. Town of Stoddard, et

District Court, D. New Hampshire
New Cingular Wirelss v. Town of Stoddard, et, 2012 DNH 046 (2012)

New Cingular Wirelss v. Town of Stoddard, et

Opinion

New Cingular Wirelss v . Town of Stoddard, et CV-11-388-JL 2/16/12

UNITED STATES DISTRICT COURT DISTRICT OF NEW HAMPSHIRE

New Cingular Wireless PCS, LLC

v. Civil N o . 11-cv-388-JL Opinion N o .

2012 DNH 046

Town of Stoddard, New Hampshire, and Zoning Board of Adjustment of the Town of Stoddard, New Hampshire

MEMORANDUM ORDER

The question in this case is whether the Town of Stoddard’s

Zoning Board of Adjustment, by granting rehearing of its decision

to approve plaintiff New Cingular Wireless PCS, LLC’s application

to construct a wireless telecommunications facility, violated

§ 704(a) of the Telecommunications Act of 1996 by failing to act

on the application “within a reasonable period of time.”

47 U.S.C. § 332

(c)(7)(B)(ii). By ruling of the Federal

Communications Commission, a local government must act on siting

applications like New Cingular’s within 150 days–-a timeframe

that can be extended with the applicant’s consent–-and failure to

act within this time is presumptively unreasonable under

§ 704(a). In the Matter of Petition for Declaratory Ruling to

Clarify Provisions of Section 332(c)(7)(B) to Ensure Timely

Siting Review, 24 FCC Rcd. 13994 (Nov. 1 8 , 2009) (colloquially

referred to as the “Shot Clock Ruling”). Here, New Cingular

agreed to extend the 150-day period by three months, and the Board approved its application within that agreed-upon deadline.

Two months after the deadline expired, however, the Board voted

to grant rehearing of its approval pursuant to a New Hampshire

law providing for rehearing of zoning decisions. See

N.H. Rev. Stat. Ann. §§ 677:2

, 677:3.

New Cingular claims that this amounts to a violation of

§ 704(a), as clarified by the Shot Clock Ruling. New Cingular

further alleges that what it characterizes as the Board’s

“failure to act” also amounted to (a) an effective prohibition on

the provision of wireless services in and around Stoddard and (b)

a de facto denial of the application that was unsupported by

substantial evidence, both of which constitute further violations

of § 704(a). This court has jurisdiction pursuant to

28 U.S.C. § 1331

(federal question).

The Town and the Board (collectively referred to herein as

“the Town”) have moved to dismiss New Cingular’s complaint, see

Fed. R. Civ. P. 12(b)(6) arguing that the Board did act on the

application within a reasonable time by approving it before the

agreed-upon deadline, and that the subsequent decision to grant

rehearing is irrelevant. Alternatively, they argue, the Shot

Clock Ruling establishes only a presumption of unreasonableness,

and that presumption is overcome by the circumstances surrounding

their decisions, as alleged in New Cingular’s complaint. They

2 further argue that the “effective prohibition” and “substantial

evidence” claims must be dismissed because such claims may only

be premised on the denial of a siting application, and New

Cingular’s application was never denied.

After hearing oral argument, the motion to dismiss is

granted in part and denied in part. The Shot Clock Ruling

contemplates that local governments will resolve siting

applications for wireless facilities within its deadline. But

New Cingular’s application is not “resolved,” because New

Cingular may not act in accordance with the initial approval

until the rehearing process is complete. Nor can the court say

as a matter of law that the presumption of unreasonableness that

the Shot Clock Ruling assigns to a delay of this length is

overcome here, as the facts alleged in the complaint suggest that

rehearing was a tactic calculated to unduly prolong the

application process. Insofar as the motion seeks dismissal of

New Cingular’s claim that the Board failed to act on its

application within a reasonable time, then, it is denied.

Because, however, claims for effective prohibition and lack of

substantial evidence cannot lie unless a local government has

denied the plaintiff’s application, and the Board has not done so

here, the motion to dismiss those claims is granted.

3 I. Applicable legal standard

To survive a motion to dismiss under Rule 12(b)(6), the

plaintiff’s complaint must make factual allegations sufficient to

“state a claim to relief that is plausible on its face.”

Ashcroft v . Iqbal, 129 S . C t . 1937, 1949 (2009) (quoting Bell

Atl. Corp. v . Twombly,

550 U.S. 5

4 4 , 570 (2007)). In ruling on

such a motion, the court must accept as true all well-pleaded

facts set forth in the complaint and must draw all reasonable

inferences in the plaintiff’s favor. See, e.g., Martino v .

Forward Air, Inc.,

609 F.3d 1

, 2 (1st Cir. 2010). Nonetheless,

the “allegations must be enough to raise a right to relief above

the speculative level,” Twombly, 550 U.S. at 555, and “[a]

pleading that offers labels and conclusions or a formulaic

recitation of the elements of a cause of action will not do,”

Iqbal, 129 S . C t . at 1949. The following summary is consistent

with that approach.

II. Background

On October 1 , 2010, New Cingular filed an application with

the Stoddard Zoning Board of Adjustment, seeking permission to

construct a wireless communications facility in the town. As

initially proposed, the facility consisted of a 150-foot lattice

tower with six panel antennae mounted near the top. New Cingular

4 currently has no wireless communications facilities in Stoddard

or the abutting communities, and has a significant coverage gap

throughout Stoddard and those communities. The proposed facility

would help address that gap.

On November 1 0 , 2010, the Board held an initial public

hearing on the application. At the hearing, opponents of the

proposed facility raised concerns about the alleged health

effects of radio frequency emissions and the potential impacts of

construction. New Cingular made efforts to respond to these

concerns, and the Board held a second public hearing on December

1 5 , 2010. At the second public hearing, opponents raised

additional concerns, such as the aesthetic impact of the proposed

facility and the availability of alternative sites. New Cingular

again made efforts to address these concerns, and the Board held

a third public hearing on January 5 , 2011. The Board

subsequently held fourth, fifth, and sixth public hearings on

February 1 5 , 2011; April 1 9 , 2011; and May 5 , 2011, respectively.

Between hearings, New Cingular conducted numerous tests, and

submitted voluminous additional materials, to address the

concerns raised by opponents and Board members.

As already mentioned, and described in more detail elsewhere

in this order, the Federal Communications Commission (“FCC”) has

prescribed a presumptive deadline of 150 days within which local

5 authorities must act to approve or deny an application to

construct a wireless communications facility. That 150-day

deadline would have expired on March 1 , 2011, but New Cingular

agreed to extend it to May 3 1 , 2011. On May 2 5 , 2011, the Board

voted 3-2 in favor of granting New Cingular’s application, with

some alterations. Rather than the 150-foot lattice tower

originally proposed, the Board approved construction of a 130-

foot unipole (a single pole with internal antennae), a decision

New Cingular does not contest.

Over the next 30 days, numerous local opponents of the

proposed facility filed motions for rehearing pursuant to

N.H. Rev. Stat. Ann. § 677:2

. Those motions argued, among other

things, that the Board had failed to consider the effect

construction of the tower would have on property values and the

town’s “rural character.” On July 2 1 , 2011, the Board met to

discuss these motions. At the meeting, Board member Fred Ward--

who had been among those most vocally opposed to the facility--

speculated that the rehearing process might “take 20 or 30

meetings” and suggested that the Board engage a new radio

frequency consultant because he considered the previous

consultant “to be less than helpful.” (That consultant had

concluded that other proposed sites for the facility could not

“provide a viable solution” to New Cingular’s coverage gap, and

6 had opined that maps Ward had submitted to support a contrary

conclusion were “seriously flawed” and should be disregarded.)

At the close of the meeting, the Board voted to grant

rehearing on its approval of the facility. The following day,

all three of the Board members who voted in favor of New

Cingular’s application resigned, as did all of the Board’s

alternate members. The only two members remaining on the Board

were Ward and his wife--the two members who had voted against the

proposed facility. On August 1 , 2011, the Stoddard Town

Administrator issued a notice that “until such time that the

Selectmen can appoint a full Zoning Board of Adjustment,” all

scheduled hearings-–including the rehearing on New Cingular’s

application, which had been set for September 1 , 2011-–were

cancelled.

New Cingular filed this action less than a week later, on

August 8 , 2011. As of September 7 , 2011, the date New Cingular

filed its first amended complaint, no successor members had been

appointed to the Board and no rehearing date had been scheduled.

III. Analysis

A. Counts 1 and 4 - unreasonable delay and declaratory judgment

Counts 1 and 4 of New Cingular’s complaint assert claims for

unreasonable delay and declaratory judgment, respectively, each

7 arising from the Board’s grant of rehearing on its approval of

New Cingular’s application. At the heart of these claims is

47 U.S.C. § 332

(c)(7)(B)(ii). That provision, part of section

704(a) of the Telecommunications Act of 1996, states:

A State or local government or instrumentality thereof shall act on any request for authorization to place, construct, or modify personal wireless service facilities within a reasonable period of time after the request is duly filed with such government or instrumentality, taking into account the nature and scope of such request.

The Act itself does not define the “reasonable period of

time” within which a local government must act on an application.

For more than twelve years following the Act’s passage, that

phrase was interpreted by various federal courts, which generally

concluded that § 332(c)(7)(B)(ii) “evinces an intent to create a

relatively flexible time frame in which local governments must

act.” USCOC of Greater M o . v . City of Ferguson,

583 F.3d 1035, 1041

(8th Cir. 2009); see also Omnipoint Comm. Enters., Inc. v .

Town of Amherst,

74 F. Supp. 2d 109, 121

(D.N.H. 1998) (“The

prohibition against delay is not absolute and no specific time

period within which to pass on applications is prescribed; the

limit is one of reasonableness under the circumstances.”). This

flexibility, however, engendered some confusion: for example,

one court concluded that a failure to take action for seven

months was unreasonable, see MetroPCS New York, LLC v . City of

8 Mount Vernon,

739 F. Supp. 2d 409, 424

(S.D.N.Y. 2010), while

another court ruled that a delay more than twice that length was

not, see SNET Cellular, Inc. v . Angell,

99 F. Supp. 2d 1

9 0 , 198-

99 (D.R.I. 2000). Without a clear rule as to when a failure to

take action became unreasonable, wireless service providers were

left guessing as to when they should seek redress from the courts

for local governments’ failures to act on applications in a

timely manner.1 See Shot Clock Ruling, 24 FCC Rcd. at 13998,

¶ 1 4 ; 14003-04, ¶¶ 2 7 , 2 9 .

The FCC attempted to remedy this confusion, and to combat

unreasonable delays in the zoning process, with the so-called

“Shot Clock Ruling.” Id. at 14004-06, ¶¶ 32-34; 14008, ¶ 3 7 . In

that ruling, the FCC “define[d] what constitutes a presumptively

‘reasonable time’ beyond which inaction on a personal wireless

service facility siting application will be deemed a ‘failure to

act.’” Id. at 14000, ¶ 1 9 . After surveying existing state and

local requirements for the timely processing of wireless facility

siting applications, and taking evidence regarding the typical

1 Because the Act requires a wireless service provider aggrieved by a failure to act to file suit “within 30 days after such . . . failure to act,”

47 U.S.C. § 332

(c)(7)(B)(v), a provider without a clear idea of when its claim accrued had an incentive under the law to file suit as early as possible to preserve its rights, creating potentially unnecessary litigation for both providers and the local governments forced to defend against such suits.

9 time periods within which local governments had historically

processed them, the FCC found that 90 days is “a generally

reasonable timeframe for processing collocation applications” and

150 days is “a generally reasonable timeframe for processing

applications other than collocations.”2

Id. at 14012

, ¶ 4 5 .

“[I]f state or local governments do not act upon applications

within those timeframes,” the FCC concluded, “then a ‘failure to

act’ has occurred and personal wireless service providers may

seek redress in a court of competent jurisdiction.”

Id. at 14005

, ¶ 3 2 . Recognizing, however, that “certain cases may

legitimately require more processing time,”

id. at 14007

, ¶ 3 7 ,

the FCC provided that the deadlines could be extended by

agreement of the applicant,

id. at 14013

, ¶ 4 9 , as they were

here. The FCC also clarified that the deadlines were only

presumptively reasonable, and that “the State or local authority

will have the opportunity, in any given case that comes before a

court, to rebut the presumption that the established timeframes

are reasonable” based upon the “unique circumstances in

individual cases.”

Id. at 14010-11

, ¶¶ 4 2 , 4 4 .

2 A collocation application involves “the addition of an antenna to an existing tower or other structure.” Shot Clock Ruling, 24 FCC Rcd. at 14012, ¶ 4 6 . Applications other than collocations would involve the construction of new facilities or major modifications to existing facilities.

Id. at 14011

, ¶ 4 3 . New Cingular’s application, which seeks approval to construct a new facility, falls into the latter category.

10 New Cingular and the Town agree that the Shot Clock Ruling

governs this case.3 They disagree, though, as to how the ruling

applies to the facts alleged in the complaint. The Town argues

that the deadline set forth in the ruling “applies only to the

Board’s initial review process,” not “post-decision rehearings

and appeals.” As long as a local government has completed its

“initial review process” and issued an initial decision on an

application before the deadline, the Town says, it has fulfilled

its obligations under the ruling, so a grant of rehearing is of

no moment. New Cingular disagrees with the Town’s

characterization of rehearing as a “post-decision” process, and

instead argues that a local government that grants rehearing has

not made any real decision on an application until the rehearing

has been concluded. If--as is the case here--the rehearing

process is not concluded before the deadline, New Cingular says,

the government has not satisfied the Shot Clock Ruling’s mandate.

3 The validity of the Shot Clock Ruling and the FCC’s authority to issue it were recently challenged in the Court of Appeals for the Fifth Circuit, which upheld the ruling. See City of Arlington v . FCC, --- F.3d ----,

2012 WL 171473

(5th Cir. Jan. 2 3 , 2012). Because the Town’s motion assumes that the ruling is valid and controlling, this court also assumes--strictly for purposes of its analysis here--that the Fifth Circuit’s holding is correct and that the ruling is entitled to deference as the interpretation of an ambiguous statute by the agency charged with administering i t . See, e.g., WorldNet Telecommc’ns, Inc. v . Puerto Rico Tel. Co.,

497 F.3d 1

, 5 (1st Cir. 2007) (citing Chevron, U.S.A., Inc. v . Natural Res. Def. Council,

467 U.S. 837

(1984)).

11 New Cingular has the better argument. The Shot Clock Ruling

contemplates not just that a local government will take some

action on an application within the deadline, but that it will

“resolve [the] application” before the deadline.4 Shot Clock

Ruling, 24 FCC Rcd. at 14008, ¶ 38 (emphasis added). Where a

local government grants rehearing under

N.H. Rev. Stat. Ann. §§ 677:2

and 677:3, it has not “resolved” the application.

Rather, a grant of rehearing--which is not mandatory, but wholly

discretionary, see

N.H. Rev. Stat. Ann. § 677:2

--“suspend[s] the

order or decision complained of pending further consideration,”

id.

§ 677:3, I I . There are no limits as to which issues may be

considered on rehearing, permitting the local government to

address the entire application anew if it wishes, and to reach a

final decision diametrically opposed to its initial decision.

See id. §§ 677:2-677:3.

To separate the “initial review process” and rehearing from

one another in the manner the Town suggests, then, is not

possible. Under New Hampshire law, a rehearing is part and

parcel of a single review process before a single entity,

culminating in a single decision that ultimately resolves the

4 The meaning of the term “act on [a] request” as it is used in

47 U.S.C. § 332

(c)(7)(B)(ii) is not before the court. The parties have instead focused on what action the Shot Clock Ruling requires within its deadlines, and the court therefore does as well.

12 application with either an approval or a denial.5 Furthermore,

where (as here) the review period permitted by state law extends

beyond the deadline set forth in the Shot Clock Ruling, the

ruling makes clear that the applicant may bring suit after the

federal deadline has expired, without regard to the longer time

allowed under state law. See Shot Clock Ruling, 24 FCC Rcd. at

14012-13, ¶ 5 0 . Accordingly, the Shot Clock Ruling’s 150-day

deadline for the processing of wireless communications facility

siting applications encompasses not only the time it takes a

5 The Town has cited V a . Code Ann. § 15.2-2232--a statute the FCC relied upon in finding that a 150-day timeframe for the processing of siting applications was reasonable, see Shot Clock Ruling, 24 FCC Rcd. at 14012, ¶ 48 & n.152--in support of its argument that the New Hampshire rehearing process is not subject to the Shot Clock Ruling. Because the Virginia statute includes an appeal process the FCC did not consider when calculating a “reasonable” period of time, the Town says, the FCC plainly did not intend the time allotted for post-decision processes to be encompassed within the Shot Clock Ruling’s deadlines. But a New Hampshire rehearing is readily distinguishable from the appeal process outlined in the Virginia statute. While an aggrieved party may appeal under Virginia law as of right, see V a . Code Ann. § 15.2-2232, B--meaning the local government has no control whatsoever as to whether or not an appeal occurs--under New Hampshire law, a local government possesses virtually unfettered discretion as to whether or not to grant rehearing, see

N.H. Rev. Stat. Ann. § 677:2

. And under New Hampshire law, rehearing proceeds before the same body that reached the initial decision on the application.

Id.

§§ 677:2 and 677:3. But an appeal under Virginia law--as is typical of appeals--is heard by a different entity than that which reached the initial decision. V a . Code Ann. § 15.2-2232, B . It is also worth noting that an appeal under V a . Code Ann. § 15.2-2232, B “shall be heard and determined within sixty days from its filing,” whereas New Hampshire law does not impose any limitations on how long a rehearing may take, see infra n.6.

13 local government to reach an initial decision on an application,

but the time it takes to complete the rehearing process set forth

in

N.H. Rev. Stat. Ann. §§ 677:2

and 677:3 as well.

While this court’s interpretation of the Telecommunications

Act and the Shot Clock Ruling is based on their language, it is

also buttressed by practical considerations. To conclude that a

rehearing under New Hampshire law is exempt from the Shot Clock

Ruling’s deadlines would encourage great mischief. A local

zoning board of adjustment, acting in concert with the board of

selectmen or other party authorized to move for rehearing under

N.H. Rev. Stat. Ann. § 677:2

, could easily avoid the Shot Clock

Ruling by voting to approve an application within the deadline--

which, under the Town’s interpretation, is all the ruling

requires--and then grant rehearing. Because New Hampshire law

imposes no time limits on rehearings,6 once rehearing had been

granted, the zoning board would be free to take as long as it

wished to address the application. This would render the

deadline set forth in the Shot Clock Ruling a dead letter, and

6

N.H. Rev. Stat. Ann. § 677:3

, I I , does provide that after a motion for rehearing is filed, the local governmental body charged with making zoning decisions “shall within 30 days either grant or deny the application, or suspend the order or decision complained of pending further consideration.” I f , however, that body chooses to suspend its original order and grant rehearing (which is what happened here), the statute does not require that “further consideration” be completed within any set timeframe.

14 undermine the Shot Clock Ruling’s stated goal of “encourag[ing]

the expeditious deployment of wireless broadband services.” Shot

Clock Ruling, 24 FCC Rcd. at 14005, ¶ 3 2 . These considerations,

though they would not lead this court to ignore clear statutory

or regulatory language to the contrary, illustrate the dangers

inherent in the Town’s construction of the Act and the Shot Clock

Ruling.

Of course, a rehearing process that occurs after, or extends

beyond, the Shot Clock Ruling’s deadline does not necessarily

violate the Telecommunications Act’s directive that local

authorities act upon applications “within a reasonable period of

time.” See

47 U.S.C. § 332

(c)(7)(B)(ii). As already noted, the

deadline set forth in the Shot Clock Ruling is only presumptively

reasonable. Though a local government’s failure to resolve an

application within that deadline entitles the applicant to bring

suit under the Act, the local government will still “have the

opportunity to rebut the presumption of reasonableness.” Shot

Clock Ruling, 24 FCC Rcd. at 14005, ¶ 3 2 . It is up to the court

to then “determine whether the delay was in fact unreasonable

under all the circumstances of the case.”7

Id. at 13995

, ¶ 4 .

7 In fact, many of the concerns the Town has raised in support of its argument that the Shot Clock Ruling does not apply to rehearing at all are also factors properly taken into account when considering whether a delay was reasonable. For example, that local governments may have little control over whether a

15 The Town argues that, even accepting all the facts alleged

in the complaint as true, the presumption of reasonableness is

rebutted in this case. Its argument rests principally on the

contention that it is per se reasonable to grant rehearing under

N.H. Rev. Stat. Ann. §§ 677:2

and 677:3 because rehearing “is not

an effort to impede or obstruct,” but instead has salutary

purposes. It points out, for example, that rehearings afford

local governments the opportunity to correct their own errors,

oftentimes giving rise to decisions supported by a stronger

record and more substantial reasoning, and saving all parties

involved from a potentially unnecessary appeal. See McDonald v .

Town of Effingham,

152 N.H. 1

7 1 , 174 (2005).

Be that as it may, the court cannot agree that the Shot

Clock Ruling’s presumption of unreasonableness is rebutted

whenever rehearing is granted under

N.H. Rev. Stat. Ann. §§ 677:2

and 677:3. While a rehearing can undoubtedly serve legitimate

goals, it does not follow that a local government always

exercises its discretion to grant rehearing with such goals in

mind, or that rehearing is never calculated “to impede or

request for rehearing is filed, and may need to allow at least three months for a rehearing to occur, are both circumstances that bear upon the reasonableness of a delay. Indeed, the Shot Clock Ruling specifically identifies such “reasonable, generally applicable procedural requirements” as the type of “unique circumstances” that affect this inquiry. Shot Clock Ruling, 24 FCC Rcd. at 14011, ¶ 4 4 .

16 obstruct” in a way prohibited by the Telecommunications Act. It

is not inconceivable that a local government hostile to the

construction of a wireless communications facility could grant

rehearing as a means of unduly prolonging the application process

and creating another obstacle for the applicant to overcome.

In any event, there is nothing in either § 704(a) or the

text of the Shot Clock Ruling that makes an intent to “impede or

obstruct” an essential element of unreasonable delay. In other

words, even where the local government’s reasons for granting

rehearing are laudable, the delay that results is not necessarily

reasonable. “At some point, acts such as raising additional

procedural hurdles well after the process has begun and providing

expansive opportunity for repetitious public comment can create

an unreasonable delay.” Omnipoint Commc’ns Enters., Inc. v . Town

of Amherst,

74 F. Supp. 2d 109, 122

(D.N.H. 1998) (DiClerico,

J . ) ; see also MetroPCS New York, LLC v . City of Mount Vernon,

739 F. Supp. 2d 409, 424

(S.D.N.Y. 2010) (local government violates

Telecommunications Act “by repeatedly requesting unnecessary

information and belaboring issues already resolved”).

The allegations of the complaint (which the Town hardly

addresses) suggest that the Board’s grant of rehearing was a

direct attempt to raise “additional procedural hurdles,” to

provide “expansive opportunity for repetitious public comment,”

17 or both. New Cingular alleges that its proposed facility faced

vocal opposition from the very beginning, and among the most

vocal opponents was at least one member of the Board itself. The

Board held six public hearings on the application, requiring New

Cingular to submit a great deal of additional evidence. Each

time New Cingular did s o , however, the facility’s opponents

(including Board members) raised additional concerns that it was

then required to address. Furthermore, after persuading New

Cingular to agree to an extension of the Shot Clock Ruling’s

deadline, the Board waited almost until the eve of the extended

deadline to issue a written decision. Two months later,

however–-and five months after the Shot Clock Ruling’s

presumptively reasonable 150-day deadline had expired--the Board,

having received multiple requests for rehearing from opponents of

the facility (who again raised previously unaddressed issues),

suspended its decision by granting rehearing. This left New

Cingular’s application in a state of limbo until the completion

of the rehearing process–-which, as already discussed, is

potentially indefinite, and which one Board member speculated

could require another “20 or 30 hearings.”

The Board’s pattern of delay in issuing a final decision on

New Cingular’s application, coupled with its apparently unlimited

18 willingness to consider the ever-growing list of objections from

the facility’s opponents, suggests an unreasonable delay under

§ 704(a) and the Shot Clock Ruling. While it is certainly

possible that the Board was simply “address[ing] the application

in a conscientious and responsible manner,” as the Town argues,

that is not the only permissible inference from the facts

alleged,8 and, in any event, conscientiousness is not necessarily

incompatible with unreasonable delay, as just discussed. Because

New Cingular has plausibly stated a claim for unreasonable delay

under the Telecommunications Act, the Town’s motion to dismiss

Counts 1 and 4 of New Cingular’s complaint is denied.

B. Counts 2 and 3 - effective prohibition and lack of substantial evidence

Counts 2 and 3 of New Cingular’s complaint are premised on

the theory that the Board’s failure to resolve its application

within the agreed-upon deadline violated both

47 U.S.C. § 332

(c)

(7)(B)(i)(II), which provides that “[t]he regulation of the

placement, construction, and modification of personal wireless

8 The resignation of a majority of the Board’s members (and all of its alternate members) immediately following the grant of rehearing could also suggest that the Board’s delay in acting was attributable to causes other than a conscientious and thorough evaluation of the merits of the application. While the court is skeptical of New Cingular’s attempt to argue that those individual members’ resignations are actions attributable to the Board itself, the mass resignation is relevant insofar as it may shed light on the Board’s motivations for its prior actions.

19 service facilities by any State or local government or

instrumentality thereof . . . shall not prohibit or have the

effect of prohibiting the provision of personal wireless

services,” and

47 U.S.C. § 332

(c)(7)(B)(iii), which requires that

“[a]ny decision by a State or local government or instrumentality

thereof to deny” an application to construct a wireless

communications facility be “supported by substantial evidence

contained in a written record.” The Town argues that for a

plaintiff to state a claim under either provision, its

application must have been denied by the local government.

Because the Board never denied New Cingular’s application, it

says, these provisions are inapplicable. The court agrees.

The plain language of the “substantial evidence” provision,

§ 332(c)(7)(B)(iii), requires that the local government make a

“decision . . . to deny” the application. Thus, when the

plaintiff’s application has not been denied, a claim under this

provision does not lie, as a number of courts have ruled. See,

e.g., N.Y. SMSA Ltd. P’ship v . Town of Riverhead,

45 Fed. Appx. 2

4 , 27 (2d Cir. 2002); Masterpage Commc’ns, Inc. v . Town of

Olive,

418 F. Supp. 2d 6

6 , 80-81 (N.D.N.Y. 2005); Nextel Partners

of Upstate N.Y., Inc. v . Town of Canaan,

62 F. Supp. 2d 6

9 1 , 697

(N.D.N.Y. 1999). Similarly, although § 332(c)(7)(B)(i)(II)’s

“effective prohibition” provision is not nearly as clear on its

20 face, the court of appeals has read it to require a showing that,

inter alia, the plaintiff’s application was denied. Town of

Amherst v . Omnipoint Commc’ns Enters., Inc.,

173 F.3d 9, 14

(1st

Cir. 1999). A claim for effective prohibition is likewise not

ripe where the local government has not denied the application.

See Cox Commc’ns PCS, L.P. v . City of San Marcos,

204 F. Supp. 2d 1272, 1277

(S.D. Cal. 2002).

New Cingular argues that although the Board never denied its

application outright, the Board’s failure to act constituted a

“functional” or “de facto” denial of the application. In support

of this proposition, it relies upon Tennessee ex rel. Wireless

Income Properties, LLC v . City of Chattanooga,

403 F.3d 392

(6th

Cir. 2005) and Sprint Spectrum L.P. v . Town of Durham, N o . 97-

305-JD,

1998 WL 1537756

(D.N.H. Aug. 2 7 , 1998). But the

defendants in those cases did not simply fail to resolve the

application, as the Board allegedly did here. Rather, in City of

Chattanooga, the defendant specifically informed the plaintiff

that its applications did not comply with local ordinances, and

“indicated that no further action would be taken on the

applications unless [the necessary] changes were made.”

403 F.3d at 398

. Reasoning that this amounted to an announcement that

the plaintiff’s “applications, absent amendment, would not be

granted,” the court in that case concluded that the defendant

21 had, in fact, rendered a decision denying the applications.

Id. at 398-99

. Similarly, in Town of Durham, the defendant declared

that recent actions by the Town Council had caused the

plaintiff’s original application to become moot, and took the

position that in order to construct the proposed wireless

communications facility, the plaintiff would need to submit a new

application.

1998 WL 1537756

at *2-3.

Here, by contrast, the Board never informed New Cingular

that no further action would be taken on its application or that

it would need to submit a new application. In fact, in granting

rehearing, it indicated just the contrary--that further action

would be taken on New Cingular’s original application. City of

Chattanooga and Town of Durham are therefore inapposite. This is

not to say that a failure to act on an application cannot ever,

under any set of circumstances, amount to an effective denial of

the application. But if such circumstances exist, they are not

presented by the allegations of New Cingular’s complaint.

Because the Board did not render a final decision denying

New Cingular’s application, New Cingular’s claims under

47 U.S.C. §§ 332

(c)(7)(B)(i)(II) and 332(c)(7)(B)(iii) are premature, and

must be dismissed.

22 IV. Conclusion

For the reasons set forth above, the defendants’ motion to

dismiss9 is GRANTED as to Counts 2 and 3 and DENIED as to Counts

1 and 4 .

SO ORDERED.

Josep ___N ______ ante ___________ United States District Judge

Dated: February 1 6 , 2012

cc: Anne Robbins, Esq. Stephen D. Anderson, Esq. Jeffrey C . Spear, Esq. James P. Bassett, Esq.

9 Document n o . 1 4 .

23

Reference

Status
Published