Herbert v. Pennsylvania Railroad
Opinion of the Court
The Pennsylvania Railroad Company, by authority of law, is constructing a connection between two points in its main track at Jersey City, for the purpose of avoiding a dangerous and expensive curve. The benefit to be derived from the undertaking will be the shortening of the line of the road, the expedition of travel, the removal of danger to the public in the use of a sharp curve, and the saving of wear to the company’s rolling-stock.
A portion of this connection is to be-upon a solid embankment, in process of construction, over the corner of a meadow,, which seems to be a bed of mud and silt of considerable depth. This embankment is to be used, not only for part of the proposed connection between points in the line of the Pennsylvania Railroad, but also by the New Jersey Junction Railroad Company, which connects the Pennsylvania Railroad system with that of the West Shore Railroad Company, and it has so nearly reached completion that the regular passenger trains of the New Jersey Junction Railroad are now running upon scheduled time over the portion of it which lies nearest to the complainant’s lot. hereafter mentioned.
The defendant company has been at work upon the embankment for nearly sixteen months, has put in it about one hundred and sixty thousand cubic yards of earth and other filling, and has expended upon it many thousands of dollars.
The complainant is the owner of a lot adjacent to the embankment, twenty feet wide and eighty feet deep, upon which is erected a three-story frame tenement house. He purchased this lot about twenty-five years ago from one Edgar B. Wakeman,. who had laid out his property into blocks, lots and streets, and mapped it. His deed describes the lot by reference to the map of Wakeman and the blocks, lots and streets shown thereon. The city of Jersey City accepted the dedication of the streets to. the public use by Wakeman, and took control of them; but in May, 1887, under and in pursuance of the provisions of the-city’s charter, vacated the portions which were occupied by the defendant’s embankment, and abutted by its property.
He also claims that because Wakeman described his lot in the deed he gave for it by reference to the map aforesaid and the streets shown upon it, that he is entitled to have the embankment removed from the portions of the streets which have been vacated, and the further filling upon such portions of the streets ' stopped.
He asks for a mandatory injunction to remove the entire filling, because he claims that it continues to damage his property, and to remove that part of it which is in the vacated streets, not only because of its damage to his property, but also because it disturbs his use of the streets by virtue of the light given to him by the Wakeman dedication.
He asks also for a preventive injunction to restrain further filling, for the same reasons.
A mandatory injunction should be issued interlocutorily with hesitation and caution, and only in an extreme case where the law plainly does not afford an adequate remedy. Longwood Valley R. R. Co. v. Baker, 12 C. E. Gr. 166; Whitecar v. Michenor, 10 Stew. Eq. 6; Lord v. Carbon Manufacturing Co., 11 Stew. Eq. 459.
It does not with any certainty appear that further injury will result to the complainant from the embankment or the further filling upon it. It can hardly be doubted that the filling already done has damaged the complainant’s building. The gradual rising of the surface of the meadow adjacent to the embank
Although questions of law, intricate and unsettled .in the courts of this state, may be involved in a suit by the complainant to recover damages, I am satisfied that the filling has been a nuisance to him, from which he has suffered and for which he has his remedy by action at law. Perrine v. Bergen, 3 Gr. 355.
The right of this court to interfere in case of a nuisance does not arise from the fact that a nuisance exists, but results from the circumstance that the equitable power of the court is necessary to protect the party from a future injury for which no adequate redress can be obtained by an action at law, or its interference is necessary to suppress interminable litigation for the recovery of damages for an actionable wrong. Carlisle v. Cooper, 6 C. E. Gr. 585.
It has not been made satisfactorily to appear that the litigation to which the complainant must x’esort will not be settled in one suit.
This case is not, in its equitable aspects, as the complainant insists, like the case of backwater from a dam which overflows the complainant’s land. The backwater will lie upon the land till the cause of its backing there is removed. Here, at any moment, the disturbance in the complainant’s lot may cease. In the one case the injury is certainly continuous until the dam shall be lowered or removed, while in the other it is as probable that the damage is now at an end as it is that it will continue, and if it now continues it is almost certain that in a short time, in obedience to natural laws, it will cease. In such a condition
The complainant's building is now badly wrecked and deserted by its tenants, and the possible future damage to him will be small in comparison to the injury which the issuance of either a preventive or mandatory injunction, at this time, will certainly work to the defendant. In such a situation the complainant must be left to his legal remedy. Quackenbush v. Van Riper, 2 Gr. Ch. 354.
The same reasoning must apply to the complainant's claim that he is deprived of his rights in the vacated streets. The damage to him by the taking away of these rights is small when compared to the injury which the injunction he seeks would work to the defendant. What those rights are, or indeed, if such rights exist at all, is, to say the least, doubtful and unsettled in this state, and such doubt is a reason why an interlocutory injunction should not issue.
The motion will be denied.