Seton Hall College v. Calumet Construction Co.
Opinion of the Court
On June 7th, 1909, the Calumet company made an agreement to erect an addition to the college building of Seton Hall Col
South Amboy Terra Cotta Company......... $800 15
Gustave L. Kimmerle....................... 51 03
Moses ESsberg ............................. 584 73
Spottiswoode Cusae Company............... 363 05
James McCullagh (first notice)............. 1,507 24
' “ “ (second notice)........... 850 57
The following claims are contested:
Glasby Lumber Company................... $4,200 00
Adamant Manufacturing Company........... 1,155 33
. Standard Concrete Steel Company......,.... 6,200 00
Maxwell & Dempsey........................ 2,000 00
Joseph Bleeker ............................ 2,300 00
The Browe Company....................... 904 21
These will be taken up and disposed of in the order named.
1. The Glasby Lumber Company Claim. — The stop notice on which this claim is founded is in proper form and demands that the owner shall pay to it the sum of $4:,000. The validity of the claim depends upon the proof of the proper demand upon the contractor and its refusal to pay. The notice was dated and served on‘January 27th, 1910; the contract between the claimant and the contractor required the claimant to furnish carpenter work and trim for the building for which the contractor agreed to pay the sum of $4,200. This was in the form of an estimate
The doctrine of these cases was approved by the court of errors and appeals in the case of Hall v. Baldwin, 45 N. J. Eq. (18 Stew.) 858, and must be considered as established law in this state. It is true that Vice-Chancellor Eeed, in Evans v. Lower, 67 N. J. Eq. (1 Robb.) 232, allowed a claim as valid where there had been a demand of an excessive amount; but this ease seems to me to be distinguishable from the case in hand; if not distinguishable, it runs counter to the general current of authority in this state, including McPherson v. Walton, 42 N. J. Eq. (15 Stew.) 282, a case Avhich has been generally followed.
2. The Standard Concrete Steel Company's Claim. — Th'is. company entered into a-contract with the Calumet company for the fireproofing of the building in question. The contract was originally for $20,000; there was an addition to it of $100, making the total contract price $20,100, on account of which $7,000 were paid in cash prior to the failure of the contractor. The contract provided for monthly payments of eighty per cent, of the work done during the previous month, the reserve of twenty per cent, being held back until the completion of the contract. The requisitions for December, 1909, and January, 1910, amounted to $6,200. For this amount two notes were given, one for $1,000, the other for $2,200. They both matured prior to the service of the notice of February 23d, 1910, and, undoubtedly, that portion of the claimant’s contract money was due at the time of the service of that notice. While the evidence of the demand is. not as full and complete as might be wished, still I think it is sufficient to justify the allowance of the claim for $6,200, with interest from February 23d, 1910. The remainder of the claim was not due at the time of the demand and notice.
The Remaining Claims. — There is an objection to all the other disputed claims, and that arises from their respective contracts. Their contracts provide that they shall be paid monthly on requisitions eighty per cent, of the value of the work done, and that the remaining twenty per cent, shall be withheld by the contractor until either the completion of the building or the completion of the work contracted for. All the demands that were made by these claimants included the deferred percentages; all the notices that were served included the same percentages. These percentages not having come due until long after the de
Besides the Mechanics’ Lien law does not have 'in view any dealings with unliquidated damages. Section 3 contemplates a dealing with fixed sums and not with unliquidated amounts. There is no machinery provided by which the owner can be certified as to the amount of unliquidated damages, nor 'any method provided by which he may be satisfied of the correctness of the demand; neither can the demand-be made accurate. The claimant would be unable to tell beforehand what the amount of his demand should be, and it would be very unsatisfactory for the owner to make any payments whatever on account of such claims. Everyone would have to be submitted to a jury before it could be paid. The owner would probably be right in refusing to recognize that kind of a demand for the reason that he could not be satisfied that the claim was correct.
The act contemplates that the owner shall pay only for labor and materials which have .been furnished for the building. A stop notice which is for unliquidated damages might include many things between the contractor and subcontractor which did not go into the building at all. Kirtland v. Moore, supra. Besides it appears that when the contractor failed these claimants
The claims which are allowed will be paid in their proper order of priority.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.