Behr v. Interlaken Constuction Co.
Opinion of the Court
This is a mechanics’ lien suit. When brought to trial before the court and a jury, it was withdrawn from further consideration by the latter, by consent, and submitted to the trial judge for determination on the testimony, evidence and exhibits offered and received, on a finding of facts and the law regarded as applicable.
The controversial question is whether plaintiff is entitled to special judgment against the land, owned at the time by defendant Interlaken Estates, Incorporated, title to which at the trial was shown to be in the Grassmere Development Company, body corporate, which was permitted to be added as a defendant. The answers of these defendants deny plaintiff’s right to a lien on the land and its reduction to special judgment against them as owners.
The suit arises in the following circumstances: On September 29th, 1927, the defendants, Schaffer, Koeppel and Weinstein, entered into a written contract with Interlaken Estates, Incorporated (the owner), for the purchase of a tract of land which had been mapped and divided into lots, upon which they contemplated building a number of houses. The consideration involved the payment of certain sums in cash and the execution of purchase-money mortgages. A number of other provisions relating to the securing of the purchase-money and the eventual payment were incorporated which need not be referred to specifically. It may be said, however, that on the payment of $24,000, on October 28tb, 1927, Interlaken Estates, Incorporated, agreed to deed to the purchasers certain of the lots; and on the payment of $25,000 on January 28th, 1928, other lots and tracts were agreed to be conveyed, while purchase-money mortgages for $55,750 each were to be executed at stipulated periods. An important modification of the agreement was made by the parties on October 27th, 1927, by an endorsement in writing, signed by them (see exhibit marked “Duplieate-P-2”), whereby the delivery and execution of the agreement was extended
A recital in the agreement was to the effect that it was understood that the purchasers intended to erect houses on the lots mentioned (one house on no less than fifty feet) and to place a first mortgage on the premises not to exceed $7,000; therefore it was further understood that the purchase-money mortgages would be subordinated and Interlaken Estates, Incorporated, would accept a mortgage of $650 on each house as erected, which would be credited on such purchase-money mortgages. It was then stipulated that the purchasers might take possession of the premises on the execution of the agreement, and within one week from the date thereof begin the erection of houses, not to exceed twenty-five. The agreement was accordingly executed and Schaffer, Koeppel and Weinstein (the purchasers) entered into possession of the tract of land involved, but were apparently unable to make the cash payment first stipulated, and secured the extension for the “delivery and execution of this agreement” to November 25th, 1927, subject to the cash payment of $12,000 on November lltli, 1927, and the balance of such payment on November 25th, 1927.
After taking possession, whether before or after October 27th, 1927, the date of the extension agreement, does not appear, the purchasers, in the name of the Interlaken Construction Company, contracted with the plaintiff (a boss carpenter) and others for the necessary labor and materials for the erection of the houses contemplated in the agreement for purchase. Plaintiff testified at the trial that with a gang of workmen employed by him he went to the premises during the second week in October, 1927, and began work and continued until November 22d, following, such work involving fifteen houses. On the latter date he was obliged to quit for the reason that he and his men were not being paid, and, as his statement goes, it would indicate that very little money
It is urged on behalf of plaintiff that he is entitled to more than a general judgment against the persons with whom he made his contract, that is to say, that he should have a judgment specially against the land on which the houses on which he and his men worked stand. It is argued that under section 7 of the Mechanics’ Lien act {Pampli. L. 1898, p. 538) his claim finds support, since the agreement for sale contemplated the erection of the houses, and by its terms a written consent on the party of the owner—Interlaken Estates, Incorporated—may be inferred in the same manner as though it had been actually given to him in writing, or so made for his benefit. If this be so, then it is contended that he is entitled to a judgment specially against the land, not merely a general judgment against the persons with whom his contract was admittedly made.
Since this appears to be the primary question of law involved in the ease, disposition of which will settle it as submitted, other question, such as whether the claim was filed in time, under the statute, and the amount really due, have not been considered.
A fair and satisfactory interpretation of the section will be found in Luce’s New Jersey Mechanics’ Lien Law (3d ed., 1923), p. 186, where it is said that “the consent required under sections 7, 9, 10 or 11 must lie such as clearly shows that the owner intended that his lands should be subjected to a possible lien for the contemplated work, or for the contemplated indebtedness. It must amount to a guaranty. While no particular form of words is necessary, the statutory requirement that such consent must be in writing indicates that the writing must contain words which unequivocally express such an intent. It would seem, therefore, that a writing would be insufficient if it merely expresses the owner’s consent that the tenant, or other person, shall erect a building on his lands, but says nothing pro or con as to who is to pay, or be chargeable therefor; and that it could not be helped by parol proof of intent, or implication from circumstances, in such case.”
A careful examination of the sales agreement in the present case, coupled with the extension of the date for the “delivery and execution,” does not disclose an intent on the part of the owner—Tnterlaken Estates, Incorporated—that its land should be subject to a possible lien or a consent to the erection of the houses thereon within the purview of section 7 of the Lien act. In fact, it now appears that the work and labor for which plaintiff seeks a recovery was performed before the date for “delivery and execution” of the agreement under tire extension, and before the purchasers had made any payment whatever on account of the purchase price of the property. The suggestion on the argument that the erection of the houses was a,condition of the sales agreement seems neither to be warranted nor a natural inference. What it does appear to indicate1 is that the houses as erected were to be paid for by the purchasers of the land—the so-called Wein
In Associates v. Davison, 29 N. J. L. 415, it was said that the “Lien law, so far as it operates to charge the lands of a party with a debt not contracted by him, or for his ultimate benefit, should be strictly construed. Such is the case when it is sought to charge the lands in pursuance of a consent in writing, where it can be charged in no other way. The owner of land who permits a building to be erected by another upon it, has this protection; until he consent explicitly in writing
The court has not stopped to consider in detail the testimony of the plaintiff at the trial in the present suit to the effect that Mr. Morgan, the secretary of Interlaken Estates, Incorporated, had by verbal statement guaranteed that he, the plaintiff, would be paid if he continued his work, or at least had in some way bound the corporation whereby the court would be justified in directing that a judgment should be specially entered against the land described in the lien claim. It is not perceived that it suffices to establish the necessary written consent contemplated or required by the Lien act, since whatever the conversations may have been, they apparently occurred after plaintiff realized that payment for his work was precarious and he either had or was considering stopping it. Moreover, the suit is not brought, on any alleged guaranty made by one with authority to speak for Interlaken Estates, Incorporated, but is made to resi entirely on the provisions of the Mechanics’ Lien act, particularly section 7 thereof. In fact no such guaranty is now claimed. In any event, it would seem that plaintiff can take nothing of the alleged conversation with Mr. Morgan. Strong v. VanDeursen, 23 N. J. Eq. 369.
In the circumstances, it is the court’s conclusion that plaintiff failed to prove that the written consent of the owner of the land within the intent and meaning of section 7 of the Mechanics’ Lien act was obtained by him, or by anyone for his benefit. He is not, therefore, entitled to judgment specially against the land in question.
A rule may accordingly be submitted discharging the lien and directing a judgment of no cause of action in favor of the defendants Interlaken Estates, Incorporated, and Grass-mere Development Company, body corporate, and against the plaintiff.