Jones v. Whittier
Jones v. Whittier
Opinion of the Court
The opinion of the court was delivered by
This is an action on mechanics’ lien, brought by the contractor against the owner. The building contract was in writing, and provided for payment of the contract price in installments as the work progressed. The provisions of the contract that are material to the present inquiry are those relating to the third and fourth payments, viz.:
“Third. When house is enclosed, except window and door openings and porch floor, $1,300.
“Fourth. When wall-hoard and patent wall plaster is on, $1,⅞00.”
There was also a provision that the contractor should buy certain materials from the owner, and that the cost of the same should be credited on the contract price.
It was conceded that the third payment was earned and made. The contractor claimed the fourth payment as due, and the owner refused to make it on the ground that the work excepted in the third payment, the window and door openings and porch floor, formed part of the requirements for the fourth payment and must be done before that payment would become due. It was conceded, or fully proved, that the wallboard and patent plaster were on, thus complying with the express requirements of the fourth payment. It was also admitted that the porches and windows and door openings had not been completed. Upon the owner’s refusal to pay the contractor abandoned the work and brought suit for the fourth payment, less credits for lumber purchased.
The case was tried oil the theory that if the work had progressed sufficiently to call for the fourth payment plaintiff was entitled to recover.
The assignments of error bring up the refusal of the court to nonsuit and to direct a verdict, the exclusion of certain
Under the assignments of error relating to the exclusion of evidence offered by defendant, the complaint is that defendant was prevented by rulings of the court from showing that, according to the usual and orderly method of constructing such a building as that in question in tills case, the wall-hoard and patent plaster should not he put on until the doors and windows were in, or, at all events, until the window and door openings excepted from the third payment had been constructed, without passing on the question whether such evidence was competent and relevant to the issue that was in trial, it is enough to say that the assignments of error do not point out the exclusion of any evidence of this kind. The overruled questions brought up by the assignments are as follows :
“(A If a contract provided that the third payment should he made when the house is enclosed, except window and door openings and porch floor, and the fourth payment provided that it should he due when wall-board and patent plaster are on, and it was admitted and was the fact that the windows were not in, that the window and door openings were not closed, the porch floors were not laid and the porches were not built, would or would not the fourth payment he due under those circumstances ?
“Q. Now, then, if a contractor had omitted from his third payment, enclosing of window and door openings and porch floors, and proceeded to put on wall-board and plaster, would the fourth payment, under this particular contract, read in the light of the custom of builders, be due?”
It is obvious that these questions did not call for testimony as to the custom of builders, hut for the construction that, in view of what the witness understood that custom to he, he himself would put upon the language of the contract. The questions were, therefore, properly overruled.
There was no error in the denial of motions to nonsuit and to direct a verdict. No grounds for the latter motion were stated. The grounds of the motion to nonsuit were that the
All the foregoing points, however, become unimportant in view of the position taken by the court in charging the jury. The trial judge held that the contract was complete and definite on its face, and needed no parol evidence to explain it, and that its construction was a matter of law for the court, and instructed the jury that as the undisputed evidence showed that the wall-board and patent plaster were on as required in the clause providing for the fourth payment, that payment was due under the contract, and that the only point for the jury to consider was the amount of set-off to which defendant was entitled for material supplied by him to plaintiff. This was equivalent to construing the contract on its face as entitling the contractor to his fourth payment when the wall-board and patent plaster were on, and as not calling for the work excepted in the third payment as a prerequisite of the fourth. We think this construction was right, and that if the parties intended that this excepted work was to be done before the fourth payment became clue it should have been so stated in the clause providing for that payment.
This view of the case disposes of all the assignments of error. The judgment under review will be affirmed.
For reversal—None.