Bierman v. Stiefel
Bierman v. Stiefel
Opinion of the Court
The opinion of the court was delivered by
This action is to recover rent reserved in a lease in which defendants in error, plaintiffs below, were lessors, and the plaintiff in error, defendant below, was lessee,
The declaration avers general performance by plaintiffs of all their covenants, and non-performance by defendant of his covenant to pay the rent reserved for the year commencing May 1st, 190?. Oyer of the written lease being craved by the defendant, the following covenant by plaintiffs appeared: “That in case of destruction or injury of the whole or any portion of the premises hereby demised by fire, he, the said lessor, will repair with all reasonable speed the destruction or injury done and place the premises in the condition in which they were, and for this purpose and to this end will keep the said buildings properly insured; also if the destruction or injury be total, or if the destruction or injury will deprive the lessee of the use of a substantial portion of the building or buildings on the premises, the rent above reserved and promised shall cease from the time of such destruction or injury until the premises are restored to the condition in which they wore prior to the injury or destruction.” Following this the plea avers that on April 11th, 190?, a fire so injured the said buildings as to deprive the defendant of their substantial use, and that the plaintiffs refusing to restore the premises to the condition in which they were prior to the fire, the defendant completed the restoration which was not finished until October 11th, 190?. To this plea the plaintiffs replied that they had, with all reasonable speed after the fire, restored the premises to the condition in which they were prior to the fire within twenty days thereafter. The only issue raised h}r these pleadings was whether the plaintiffs had restored the premises to the condition existing prior to the fire, before May 1st, 1908, that being the date to which rent was claimed. Under the lease the tenant was permitted to, and did, make substantial alterations to fit the building for restaurant purposes so that it was not, at the date of the fire, in the condition it was when demised, but much improved. It is not claimed by the plaintiffs that they restored the improvements made by defendant, for their contention at the trial was that they were only bound to restore tlie building to its condition at the date of demise and the case
At the close of the case the defendant moved for a direction of verdict in liis favor upon the ground that the lease, properly construed, required the plaintiffs to restore the premises to the condition theji were in at the time of the fire, and did not limit the obligation of the plaintiffs to the condition when demise was made. The trial court held, and properly, that the construction of the contract was a court question, and in construing the contract held that the plaintiffs, in order to comply with their covenant, were bound to restore the building to the condition it was in at the time of the fire, and the covenant was not satisfied by limiting restoration to conditions present when the demise was made. Whether this construction is correct, it is not now necessary to determine, for it was the law of the case as applied by the court, and settled in favor of defendant the only issue raised by the pleadings, but the court refused the direction upon the ground that the tenant having undertaken to complete the restoration required of the plaintiffs was bound to do it in a reasonable time, and therefore two jury questions were presented. First, when did the tenant complete the restoration as required by the lease, at which time it was held the suspension of rent ceased? Second, did the defendant use reasonable diligence in completing the work, for if not, then the rent would revive from the period when, with reasonable diligence, it should have been finished? Without expressing any opinion on the correctness of this rule, which seems to charge the defendant with diligence in the performanpe of an obligation of the plaintiffs, it is enough to say that it imports
A careful examination of this record fails to show that either party had in mind during the trial the question of diligence on the part of the defendant, in performing the covenant of the plaintiffs, for the claim of the plaintiffs was that they had done all their covenant demanded when they restored as of the time of the demise, while the defendant insisted that they had not done even what they admitted they were bound to do, and this raised a question of fact which became of no moment when the court decided that admitting plaintiffs did all they claimed, it was not a compliance with their covenant which was a condition precedent to their recovery. Therefore we have before us a record showing an action for rent on a written ¡ease with averment of general performance by plaintiffs of all their covenants, to which defendant pleads non-performance of a covenant by plaintiffs to restore partial destruction by fire, with replication by plaintiffs that they did restore to the extent they were bound, and. a ruling by the court that on the issues raised by the pleadings the defendant would be entitled to judgment. This condition of the record did not warrant the trial court in submitting to the jury a question not within the issues presented hv the pleadings, namely, whether when the defendant undertook to perform for his own benefit the covenant of the plaintiffs he had acted with reasonable diligence.
In Martinez v. Runkle, 28 Vroom 111, 122, the plaintiff declared upon an express contract for payment, at a specified price, for services which he claimed he had performed, and it was there held to be error to submit to the jury the question of quantum meruit upon an implied promise, that not being the case made by the pleadings.
“It is a cardinal rule for the control of a trial court that the questions submitted to the jury should he within the issues raised by the pleadings.” Excelsior Electric Co. v. Sweet, 30 Vroom 441.
The trial court having in this case submitted to the jury questions not put in issue by the pleadings, or within the
This case comes from the Supreme Court where the judgment was affirmed on error, but the conclusion we have' reached requires a reversal of the judgment below, and the awarding of a new trial, and it is so' ordered.
For affirmance—Yroom, White, JJ. 2.
For reversal—Garrison, Swayze, Parker, Bergen, Yoorhees, Bogert, Yredbnburgh, Congdon, JJ. 8.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.