Tuttle v. Cadwell
Tuttle v. Cadwell
Opinion of the Court
The opinion of the court was delivered by
This action was brought under section 3 of the Mechanics’ Lien law. The defendant, on the
The fundamental question presented by this appeal is whether this action can be maintained, under the third section of the Mechanics’ Lien law, against the owner as well as against the primary contractor. That section, as amended in
• This section of the statute imposes upon tire materialman the duty of specifying, as nearly as possible, the amount^ actually due him from the contractor. It also imposes upon the owner the duty of making payment upon being satisfied of the correctness of the materialman's demand, in case of the refusal of the contractor to do so.
Prior to the amendment of 1910 the failure of the material-man to state in his stop notice with absolute accuracy the amount of the debt due to him was fatal to his right to recover under this section. Reeve v. Elmendorf, 38 N. J. L. 125. And this was true even where the variation between the amount actually due and that claimed was slight, and had resulted from an honest mistake. The purpose of the amendment of 1910 was to relieve to some extent the burden resting upon the materialman, and this was done by providing that he should specify in his stop notice the amount due to him “as nearly as possible.” The theory upon which the case went to the jury seems to have been that this amendment obviated the necessity of any accuracy in the. specification of the amount due, and that if it should appear at the trial that the amount demanded was in exces's of that which the plaintiff was entitled to recover from the contractor, he could, nevertheless, hold the owner responsible for whatever sum was..shown to be actually due. We think that so broad a
There is another reason why this ease should hot have been submitted to the jury, and that is that the owner not only is not required to pay, hut is not justified in paying the materialman the amount of his claim, unless he, the owner, is satisfied of the correctness of the demand. The defendant notified the plain tiff that he was not satisfied, and gave as a reason the fac-t that' the Conrady-Stevens company denied that they owed the sum of money specified in the stop notice. The owner, of course, cannot assert his dissatisfaction without having any just cause for its existence; but; in the present case, not only did the fact that the amount was in dispute between the contractor and the materialman furnish such ground, but the proofs at the trial demonstrated the soundness of the defendant’s position; for, not only was there no attempt to show that the plaintiff’s claim as expressed in the stop notice was valid, but, on the contrary, it was admitted that the contractor’s challenge of the correctness of the
It is argued on behalf of the plaintiff that if the owner is satisfied of the correctness of a part of the materialman’s demand, he is bound to retain for the benefit of the latter sufficient moneys to pay the same, and that if he fails to do so the materialman has a right, under the third section of the Mechanics’ Lien law, to recover such portion from him. The answer to this contention is that the statute makes no such provision.. The demand referred to in it is to be of the amount which the materialman claims to be due to him. The satisfaction of the owner must be as to the correctness of this demand. He is not required to investigate as to the correctness of a part thereof; nor has he any authority under the statute to retain out of the moneys due to the contractor a sum sufficient to pay such part as he is satisfied is justly due.
For this reason also the judgment should be reversed.
It appeared in the proofs that after service of the stop notice the defendant paid to the Conrady-Stevens company , all moneys in his hands due under the primary contract, and took from them an indemnity bond to protect him against any liability to the plaintiff; and it is insisted that by doing so he estopped himself from denying the existence of such liability. We think not. He could not absolve himself from liability to pay the plaintiff’s just demand by such a course of action as that indicated; but the mere payment to the contractor of the moneys due under the contract could not operate to create a liability in favor of the plaintiff which, until such payment was made, had no legal existence.
The judgment under review will be reversed.
Reference
- Full Case Name
- LOUIS E. TUTTLE v. EDWIN B. CADWELL
- Cited By
- 2 cases
- Status
- Published