Brannworth v. Borough of Verona
Brannworth v. Borough of Verona
Opinion of the Court
The'opinion of the court was delivered by
At the trial, after refusing a motion to non-suit, the court directed a verdict against the plaintiff at the close of the case. The suit was based; upon a contract in waiting, between the parties, which provided for the erection by the plaintiff of a sewage disposal works in the borough.
The work was substantially completed as 'plaiaitiff alleges, according to the terms of the contract, but the borough a-e-fused to pay an unpaid balance due on the contract; and also refused to recogoaize a claim for damages arising out of delay by the borough for tha-ee months, in acquiring the locus in quo; and also refused to pay for the increased cost oE performance arising from a mistake in location of the locus, as well as the additional cost entailed, caused by an alleged mistake in the elevation of the works; and also for the cost of certain rock excavation not contemplated or provided for
The defendant interposed the defence of failure to complete the work; failure to produce the certificate of the engineer in charge, as required by the contract, as well as failure to produce an order in writing for the alleged extra work, as required by statute, and a general denial of its obligation to recognize the remaining claims.
There was testimony in the case from which a jury might reasonably infer the substantial completion of the contract. As a fact, the plant as plaintiff left it and at the time of the trial, and for almost two years, was in practical operation without any extensive expenditure upon it by the borough, and if any expenditure were necessary to complete it in any contract detail, quite apparently the item involved in the estimation of a jury might not be said to materially diminish the practical efficiency or completion of the plant, and the cost of such detail could easily have been estimated by the jury under the testimony.
Tinder our cases this situation presented a jury question, as to whether there had been a substantial completion of the work, due allowance being made by the jury for the failure of plaintiff to make good in sudh, details of the contract as were evidenced by proper proof. Feeney v. Bardsley, 66 N. J. L. 239. Dyer v. Lintz, 76 Id. 204; Jersey City v. Flynn, 71 N. J. Eq. 104; Anderson v. Odd Fellows Assn., 84 N. J. L. 176.
The same rule is applicable to- the plaintiff’s failure to produce the engineer’s certificate, if the latter unreasonably persisted in refusing it. By repeated adjudications of this court, the rule applicable to such a situation is now-familiar law, that the jury axe the judges of the right of the plaintiff to receive the certificate, in view of the alleged mental attitude of the architect in fraudulently withholding it. Byrne v. Sisters, &c., 45 N. J. L. 213; Chisin, v. Schipper, 51 Id. 1; Landstra v. Bunn, 81 Id. 680.
We there held that the necessity for the performance of the collateral work, and the bona fide conduct of the contractor in its execution, were questions for the jury. To the same effect also are Norcross v. Wills, 198 N. Y. 336; 13 Cyc. 160, and cases cited.
We think that thie issues in the case were therefore entirely of faqt, and presented a jury question. The judgment appealed from will therefore be reversed and a venire de novo will issue.
For affirmance—Parker, Black, JJ. 2.
For reversal—The Chancellor, Citiee Justice, Swayze, Trenchard, Bergen, Minturn, Kalisoii, White, Heppenheimer, Williams, Taylor, Gardner, Ackerson, JJ. 13.
Reference
- Full Case Name
- PERCY L. BRANNWORTH v. THE BOROUGH OF VERONA
- Cited By
- 2 cases
- Status
- Published