This action was tried in the District Court of Camden, without a jury, and resulted in a verdict for $355 in favor of plaintiff, from which defendant appeals. Some of the items recovered are not involved in this appeal.
The defendant employed a builder named Bittle to erect a house. Bittle engaged the plaintiff to do the plaster work for $360. After the plaintiff had performed some of the work, the relations between the defendant and builder were terminated. The defendant then orally agreed with the plaintiff that if the plaintiff would complete the work the defendant would pay him not only the cost of completing it, but also the amount due him from Bittle, which two sums totaled $360.
After the plaintiff started performance of this oral agreement, the defendant requested a written estimate of the cost of completion of the work, whereupon such estimate in the sum' of $100 was given him by the plaintiff. From this evidence a jury could find, as,the court, in effect, did find, that the oral agreement was the complete contract, and that
Such was the situation here and the judgment will therefore be affirmed.
Reference
- Full Case Name
- SAMUEL GARRISON v. HORACE E. LANE
- Status
- Published