Connolloy v. Board of Education
Connolloy v. Board of Education
Opinion of the Court
The defendant moves to strike out the complaint filed in this case on four grounds, all of them resolving, however, into the single proposition that the complaint discloses no cause of action.
Paragraph 25 of the specifications, which are made part of the contract, provides that "if either party to this contract shall suffer damage by delay, then he shall be reimbursed by the other party for such damage.” The same paragraph provides further that "in order to receive credit for delays the contractor shall make and file with the architect a written claim for allowance of time on account of such delays caused him within twenty-four hours of the occurrence of the same; but the time will not be extended unless the claim is found to be reasonable and that the contractor is entitled to such allowance under the contract.”
The complaint then proceeds to'state that the architect, “then and there being the agent of the said defendants,” granted extensions of time to the O. J. Smith Construction Company, "whereby the plaintiff was wrongfully hindered and delayed in the prosecution of his work.”
We think a fair reading of the provision first above quoted evinces that it is intended to protect either party from the hindering acts of the other, and does not apply to delays provided for in the contract itself. If for illustration the board were unable to obtain title to the property or were unable to eject a tenant or were unable to comply with the terms .of the contract respecting the payment of money, all of these due to its acts or failures, and for which the defendant would be responsible, it would constitute delays to the
Assuming, therefore, that the delays contemplated by the section relied upon by the plaintiff cover only those which were occasioned by the acts of the other party to the contract, the question remains whether the extension accorded to the C. J. Smith Construction Company, and which as a result occasioned delaj to the plaintiff, was the act of the defendant. On this point we think there can be no element of doubt. While the complaint avers agency, in no part of the contract is the architect made the agent of either party. On the contrary, where he is authorized to act it is in the nature of an arbiter and he acts in a judicial capacity. The case is similar to that of Gerisch v. Herold, 82 N. J. L. 605, in which it was held that questions submitted to the architect for his decisions are so submitted to him in a judicial capacity and his findings are conclusive and binding on the parties. It cannot be contended that if the C. J. Smith Construction Company’s application for an extension of time had been resisted by the board of education that this would have been effective to pre
In our view the complaint fails to exhibit a cause of action and the motion to strike out will therefore be allowed.