Moro v. Smith & Hoffman
Moro v. Smith & Hoffman
Opinion of the Court
The case was tried before the court and a jury in the Morris Circuit. The situation presented by the status of the parties is peculiar in its results.
The board of education of Harding township contracted with Smith & Hoffman for the erection of a school building; Smith & Hoffman, as general contractors, subcontracted the mason work to the plaintiff Moro. Upon completion of the w„ork the board refused to pay Smith & Hoffman the last installment because of alleged defective mason work. Smith & Hoffman in turn refused to pay Moro, who thereupon brought suit against them. Smith & Hoffman then impleaded the board of education. The board filed a counter-claim and defended on the ground that the mason work was not satisfactorily performed according to the specifications. The jury found in favor of Moro, as against Smith & Hoffman, in the sum of $1,595, and in favor of Smith & Hoffman, as against the board, in the sum of $1,529.
The board's evidence was that Moro did not strictly comply with the specifications in that he did not use a sufficient amount of “anti-hydro” (a water-proofing compound to be mixed with the cement stucco placed over the cement blocks), and that in places he neglected to apply it, the result of which was that the building leaked in certain places, and the walls became discolored because of dampness.
Moro’s evidence was thát the leaks were due to the failure of the specifications to provide for caulking the space between the window frame and the stucco, with oakum or cement; that the discoloration of the walls, owing to dampness, was due to placing plaster directly on the cement blocks, the specifications failing to provide for furring between the blocks and plaster, and that he did the work properly, as required by the specifications.
The rule will therefore be discharged.