District Court, D. Nevada, 2021

Singer v. C R Bard Incorporated

Singer v. C R Bard Incorporated
District Court, D. Nevada · Decided April 7, 2021
Singer v. C R Bard Incorporated

Trial Court Opinion

1 ERIC W. SWANIS, ESQ.

Nevada Bar No. 006840 GLENN F. MEIER, ESQ.

Nevada Bar No. 006059 GREENBERG TRAURIG, LLP 10845 Griffith Peak Drive, Suite 600 Las Vegas, Nevada 89135 Telephone: (702) 792-3773 Facsimile: (702) 792-9002 Email: [email protected] 6 [email protected] CASEY SHPALL, ESQ.* GREGORY R. TAN, ESQ.* *Admitted Pro Hac Vice GREENBERG TRAURIG, LLP 1144 15th Street, Suite 3300 Denver, Colorado 80202 Telephone: (303) 572-6500 Email: [email protected] 11 [email protected] C ounsel for Defendants 13 IN THE UNITED STATES DISTRICT COURT 14 FOR THE DISTRI CT OF NEVADA ROBERT SINGER, CASE NO. 2:19-cv-01579-JCM-BNW 16 Plaintiff, STIPULATION AND [PROPOSED] ORDER TO STAY CASE v. 18 (FIRST REQUEST) C. R. BARD, INC.; BARD PERIPHERAL VASCULAR, INCORPORATED, Defendants.

22 Plaintiff Robert Singer (“Plaintiff”) and Defendants C. R. Bard, Inc. and Bard Peripheral Vascular, Inc. (“Defendants” and collectively with Plaintiff, the “Parties”), pursuant to Fed. R. Civ. P. 26(c) and (d) and LR IA 6-2, respectfully request that this Court temporarily stay discovery and all pretrial deadlines until June 30, 2021 while the Parties pursue settlement. In support thereof, the Parties state as follows: / / / / / / 1 1. This case was part of the Multi-District Litigation proceeding In re: Bard IVC Filters Product Liability Litigation, pending before Senior Judge David Campbell of the District of Arizona.

3 2. Plaintiff alleges experiencing complications following the implantation of a Bard Inferior Vena Cava (“IVC”) filter, a prescription medical device. He has asserted three strict products liability counts (manufacturing defect, information defect (failure to warn) and design defect), six negligence counts (design, manufacture, failure to recall/retrofit, failure to warn, negligent misrepresentation and negligence per se), two breach of warranty counts (express and implied), two counts sounding in fraud (fraudulent misrepresentation and fraudulent concealment), an unfair and deceptive trade practices count, and a claim for punitive damages.

10 3. Defendants deny the Plaintiff’s allegations.

11 4. After four years, the completion of general issue discovery, and three bellwether trials, Judge Campbell ordered that certain cases, which have not settled or are not close to settling, be transferred or remanded to the appropriate jurisdictions around the country for case-specific discovery and trial. As a part of that process, he established a “track” system, wherein certain cases were placed on tracks either to finalize settlement paperwork, continue settlement negotiations, or be remanded or transferred.

17 5. This case was transferred to this Court on June 1, 2017 because at the time it was not close to settling. Recently, the Parties have begun settlement discussions and are scheduling a global mediation as to all of Plaintiff’s counsel’s IVC filter cases in June 2021. The Parties believe that a stay is necessary to conserve their resources and attention so that they may attempt to resolve this case and those of the other plaintiffs represented by Plaintiff’s counsel with cases pending before this Court.

22 6. Accordingly, the Parties request that this Court issue an order staying discovery and pretrial deadlines until June 30, 2021 to allow the Parties time to continue their settlement discussions and attend mediation in June if still necessary. This will further facilitate settlement discussions, prevent unnecessary expenditures by the Parties, and conserve judicial resources as well as place this case on a similar “track” as the MDL cases Judge Campbell determined should continue settlement dialogue.

27 7. A district court has broad discretion over pretrial discovery rulings. Crawford-El v. Britton, 523 U.S. 574, 598 (1998); accord, Republic of Ecuador v. Hinchee, 741 F.3d 1185, 1188-89 (11th Cir. 2013); Thermal Design, Inc. v. Am. Soc’y of Heating, Refrigerating & Air-Conditioning Engineers, Inc., 755 F.3d 832, 837 (7th Cir. 2014); see also, Cook v. Kartridg Pak Co., 840 F.2d 602, 604 (8th Cir. 1988) (“A district court must be free to use and control pretrial procedure in furtherance of the orderly administration of justice.”).

5 8. Under Federal Rules of Civil Procedure 26(c) and 26(d), a court may limit the scope of discovery or control its sequence. Britton, 523 U.S. at 598. Although settlement negotiations do not automatically excuse a party from its discovery obligations, the parties can seek a stay prior to the cutoff date. Sofo v. Pan-American Life Ins. Co., 13 F.3d 239, 242 (7th Cir. 1994); see also, Wichita Falls Office Assocs. V. Banc One Corp., 978 F.2d 915, 918 (5th Cir. 1993) (finding that a “trial judge’s decision to curtail discovery is granted great deference,” and noting that the discovery had been pushed back a number of times because of pending settlement negotiations).

12 9. Facilitating the efforts of parties to resolve their disputes weighs in favor of granting a stay. In Coker v. Dowd, 2:13-cv-0994-JCM-NJK, 2013 U.S. Dist. LEXIS 201845, at *2-3 (D. Nev. July 8, 2013), the parties requested a 60-day stay to facilitate ongoing settlement negotiations and permit them to mediate global settlement. The Court granted the stay, finding the parties would be prejudiced if required to move forward with discovery at that time and a stay would potentially prevent an unnecessary complication in the case. Id. at *3. Similarly, the Parties in the present case are engaged in ongoing comprehensive settlement negotiations with Plaintiff and the other plaintiffs represented by Plaintiff’s counsel and plan to mediate these cases in June 2021.

20 10. The Parties agree that the relief sought herein is necessary to handle the case in the most economical fashion yet allow sufficient time to schedule and complete discovery if necessary, consistent with the scheduling obligations of counsel. The relief sought in this stipulation is not being requested for delay, but so that justice may be done.

24 / / / / / / / / / / / / / / / 1 WHEREFORE, Plaintiff and Defendants respectfully request the Court’s approval of this 2|| stipulation to stay discovery and all pretrial deadlines until June 30, 2021 to allow the Parties to conduct 3|| ongoing settlement negotiations and mediation.

4 IT IS SO STIPULATED.

5 Dated this 22" day of February 2021.

6 WETHERALL GROUP, LTD. GREENBERG TRAURIG, LLP By: /s/ Peter C. Wetherall By: /s/Eric W. Swanis 8 PETER C. WETHERALL, ESQ. ERIC W. SWANIS, ESQ.

Nevada Bar No. 4414 Nevada Bar No. 6840 9 [email protected] [email protected] 9345 W. Sunset Road, Suite 100 10845 Griffith Peak Drive, Ste. 600 10 Las Vegas, Nevada 89148 Las Vegas, Nevada 89135 Telephone: (702) 838-8500 Telephone: (702) 792-3773 1] Facsimile: (702) 837-5081 Facsimile: (702) 792-9002 12 Counsel for Plaintiff Counsel for Defendants 14 IT IS SO ORDERED.

La WEES 16 BRENDA WEKSLER United States Magistrate Judge ig Dated this 7th day of _April 2021.

1 CERTIFICATE OF SERVICE 2 I hereby certify that on February 22, 2021, I caused the foregoing document to be electronically filed with the Clerk of the Court using the CM/ECF system, which will send notification of such filing to the CM/ECF participants registered to receive such service.

/s/ Shermielynn Irasga 7 An employee of GREENBERG TRAURIG, LLP

Case-law data current through December 31, 2025. Source: CourtListener bulk data.