New York Building & Improvement Co. v. Springfield Elevator & Pump Co.
Opinion of the Court
The plaintiff brings this action to recover damages for the violation of a contract made between the defendant and itself on the 5th day of March, 1898. On the 22d of October, 1896, the plaintiff, being engaged in the construction of a building, made a contract with the defendant to put elevators therein. The terms of that contract are not necessary to be considered, except so far as to say that the defendant guarantied to do the work to the satisfaction of the architect, and to make good any faults or defects in the work for which it was responsible, and in consideration the plaintiff agreed to pay a certain sum for the work, one half of which was to be paid in 30 days, and the other half in 60 days, after the completion of the elevators. It was claimed by the plaintiff that this contract was not completed, by the defendant, and the contract which lies at the basis of this action was the result of that claim. In that contract the making of the original agreement to put in the elevators was recited, as were also the facts that the plaintiff claimed that the contract was not performed; that there was still unpaid the sum of |2,620.26, which the defendant, was desirous of having paid before the complete performance of the contract. And in consideration o-the payment of that sum it was agreed, among other things, tha-. the defendant would perform “completely every provision and re
The defendant sought to prove, in the first place, that it had substantially completed the original contracts to put in the elevators, and it excepted to a ruling excluding evidence of that fact. That ruling was not error. The contract upon which this action was brought recited that it was claimed by the plaintiff that the elevators had not been completed, and the new agreement expressly was that the defendant should perform completely every portion and requirement of the original contracts. That provision in the contract necessarily implied that there was still something to be done to make the elevators comply with the requirements of the original contracts, and how that necessity arose is of no importance. The agreement was that the requirements of the contracts should be completely performed, and that Watson’s certificate to that effect should be final and conclusive upon the parties; and, when his certificate had been given that the contract of March 5th had not been performed, it was conclusive upon the parties. The rule in such cases is that, where one agrees to be bound as to the fact of the performance of a contract by the certificate of any person who is named therein as arbitrator, that certificate is conclusive, in the absence of proof of bad faith, corruption, or palpable error in the making of it. Smith v. Mayor, etc., 12 App. Div. 392, 42 N. Y. Supp. 522; Commissioners v. Sullivan, 11 App. Div. 472, 42 N. Y. Supp. 358, affirmed in 162 N. Y. 594, 57 N. E. 1123. If the certificate had been given corruptly or in bad faith, or there had been a mistake palpable on its face, that would constitute an affirmative defense, which must be pleaded, and unless it was pleaded the defendant would be in no situation to prove it. Everard v. Mayor, etc., 89 Hun, 425, 35 N. Y. Supp. 315.
Upon the question as to the reasonable cost of doing this work, it appeared by the testimony of the men who completed it that the amount expended was the reasonable cost. It appeared also by the certificate of Watson that that sum was actually paid. The plaintiff insists that that certificate was conclusive with respect to that matter, and that the defendant was not entitled to go beyond it. With that claim we agree. The agreement was that the certificate of Watson stating the amounts expended by the plaintiff in the per- « formance of the contract should be .conclusive evidence of those sums. Watson’s certificate was produced, and, within the terms of the contract, we think it was conclusive. But there was no evidence to contradict that of the plaintiff as to the reasonable value of the work u-cne by it. The defendant, when he had the case, offered to prove whether or not certain parts of the machinery which were mentioned in the certificate of Watson as defective could not have been procured and placed on the elevators, and that there was no necessity of ripping out all this machinery and replacing it with new. Then it offered to show the cost of buying the parts required and of repairing the machinery. We do not think that, within- the terms of the contract, the plaintiff was called upon to content itself simply with replacing parts of the machinery which were said tó be defective. It was entitled to have the elevator so completed that it would do the work as well as the defendant had agreed. In doing that it was not called upon to confine itself to the machinery manufactured by the defendant, or to use any portions of that machinery, unless it chose; but, by the express terms of the contract, it was at liberty to use the machinery of other manufacturers. If it saw fit to use machinery manufactured by other parties, it was authorized .to take so much of that machinery as might be necessary to finish the work completely and.perfectly. It was not called upon to patch up
We have examined all the exceptions taken by the defendant, and it seems to us that they are all covered by what has been said in this opinion, and that, within the principles laid down here, the trial court was correct in its conclusion; and the judgment must be affirmed, with costs. All concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.