New York & New Haven Automatic Sprinkler Co. v. Andrews
Opinion of the Court
In this action the plaintiff sought to recover the amount agreed upon for supplying the defendant’s factory at Astoria, L. I., with the “ dry pipe system of automatic sprinklers, in accordance with the rules and regulations of the New York Board of Fire Underwriters.” The contract is evidenced by a proposal signed by the plaintiff and accepted by the' defendant. It was therein provided : “ The work and materials under this proposal to consist of furnishing and placing one cedar tank of sufficient capacity on top of a foundation to be erected by J. F. Andrews. Enough sprinklers to meet the requirements of the New York Board of Fire Underwriters. All the necessary risers, pipes, fittings and labor to put in position all necessary sprinklers. The system to be erected so that it will drain back to Central Points. A cut-off valve on each floor of the two main buildings, a check valve under the tank, and one at a point where the city water enters the system. . Necessary gate .valves for the risers. * * * The work to be done subject to the rules of the New York Board of Fire Underwriters,” with further provisions as to painting the tank and protecting it from frost.
This was what under the contract the plaintiff agreed to do, and for this work it was to receive the sum of $1,400. It was not disputed but that the plaintiff completed this work according to the contract, and having finished it, it asked to be paid the contract
The contract plainly contemplated the doing of certain work by the plaintiff in the defendant’s factory, and by the contract certain obligations were imposed upon the defendant. The defendant was to build a foundation upon which the tank was to be erected. He was also to bring the water from the street inside the walls of the building, and while by the contract the money was earned when the plaintiff did the work that it was required to do, it was not payable until the certificate of approval was issued by the New York board of fire underwriters. The rules of the board of fire underwriters were introdued in evidence. They prescribe specific requirements for automatic sprinklers. The character of the sprinklers is specified ; distribution of sprinkler heads and arrangements for supplying pipes are provided for; certain tanks are required. There is also a provision for water supply, as follows: “Each sprinkler equipment must have at least two approved sources of supply, one of which shall be from a tank as herein provided for. * * * Each secondary water supply must be of sufficient quantity and pressure to fully operate for one hour at least seventyrfive per cent of all the sprinklers which are located in the largest room, or compartment enclosed within non-combustible walls, to which the system gives protection. * * * In cases where the risk is located beyond the reach of a fully organized paid fire department, provision must be made, to supply the pipes with water from an independent and reliable source, operating automatically upon the opening of a sprinkler head. Where steam or power pumps are accepted in connection with a secondary source of water supply, they must each
The work that the plaintiff was required to do was done as required by «these rules of the board of fire underwriters. Upon application to that board for a certificate, an instrument was given which certified that the buildings owned by the defendant “ have been fully equipped with automatic sprinklers by the New York & New Haven, Sprinkler Co., arranged for dry pipe system for the winter months.” The equipment is then described, and the certificate proceeds: “No certificate "can be issued for this equipment because it does not fulfill the requirements of this Board in the following particulars, viz.: The premises are located beyond the reach of a fully organized paid fire department, and provision is not made to supply the pipes with water automatically upon the opening of a sprinkler head, and the pump is not of 500 gallon capacity per minute, and there is no guarantee that steam will be maintained at all times to work pump.”
The inspector for the board of fire underwriters was called and testified that he inspected this work, and that the objection to giving the certificate was that “ there was no pump, or not a proper sized pump, and the city supply was not acceptable to the board. It was a question of water supply.” Upon the trial the complaint was dismissed on the ground that a certificate of the board of fire underwriters had not been obtained as required by the contract.
The contract contained explicit provision as to the work that the plaintiff was to do, for which it was to receive the sum of $1,400. It is not disputed but that the plaintiff performed the work which it was required to do. The contract also provided that this amount should be payable upon obtaining a certificate of the board of fire underwriters; and the correctness of the direction of this verdict depends .upon the proposition that this amount never could be payable until such a certificate had been obtained, irrespective of the cause that prevented its issuance. Here the plaintiff did not
All contracts which provide that the.contract price shall be payable upon a third party’s issuing a certificate are subject to the condition that where the production' of such a certificate is rendered impossible by any act other than that of- the plaintiff, or where such a certificate should have been supplied, but is unreasonably withheld or refused," the-plaintiff may recover, notwithstanding_the fact that no certificate is produced. This rule has been applied in many cases and is now the settled law of this State. Thomas v. Fleury (26 N. Y. 33) was to recover the final payment under a contract whereby the defendant was “ to pay the sums named in the manner and -at the times mentioned in the agreement, provided that in each case a certificate was obtained, signed by the architect.” The architect refused to give a certificate, but it was held that if he unreasonably and in bad faith refused, the plaintiff was not to be held responsible, blit could establish his right to recover by other evidence. “ The certificate is mere evidence of the substantial fact of performance; and if the kind of evidence of the fact stipulated for is obstinately and unreasonably withheld, a forfeiture of - $2,700 is not to be exacted, for that reason, from the plaintiff.” This has been followed in many cases and is now the settled law of this State. MacKnight Flintic Stone Co. v. Mayor (160 N. Y. 72) is the latest ease in which- this principle has been applied. In that case the plaintiff was to furnish “ all the materials and labor for the purpose. and make water tight the boiler room, * * * in the manner and under the conditions prescribed and set forth in the annexed specifications,” and was to turn the work over to the city in perfect order and guaranteed absolutely water and damp proof for five years from the date of the acceptance of the work. It was held that the reasonable meaning of this obligation was that the plaintiff agreed to make the boiler room water tight by following the plan and specifications, provided "it could be done in that wa-y;
Certainly, upon the principle here stated, if the plaintiff complied with its contract, did the work that the contract required it to do, according to the rules and regulations of the New York board of fire underwriters, and thus completed its work, the fact that under the contract the amount due the plaintiff was not payable until a certificate was issued by that board would not prevent the plaintiff from recovering, because such certificate was refused by reason of the failure of the defendant to comply with the requirements of that board, which requirements the plaintiff was neither bound to, nor had the power to comply with. It is quite evident that the plaintiff would have had no power to enter upon the defendant’s premises and provide a new pump for the defendant; nor could the plaintiff give a guaranty that steam would be maintained at all times to work the pump. Certainly, the plaintiff was not required to provide a fully organized paid fire department for this locality. Nothing in the contract required the plaintiff to comply with the rules and regulations of the New York board of fire underwriters as to the water supply. The plaintiff’s contract was performed when it installed in this factory the dry pipe system of automatic sprinklers, with the tank sprinklers and necessary fittings; and the plaintiff was not responsible because of a failure of the defendant to comply with
In neither of the decisions rendered upon former appeals in this action was there any principle established contrary to the view here expressed. On the first appeal (4 Misc. Rep. 124) the court held that the failure to obtain a certificate from the board of fife underwriters would not prevent a recovery if the plaintiff established that it had complied with its contract and the certificate was unreasonably refused. Upon appeal from the second judgment where the plaintiff had a verdict (38 App. Div. 56), the judgment was reversed because evidence that the system, did not and would not drain to central points, as provided for by the contract, and-of the negotiations ánd conversations between the parties leading up to the written contract, was improperly excluded.
This evidence was held competent upon the ground that it might have appeared that the certificate was required, not merely as evidence that the plaintiff had done the stipulated work, but for an independent value of its own; that it might very well be that the defendant had no faith in the efficacy of the plaintiff’s system as a protection against fire and would not have agreed to pay a penny for it by itself, but was well content to buy the appliances at the contract price on condition that the plaintiff - also obtain the underwriters’ certificate, which would lower the rates of insurance on the factory. Upon this trial such evidence was admitted, but it failed to show that the plaintiff assumed any obligation to obtain a certificate except that expressed in the contract, or that it assumed the burden of supplying any defects or any conditions required for. such a certificate that were not included in the work which it was to perform. It is undoubtedly true that the plaintiff understood that the defendant’s object in' having this appliance furnished was to procure lower rates of insurance, and that the defendant’s tenants had agreed to pay a proportion of the net cost of equipment of the factory after obtaining the certificate of the New York board of fire underwriters. That the appliance was ordered for the purpose of obtaining decreased rates of insurance, which were to be based upon obtaining this certificate, was understood by both the parties ; but if to obtain the certificate an additional pump was necessary or an additional water supply was to be furnished, the obligation to comply
It follows that the judgment appealed from should be reversed and a new trial ordered, with costs to the appellant to abide the event.
O’Brien and Laughlin, JJ., concurred; McLaughlin and Patterson, JJ., dissented.
Dissenting Opinion
The contract under which the plaintiff predicates his right to recover provides, among other things, that “ enough sprinklers ” should be put in and so equipped in defendant’s building as “to meet the requirements of the New York Board of Fire Underwriters,” and in thus equipping the defendant’s building the work, in all respects, was “to be done subject to the rules of the New York Board of Fire Underwriters * * *
For equipping-the building in this manner the defendant agreed to pay a specified price, but the contract expressly provides as to the price and the time when the same should become payable, as follows: “The above price includes all labor, transportation and traveling expenses and board of men, and shall be in full for all material furnished under this contract, and shall be payable after a certificate of approval shall have been issued by the New York Board of Fire Underwriters.”
Upon the trial the certificate of approval provided for in the contract was not produced, nor was any evidence offered tending to establish that the board of fire underwriters had ever granted such certificate, or that it had unreasonably or arbitrarily refused to grant the same ; on the contrary, it did appear that it had refused to give such certificate for the reasons (1) that the building in which the sprinklers were placed was located “ beyond the reach of a fully
It appeared upon the trial, and the fact was not disputed, that the object to be attained by the defendant in putting in the sprinklers was not so much to obtain protection against fire as it was to secure the certificate in order that a lower rate of insurance upon the building might be had, and, of which fact -the plaintiff was:fully informed prior to and at the time of the execution of the contract. It, therefore, entered into the contract with full knowledge that the certificate was an essential and a material part of the contract. Upon a former appeal this provision of the contract was considered and the law applicable to it laid down in an opinion delivered by Hr. Justice Cullen . (38 App. Div. 56), in which, referring to the ■certificate, he said: “ If such a certificate enables an owner to secure insurance at less rates than he would be required to pay in the absence of the certificate, then it was an essential part of the plaintiff’s contract that it should obtain the certificate. It might very well be that the defendant had no faith in the efficacy of the plaintiff’s system as a protection against fire and would not have agreed to pay a penny for it by itself, but was well content to buy the appliances at the contract price on condition that the plaintiff also obtain the underwriters’ certificate, which would lower the rates of insurance on the factory.”
It seems to me we are bound by this construction of the contract, and such construction necessarily requires an affirmance of the judgment appealed from. But independent of it, it seems to me the judgment upon principle should be affirmed. The rule is well settled that, where a plaintiff’s right to recover depends upon some condition precedent, a recovery cannot be had until that condi
In Mittnacht v. Wolf (6 N. Y. St. Repr. 44) the plaintiff presented to the defendant a proposition to furnish materials and to perform the necessary labor in erecting iron balconies in such a way as to equip the defendant’s building with fire escapes according to the requirements of the building department of the city of New York. The proposition was accepted and the balconies constructed. Thereafter an action was brought to recover the contract price, and the defendant defended upon the sole ground that the plaintiff had not performed according to the terms and conditions of the contract. Upon the trial no proof was offered to the effect that the balconies had been erected in accordance with the requirements of the building department, and for that reason a verdict was directed for the defendant. On appeal it was held that the plaintiffs were not entitled to recover under the express terms of the contract until such proof had been furnished. (See, also, Baker v. Johnson, 42 N. Y. 126 ; Ward v. H. R. B. Co., 125 id. 230.)
Under the express terms of the contract the plaintiff is not entitled to the payment therein provided until he has produced the certificate referred to. He did not produce it upon the trial, and its non-production was not the fault either of the New York board of fire underwriters or of' the defendant. Therefore, it seems to me that, for the plaintiff’s failure to produce the certificate, the complaint was properly dismissed.
I think the judgment appealed from should be affirmed, with costs.
Patterson, J., concurred.
Judgment reversed, new trial ordered, costs to appellant to abide event.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.