James Curran Manufacturing Co. v. Aultman & Taylor Machinery Co.
Opinion of the Court
The action was brought to recover the damages sustained by the plaintiff in consequence of the failure of the defendant to deliver three horizontal water tube boilers. It appeared that on May 1, 1899, the defendant made a written proposal to furnish these boilers. This was stated to be “specifications for contract.” It provides that, “ for and in consideration of the hereinafter-named amount» we propose to furnish.to Jas. Curran M’f’g Co: * * * 375 H. P. ‘ Cahall ’ ■ Horizontal Sectional Water Tube Boilers * * * for the sum of -as per letter. One-half payable on presentation of sight draft, with shipping receipt. Balance in 60 days from shipment,” and signed by the defendant per Thayer & Company, Inc. Annexed to this proposal was a blank to be filled up and signed if the proposal was accepted, and accompanying this proposal was a letter from the defendant fixing the price at $5,690. Subsequently, on May twenty-ninth, the defendant submitted to the plaintiff another letter, making the net price $5,500. Upon the same day the plaintiff filled up the blank attached to the proposal, adding the words in the blank left for date of delivery, “ and completed in 60 days.” The acceptance of this order was to be subject “ to our .acceptance of May 29/99,” and was signed by
“ These boilers to be delivered, erected and enclosed in mason work in 60 days from date of order or acceptance.” (Signed by the plaintiff.)
The plaintiff’s president testified that the letter of the defendant dated May twenty-ninth was received by him by ■ mail; that Mr. Thayer, the defendant’s agent, subsequently, and on the same day, called on the president of the plaintiff; that there was some discussion about the terms mentioned in the letter; that in their discussion it w.as agreed that the boilers were tó be delivered and erected sixty days from the date of the acceptance, and that while Mr. Thayer was in the plaintiff’s office he read the letter of May twenty-ninth, accepting the proposal upon the conditions named; that the terms of payment were discussed between the plaintiff’s president and Mr. Thayer and agreed to; that in that conversation it was stated that the building was to be completed before the first of October, and that the plaintiff could not get the building done unless the boilers were placed and erected within sixty days from the twenty-ninth of May. Mr. Thayer was called as a witness and testified that he received the acceptance of the proposition and the letter accompanying it on the twenty-ninth of May; that when he read the letter of acceptance he took some exceptions to the terms of payment, as they were most extraordinary terms, “ and terms that we very rarely allow, and I said that there would be some difficulty in regard to that; that I should have to take it up with the Aultman & Taylor Machinery Co., my principal, before definitely accepting that part of the acceptance; ” that in regard to the delivery of the boilers sixty days from date he said that there might be some delay over that, as that was an extraordinarily quick delivery, and the defendant
“We accepted your proposal of May 29th, ’99, and you accepted our order of same date, and on or about June 23rd you called on the writer and made the statement that you could not or would not deliver the boilers as per your proposal unless we extended the time for delivery and erection Thirty days, which extension we could not allow, as the building had to be finished and occupied by Sept. 1st,
“ All this places my Company in a very bad position' before my customers, and we want your Company to state your end of the maD ter in writing at the. earliest possible time, so that I can place it before Mr. Butler and the Architect.”
In reply to that letter, on the 6th of July, 1899, the defendant’s agent Wrote a letter to the plaintiff as follows : “ Your favor of the 30th ulto. duly at hand and noted. In regard to the order which you
“Immediately upon receipt of this communication from them we notified you of the fact of our not being able to complete this work within the time specified, and asked if it were possible to secure an extension, when you told us you could not give us any such extension, and referred us to the general contractor on this job, Mr. T. J. Reilly. Upon communicating with him we learned that the boilers had to be in operation by September 1st, at the very latest. We then communicated with our shops to that effect, and they replied that it was beyond their power to complete the work within that time. * * * Upon receipt of information from the Aultman <& Taylor Company that they could not meet this completion of the contract by September 1st, we notified T. J. Reilly and had considered your order canceled.,
“We beg to state that we are extremely sorry that we are unable to build these boilers for you, and assure you that, had we been able to meet the delivery in any possible way we would have been glad to do so; our inability being entirely due to the overcrowded condition of the iron and steel market and the inability to secure material quickly.”
At the end of all the testimony the defendant moved to dismiss the complaint. That motion was denied, the court stating: “ The specifications were modified by the written letters on both sides, which finally crystalized the contract as to the terms of payment. I cannot let you go to the jury on that issue at all. The letters themselves show that you could not deliver the goods on time, and the only question is whether the time of delivery was of the essence of the contract.” To that the defendant excepted, and then asked to go to the jury., to which the court replied, “ Certainly.” From
There was undoubtedly a modification by the plaintiff of the original proposition made by the defendant as to the time of payment and a limit of the time within which the boilers were to be delivered. By the original proposition made by the defendant there was no time fixed within which the boilers were to be delivered, and the terms of payment were one-half payable on presentation of sight draft with shipping receipt and the balance in sixty days from shipment. The plaintiff accepted the proposal upon condition that the payments should be one-third when all the materials for the boilers were delivered, and one-third when the boilers were set up and the mason work for the same put in complete, and the balance thirty days after the boilers were complete and tested according to the architect’s specifications ; and there was also a modification as to the time of the delivery which, instead of being unlimited, was limited to sixty days from the date of the contract. According to the plaintiff’s testimony, these conditions were unconditionally accepted by the agent of the defendant, and, if that was true, there was .then a completed contract. The testimony of the agent of the defendant, however, denied this acceptance of the conditions imposed by the plaintiff, both as to the time of payment and the time for the completion of the boilers. When, however, the defendant had refused to carry out its agreement and was asked to explain its position, the defendant’s agent, by the letter of July sixth, distinctly placed' the refusal to deliver the boilers upon its inability to deliver them within the time specified. No question was then made as to the time of payment, the order was treated as an existing order accepted by the defendant, but as having been subsequently canceled because of the inability of the defendant to deliver the boilers in time. That letter is entirely inconsistent with the claim of the defendant that no contract was ever made, or that any question had been raised as to the time of payment. The agent for the defendant there stated: “Had we been able to meet the delivery in any possible way we would have been glad to do so ; our inability being entirely due to the overcrowded condition of the iron and steel market and the inability to
Upon the whole case, I think the substantial question was fairly submitted to the jury by a charge which was unexceptionable, and that the finding of the jury that there was a valid contract between the parties was sustained by the evidence. I think the judgment should be affirmed, with costs.
Patterson and McLaughlin, JJ., concurred; Hatch and Laughlin, JJ., dissented.
Dissenting Opinion
I find myself quite unable to concur in the opinion of Mr. Justice Ingraham in this case, either as to the conclusions reached or the views expressed, and am impelled to express my reasons therefor.
The facts are very fully stated in the prevailing opinion, and I need not, therefore, discuss at length or in detail the preliminary .steps in the negotiations, which it is claimed resulted, as matter of ' law, in a contract for the alleged breach of which this action is brought. I think it perfectly apparent that it cannot be successfully maintained that the proposal from the defendant of May first, •containing specifications for the work, the letter from defendant of May twenty-ninth following, by which the proposed contract price was reduced from $5,690 to $5,500, and the order or acceptance of the defendant’s said proposal, made by the plaintiff in writing on the latter date, constituted a meeting of the minds of the parties so .as to consummate a contract between them. It will be seen, ji/rst, that the proposal and specifications contain no time of delivery, while the order or acceptance requires delivery and completion within r sixty days; second, it is an acceptance upon condition, viz., “ as per . amended proposition of even date; ” third, the “ amended proposition ” referred to was a written proposition from the plaintiff, dated (May twenty-ninth, the same day as the order, and containing matters • of substance not in any of the previous writings, and substantial ■ changes as to other matters. It required the boilers to be set “ as per drawings and specifications and subject to Architect’s approval,” .a condition not suggested in any previous writing. It changed •wholly the terms of payment as contained in the proposal from the
From this time there is no written instrument in evidence by which the defendant accepts these new conditions in terms. Indeed, it claims it never did accept them, and that, therefore, the minds of the parties never met in a consummated agreement. The prevailing opinion seems to hold that the letter from the defendant’s agent dated July sixth, which is fully set out in the opinion, is so inconsistent with the claim that no contract was made; that it shows so conclusively that no other question was open between the parties than that of time of delivery that, taken in connection with the oral testimony, a finding of the jury that any objection was taken to the terms of payment would have been clearly against the weight of evidence. I utterly fail to see the force of this reasoning. As I view it, such reasoning ignores the true situation and shifts the burden of proof unjustly. The plaintiff is here claiming for a breach of an express contract, and the onus is upon it to show that a contract ¿xists, to do which it is necessary for it to show that the conditions imposed by it were accepted by the defendant; not upon the defendant to show that they were rejected. It cannot be said, and is not claimed in- the prevailing opinion, that this letter alone is sufficient to show that the terms were accepted. Whatever else may be said of it, it must be conceded that it makes clear that the time of delivery was in dispute. May we indulge the violent
It appears that having denied a motion to dismiss the complaint, the court said, “ the specifications were modified by the written letters on both sides, which finally (when) crystaliz'ed the contract as to the terms of payment. I cannot let you go to the jury on that issue at all. The letters themselves show that you could not deliver the goods on time, and the only question is whether the time of delivery was of the essence of the contract.” Counsel for defendant said, “ I take an exception to your Honor’s ruling and ask to go to thé jury.” To which the court replied, “ Certainly.” The court then said, “ Counsel is not allowed to sum up on the point as to whether there was a contract or. not. I shall charge the jury that there was a contract. That is a false issue.” To this ruling counsel for defendant duly excepted. The court then proceeded with its charge, in which it did instruct the jury that “ The only dispute in the case, and which I leave you, is whether or not they did agree to do that within sixty days. * * * I charge you that there was a contract made between these parties.” Counsel for defendant duly excepted to the charge that a contract was made, and that the minds of the parties met with regard to the agreement of payment and with regard to the time of delivery. After discussion between counsel and court regarding the meaning of the exception,
It seems to me that the whole question was one of fact, requiring its submission to the jury, and that the refusal so to do was error. It follows that the judgment should he reversed and a new trial granted, with costs to the appellant to abide the event.
Laughlin, J., concurred.
Judgment affirmed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.