Miner v. Blume
Dissenting Opinion
I dissent from the conclusion reached in this case by the majority of the court. The plaintiffs have recovered a judgment for damages for the breach of a contract of purchase of an engine and boiler to be delivered for transportation upon a vessel, the damages arising from a delay of seven days in the delivery of the articles. The judgment recovered amounts to the sum of $183, and while there are four items in the plaintiffs’ bill of particulars, the recovery appears to have been made up from two of such items only, viz., one representing the actual expense incurred by the plaintiffs in the delay, amounting to $15, and the other being for demurrage in the detention of the vessel, seven days- at $24 per day, amounting to $168. It, therefore, appears that almost the entire claim is made up
It is true there was no denial by the defendants that they knew that the boat was to be held for the purpose of receiving the property, but I know óf no rule of law which requires the defendants to deny a fact which is not proved and not pleaded. The evidence of the amount of demurrage was received without objection, but that fact does not prevent this court from doing justice in the case, because the evidence of the defendants’ knowledge might have been supplied afterwards by the plaintiffs.
Judgment of the Municipal Court affirmed, with costs.
Opinion of the Court
The plaintiffs in this action are copartners, and in the course "of their business as. dealers in machinery entered into a contract with the defendants for the purchase of a certain hoisting engine and' boiler, which the plaintiffs, to the knowledge of the defendants, had agreed to deliver to a customer on a certain day on board a vessel which was held for the purpose of receiving such engine and boiler The defendants accepted the check of a third party in payment, and delivered to the plaintiffs an order upon the watchman having the property in charge for the delivery of the same, -stating that this would be sufficient to enable the plaintiffs to secure the engine. The latter hired a truckman, went to the place designated, and were refused possession of the property. After about -one week’s delay the engine and boiler were delivered on board the boat, and this action was brought to recover for the time and money spent by the plaintiffs in getting’ possession of their property, as well as for the expense of keeping the vessel in waiting, which , had cost''them twenty-four .dollars per day. Upon the trial the learned court appears to. have disregarded the claim of the plaintiffs for time spent in the transaction, but allowed for the cost; of keeping the vessel and for the money actually expended in telegraphing, street car fares, etc., and from the judgment entered defendants appeal to this court. . ■ '
The pleadings were verbal; the plaintiffs complained of breach of contract, and the defendants appeared, making a general denial and asking for a bill of particulars. This was ordered and the bill of particulars was served, in which, as a part of the damages, is set forth the following item: “ Demurrage of vessel held in waiting until title to property could.be effected by the1 defendants 7 days at
We think no material error was committed by the court.
The judgment appealed from should be affirmed, with costs!
Goodrich, P. J., Jenks and Sewell, JJ., concurred; Hirschberg, J., read for reversal.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.