Appellate Division of the Supreme Court of New York, 1901

Williams v. Daiker

Williams v. Daiker
Appellate Division of the Supreme Court of New York · Decided July 9, 1901 · Brien
71 N.Y.S. 247 (New York Supplement)

Counsel

Chas. A. Winter, for appellant., John E. Brodsky, for respondents.

Williams v. Daiker

Opinion of the Court

O’BRIEN, J.

The lien, as filed, contained statements in detafl as to the amount of sand furnished for different purposes, which must have been the result of some calculation, because given with exactness. The aggregate sum claimed in the lien was $5,932.79, giving a credit of $1,250, and claiming a balance due of $4,682.09. A statement- in the lien is that all the work and materials for which the claim is made have been actually performed and furnished; and the amount, now claimed, therefore, is as above stated. Upon the trial plaintiff admitted that the claim was excessive, that he abandoned the contract, and that the claim after the payment should be limited to $2,040, which was all that he was entitled to recover. The lien, as filed, therefore, was concededly for more than double the amount due the plaintiff. In determining whether the error or mistake was honest or intentionally false, we have the fact that *248the lienor himself had charge of the work, and that he himself was responsible for the error. Some of the cases relied upon, therefore, where the mistake was made by subordinates upon whom the lienor relied, are not applicable. Here the lienor knew he had not furnished sand for 3,000,000 brick, for he made his estimate on 1,250,-000 brick, and abandoned the contract when he found that sand for 3,000,000 brick was required. This is also true with respect to .sand for plastering. Thus he had abandoned the contract, and no satisfactory explanation is given for the statement that all the work and materials had been supplied for which the claim is made. It is impossible to escape the conclusion reached by the learned trial judge that the claim as made was “grossly exaggerated, extremely inaccurate, and clearly false.”

The judgment should he affirmed, with costs. All concur.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.