Norton v. New Amsterdam Gas Co.
Opinion of the Court
The facts, so far as relevant to the only question raised upon this appeal, seem to be as follows : On the 19th of September, 1898, the plaintiffs, under the firm name of Norton & Dalton, entered into a contract with the defendant, which provided that the plaintiffs should furnish the materials and tools, and execute the labor necessary for the laying of certain gas mains of the defendant in certain streets of the city of New York. The work to be done by the plaintiffs included the digging of the necessary trenches, the laying of the mains, the refilling of the trenches and the repaving of the streets. The payments were to be made on each alternate Thursday after the date of the first payment, which was agreed to be made on the second Thursday after the commencement of the work under the contract. These payments were to be based upon the estimates made by the engineer, and to be for work completed up to the point where the pipe was laid and the trench refilled and paved and the street cleaned.
It appears that after the making of the contract the plaintiffs entered into the performance thereof, and at the time of the suspension of the work, as hereinafter mentioned, there was a quantity of repaving, which remained to be done where pipes had been laid and the trench refilled and temporary paving done. The plaintiffs began work on the contract' some time in October, 1893, and ceased to work about the 23d or 21th of January, 1899. On the 25th of January, 1899, an estimate was given to the plaintiffs, showing that up to that date work had been done by them, amotinting, at contract prices, to $21,627.20, of which there had been paid $17,672.91, leaving a balance unpaid of $3,951.20. The plaintiffs demanded payment of this sum, which the defendant refused, unless the plaintiffs would give a bond in the sum of $10,000 to do the repaving which had not been done, and which the plaintiffs were required to do according to their contract. The plaintiffs refused to comply with this request, but stated that they would do
No controversy is presented by this record as to the amount of the recovery, the only question being as to whether the defendant was under obligation to furnish to the plaintiffs a permit from the department of highways for the opening of the streets, for the pur- ' pose of repáving which the plaintiffs, under their contract with the defendant, had agreed to do. .
There is, however, a question raised in respect to the form of the pleadings. It is claimed upon the part of the defendant that the-plaintiffs sued as for an amount due under the contract, and seek te recover as for a breach of the contract. But an examination of the complaint seems to us not to sustain this contention. The plaintiffs-by their complaint substantially intended to allege that they had performed all the conditions precedent- required by the contract up to the time when they ceased to work, but that they were prevented by the action of the defendant from the completion of the work, and, hence, as the contract was broken by the defendant, they were entitled to recover their damages.
The evidence shows that on the 18th of January, 1899, the defendant sent a letter-to the plaintiffs stating that it was in receipt of a notice, dated January thirteenth, from the department of highways requesting it to send to such department an order to repave the openings in question. In that letter the. defendant stated, “ as you are under contract with the New Amsterdam Gas Company te restore said pavement we request that you commence this work at once.” On the 26th of January, 1899, the plaintiffs wrote to the defendant stating that they were ready and willing, as they always had been, to relay the pavement over the openings under their contract and at the price named therein, but that for some reason, unknown to them, the department of highways was preventing them from doing so. They then asked the defendant to arrange the matter with the department and procure the necessary permit as required by the contract. ■ This permit was never furnished or procured by the -defendant, and, as has already been stated, the question is whether it was the duty of the defendant to furnish the same.
We think, therefore, that*the defendant was at fault in not procuring a permit for the reopening of the street, and, such being the» case, the judgment appealed from must be affirmed, with costs.
O’Brien, Ingraham and Hatch, JJ., concurred.
Judgment affirmed, with costs.-
Case-law data current through December 31, 2025. Source: CourtListener bulk data.