Merritt & Chapman Derrick & Wrecking Co. v. Tice
Opinion of the Court
The complaint avers that the plaintiff is a corporation, and that ;,the defendants were partners and owners of the barge E. W. Stet■sonj “ that at the special instance and request of the defendants, between the 3d day of December, 1898, and the 6th day of January, 1899, both dates inclusive, the plaintiff performed certain wrecking ■services and work and labor and furnished certain materials to the •defendants in and about the rescue and floating of the said barge E. W. Stetson which was ashore off the north shore of Long Island, near Jamesport, New York, and bringing the same to the port of New York, putting her upon a dry dock and delivering her to the •defendants. * "x" "x" That said wrecking services, work and labor sand materials furnished were of the fair and reasonable value of ‘.$4,249.48, no part of which has been paid, although duly demanded.” •Judgment was asked for the recovery of said sum. Before any
It is conceded by both parties hereto that if the contract averred in the complaint is a mayine contract for salvage, the State courts have no jurisdiction. Such undoubtedly is the rule. It does not follow, however, that a valid contract may not be made for compensation for work, labor and services, even though the subject-matter of the action might furnish the basis of a claim for salvage. The two matters are quite distinct. Where the contract is made to perform work, labor and services, either for a sum agreed upon or for a reasonable compensation for the services performed, such contract is good and may be enforced in personam. If there were no contract, a claim only for salvage might arise. The disposition, however, of such question rests upon different principles, and facts which- would support one would wholly fail in support of the other. Thus, in a case of salvage, the right of the person making the rescue to compensation is dependent solely upon the fact that the property is saved ; this is a condition precedent to his right to receive any award. The amount of the award rests in the discretion of the court. In the case of a contract to perform work, labor and services in connection with the rescue of a vessel, subject to marine perils, the right of recovery for such service depends upon its rendition pursuant to the contract, and the party entitled to recover for such services is not deprived of such right even though the subject-matter he wholly lost. This distinction is recognized in the cases (The Independence, 2 Curt. 350; Bondies v. Sherwood, 22 How. [U. S.] 214). A claim for salvage and a claim for work,
Upon the averments of the complaint in the present case the plaintiff will be authorized to prove a contract for work, labor and services, and, if established, recover therefor the fair value thereof, even though it might have become entitled to salvage for the services rendered, in the absence of a contract. It is clear, however, that in order to maintain the action, it must prove the existence of a contract for the rendition of the service. Under the pleadings, the plaintiff could not recover upon the theory that it was entitled to salvage, as its right of recovery is strictly in personam, and rests, upon contract.
It follows, therefore, that the order granting plaintiff’s motion for a new trial should be affirmed, with costs to the respondent to abide the event.
Van Brunt, P. J., Patterson, Ingraham and Laughlin, JJ.,. concurred.
Order affirmed, with costs to respondent to abide event.