Baker v. State
Opinion of the Court
The contract, for the breach of which this claim is made against the state, providés, in substance, that if the execution of the contract shall be suspended by the state at any time, for any cause, no claim for prospective profits on work not done shall be made and allowed, but the contractors shall complete the work when, the state shall order it to be resumed, and the date of such completion shall be fixed by the superintendent of public works. It is claimed on the part of the state that the breach complained of is but a “suspension,” under the above provision. If such claim is correct, it is plain that not only could no prospective profits be now claimed as damages, but neither could the sums which by the terms of the contract are to be retained until the completion of the work be now demanded. No breach of the contract would have occurred, nor would such sums have yet become due. But I am of the opinion that the action of the state upon and after the 14th of May, 1898, was an abandonment of the work referred to in the contract, instead of a mere “suspension” thereof. The contract was then terminated by the state, and the contractors were notified to that effect. No suggestion was made that the work provided for in the contract was to be thereafter completed, or that any time would be thereafter fixed for its completion. They were simply notified that the work was to cease, and operation under the contract was then brought to an end. Chapter 544 of the Laws of 1899 seems to be a declaration on the part of the state that it so considered the situation, and that if the contractors were willing to^ adopt that view, and take what was due them upon their contracts, and release all further claims, they would be paid upon that basis, including all moneys held by the state as security for the performance of the contract on their part. A clear abandonment of the scheme to improve the canal to the depth of nine feet is here shown, and it is very apparent that the breach of which the appellants complain is not the mere suspension above referred to.
We have, then, this situation: The contractors institute against the state these proceedings for a breach of its contract, and they claim not only the amounts due for work actually done by them thereunder, but also such damages as have naturally accrued to them on account of such breach. The amount still unpaid for work actually done is conceded to be $8,881.23, and the amount of money deposited with the state as security for the work is conceded to be $5,100. It is also conceded that, so far as they were permitted, the contractors have well and faithfully performed the work. The state having abandoned the work, and prevented further performance on the part of the contractors, it is clear that both the. sums of $5,100
But the further claim that the contractors make in this proceeding, that they are entitled to recover the profits which they would have made had the work proceeded to full completion under the contract, is not so clear. On the face of the contract, and on the .proof disclosed by the record before us, the total work which the contractors undertook to perform was, it seems to me, to “construct and finish” the improvement of a certain specified 5.87 miles of the Erie Canal, according to plans and specifications submitted with, and made a part of, the contract. Such is their undertaking in the first provision of the contract. No change in such plans and specifications has ever been made by the state, and it is conceded that, when abandoned, such work had not been completed. Such being the ■obligation on the part of the contractors, it would seem' from the proof disclosed by the record that the reciprocal obligation on the part of the state to permit them to prosecute the work to completion, and to pay them for the same, exists, unless the state has re■served to itself the right to end the work at any period of its progress. If such right is reserved, undoubtedly no loss of profits could be claimed as damages for a breach of the contract, because in that case there would be no breach. The court below has substantially held that such is the situation here, and has therefore rejected the contractors’ claim for such damages. If the solution of the question depends upon the construction of the terms of the contract alone, a ■careful study of that instrument will force the conclusion that no such reservation can be found within it. Notice that bids for the performance of the work upon the 5.87 miles covered by this contract would be received was published. Accompanying that notice, the plans, specifications, and statement of the engineer’s estimate for the work to be done thereon were submitted and filed as required by chapter 794 of the Laws of 1896. Under such notice and statement, these claimants made a bid, and affixed their prices per yard and per ■foot to the several estimated amounts of excavation, construction, or material contained in such statement. They were awarded the work, and thereupon entered into the contract which is set forth at length in the appeal book. By such contract, such plans, specifications, and statement are made a part of the contract. By such statement the total cost of the work and materials to be done and furnished; less value of old materials furnished by the state, amounted, at the agreed prices, to the sum of $98,760. The work done and materials furnished by the contractors up to the time the work was stopped amounted to $75,886.23. It is proven in the case that most of the estimated amounts given in such “statement” fell far short of the amounts actually necessary to finish the work according to the plans and specifications referred to in the contract. The total cost of such work, at the agreed prices, would amount to $165,953.75. Thus, at the time the work was abandoned, there was still unperformed and unfurnished, of the estimated work and materials, an
There are several provisions in the contract, specifications, and statement which it is claimed amount to a reservation by the state of the right to terminate, at any time it desired, the work under this contract. First, in the bid, which is written and signed by the contractors, at the foot of the “statement” of estimated amounts, etc., they offer “to construct and to finish, so far as the superintendent of public works shall direct, all of the work to which prices are affixed in the above schedule in all respects according to the contract and specifications,” etc., “ * * * this day exhibited. * * * ” But this offer is no part of the contract, and it is to be noticed that in the contract their undertaking is to do all the labor, etc., necessary to “construct and to finish in every respect” the 5.87 miles in question, and such work is to be done according to the plans and specifications furnished, etc. Here is a distinct undertaking on the part of the contractors to finish the contract according to the plans, and there is no provision or suggestion here that they are to do that work, or so much thereof as the superintendent of public works shall require. Under the contract, thev are required to- do it all. And the mutual obligation on the part of the state to permit them to do it all, and to pay them accordingly, is not .in any way limited by any provision here made. The limitation suggested in "the offer is not incorporated into the contract. Moreover, if such offer is to be deemed a controlling part of the contract, then the contractors’ obligation to do work would extend only to the amounts specified in the various classes named in the statement under which it is written, for the language there used is to “do all of the work to which- prices are affixed in the above schedule,” etc. It will hardly be claimed that either party expected that no more work should be done than was specified in that estimate, inasmuch as the contractor is distinctly notified that the quantities there named are “approximate only”; and the provision of the contract headed “Alterations and Directions,” etc., and the twenty-eighth specification, hereinafter referred to, are utterly inconsistent with that theory. So, also, the contractors in several instances did more work than was specified in the estimate; thus indicating that the parties understood that the amount of work to be done was not limited by that estimate. In all these respects the offer differs materially from the contract, and cannot be deemed to modify or control it. There are certain other provisions in the contract in which it is required that the work shall be “prosecuted at the times and in the manner directed by the resident engineer,” etc. These have reference to the method of carrying on the work, and clearly were not intended to provide that the resident engineer might at any time order an abandonment of the work.
It was further provided in section 28 of the specifications that “the state reserves the right to- increase or diminish the amount or amounts of any class of work from the amount shown on the bidding sheet,” and’in that event the amount of work required will be done at the rates named in the contract, and no claim for damages or
I have given so far only what seems to me a fair construction of the terms of the contract as it reads, and, if it can be shown that such a contract was authorized, I see no way by which the state can avoid payment of damages for its breach. But there are other considerations, which are barely suggested by the record and by the arguments, which to my mind have a very serious bearing upon the proper conclusion to be reached in the premises. Until we are furnished with a record which discloses all the material facts bearing upon the question of the authority of the superintendent of public
“None of the work called for by this act shall be contracted for until the state engineer shall have ascertained with all practicable accuracy the quantity of embankment, excavation, masonry, the quantity and quality of .all materials to be used and all other items of work to be placed under ■contract, and a statement thereof, with the maps, plans and specifications, ■corresponding to those adopted by the canal board, and on file in the office of the state engineer, is publicly exhibited to every person proposing or desiring to make a proposal for such work. The quantities contained in ■such statement shall be used in determining the cost of such work.”
The act then provides for filing the proper maps, etc., with the state engineer, and that no alteration shall be made in the specification or the plan of any work under contract during its progress, except an approval of such alteration be in writing, signed by the parties. “No change of plan which shall increase the expense of any such work, or create any claim-against the state for damages arising therefrom, shall be made,” unless a written statement is submitted to the -canal board, and their assent is obtained. It is here contemplated that the bids should be for specific work, and the price bid should determine the cost of the improvement contracted to be done. Safeguards are provided against any increase over the sum bid, and, if these directions were adhered to, it was reasonable to suppose that the aggregate of the sums bid would fairly determine the whole cost of the entire, improvements contracted for. If the aggregate of •these bids were within the $9,000,000, it would seem that the contracts, up to the bids made on each, would have been authorized. I assume that such was the fact, to wit, that the aggregate of these bids were within that sum, though this record shows nothing on the ■subject. If the sum of these bids practically exhausted the $9,000,000, I do not see how there remained any room for expansion in any contract; and the elastic quality in the direction of increase over the •sum bid in any contract would seem, under this theory, to have been
Our conclusion that the contract has been abandoned on the part of the state entitles the claimant to a judgment for money conceded to be due for the work actually done, and for the sum deposited as security for performance of the contract. And if the facts shall prove to be what has been suggested that the}'- really are, viz., that' the aggregate of the contracts, upon their face, as shown by the estimates and bids, was not in excess of the $9,000,000 voted, the plaintiff may be entitled to such damages as he can show he has suffered by reason of the abandonment on the part of the state before the sum of $98,760, the amount of plaintiff’s bid on the estimate presented' was exhausted.
The judgment of the court of claims is reversed, with costs, and a new trial before the court of claims is directed. All concur.