In re McDonald
Concurring Opinion
I concur in the conclusion of Mr. Justice HATCH. The scheme adopted by the statute imposed upon the Board of Rapid Transit Commissioners extensive power in the construction of this road. They were to provide the plans by which the road was to be constructed, and necessarily, were to determine the width of the cut, the thickness of the walls, and just how they were to be constructed; and from time to time, as the construction proceeded, they had authority to change the plans or the method of construction. The construction of the subway was to be paid for by the city; the equipment of the road was to be paid for by the contractor; and the statute defined what should be equipment and what should be construction. The contract that was made carried this definition of equipment into it. It cannot be doubted but that the board and the engineer had power to change the plans for the side walls of the tunnel, and provide that they should be thicker than provided for by the original plans, and contain open spaces to be used for the conduits by which the electric power was to be carried to the cars to be used in operating the road. I quite agree with the court below that neither the board nor the engineer could call that construction which was in reality equipment, and compel the city to pay for it; but the board had the right to determine how the side walls of the tunnel should be constructed, and that it should contain spaces to be used for the ducts or conduits for the electric wires, and such a provision would not make the whole wall a duct or conduit, nor the cost of constructing the walls cost of equipment. When the Rapid Transit Commissioners determined that the walls should be built wider than at first contemplated, and in that wall there should be left a space to be used for a conduit, it determined the question of the construction of the wall, which was an essential part of the subway construction. I think we should look at this wall as if its present method of construction had been provided for by the original plans, as undoubtedly it would have been if, at the time the original plans were made, it had been determined that electricity should be used as the motive power, and that the safe and efficient operation of the road required that the ducts for the transmission of this power should be inserted in the wall; and in that case I do not think it would have been claimed that the cost of the construction of the wall should be charged to equipment. The fact that the determination by the board to adopt electricity as the motive power, and that the proper method of supplying. such electricity to the cars was by ducts or conduits built into the wall, could not, upon any principle, make the cost of the necessary excavation or the building of the wall a part of the equipment, any more than if the board had originally determined to build the wall as it is now built. It is still the wall of the subway, which is a part of the con
As, however, the corporation counsel conceded on the argument that this was all construction or all equipment, and as I am clearly of the opinion that the walls are construction, and not equipment, I concur in granting the application.
Concurring Opinion
(concurring). I agree with Mr. Justice HATCH that the relator is entitled to recover of the city the cost of the extra excavation necessitated by the change of plans incident to placing the conduits for the electrical cables in the side walls of the tunnel and of constructing the vitrified hollow tile conduits or ducts. During the argument it occurred to me — but the point was not made by counsel for the respondent — that it would be inequitable to decide that this extra work was construction, the entire cost of which must be borne by the city, for the reason that, if the contractor is to be permitted to use these conduits without paying rental to the city other than the low rate of rental provided for on all construction originally contemplated to be made by the city, and on which his com
That this method of construction is superior, and will tend to insure greater safety to passengers and those working in the tunnel as well, is manifest. Had the idea been thought of or suggested originally, there can be but little doubt that it would have been adopted then. We cannot say that the change of plan was made solely for the benefit of the contractor. I think the fair inference is that it is for the benefit of the city and of the public as well. It does not appear how long this tunnel will last; but the fair inference is that it will last much longer than the period of 50 years over which the lease to the contractor extends; and probably, by repairs and recon
For these reasons, therefore, I vote for a reversal of the order, and for awarding a peremptory writ of mandamus according to the prayer of the petition.
Opinion of the Court
It cannot, I think, be doubted, but that both statute and contract contemplated that the commissioners should exercise very broad powers in providing for the construction of the tunnel, and in changing the detail of the plans after the same had been begun. In the exercise of power respecting changes the only limitation seems to be that departure should not be made from the general plan of construction. It logically follows, therefore, that whenever the commissioners, by reason of matters not contemplated when the contract was made, and the exigency of the situation required a change in method and manner of construction, they have the power to make such, change, and the contractor is bound to observe and comply with the directions given concerning it. As motive power was in process of development when the contract was made, it was not definitely determined what power should be used. When this subject was settled, it was agreed that electricity was the only power practicable. The commissioners, when this conclusion was reached, undoubtedly had the power to make such change as was necessary to conform the tunnel to meet the requirements of electricity as a motive power, and enlarge the same, in order to make provision therefor. Consequently, the increased excavation, which was found necessary for the walls of the tunnel in order to accommodate and apply the electric motive power to the best advantage, was clearly within the power of the commissioners to direct, and the work rendered necessary thereby became a part of the construction of the tunnel. Primarily, the construction of the tunnel was to furnish a place for a railroad. The whole purpose is to enable a railroad to be operated in this space, and when the space is excavated it becomes a place in which to put the equipment of a railroad; and this embraces cars, rails, motive power, and all else essential to the complete establishment of the same with the power which moves the trains over its tracks. The increased excavation, therefore, rendered necessary by the adoption of electricity as a motive power, was clearly within the power of the commissioners to order, the contractor to do; and, when done, it was properly chargeable to construction.
The vitrified ducts, which form a part of the solid wall of the tunnel, fall within the same category, and, if the enlargement of the excavation be construction, the wall is also. I am quite ready to concede that within a strict definition and in a technical sense these ducts, or hollow, vitrified brick, may be described as a conduit or way, and therefore within the words of the statute; but that is not the controlling consideration. The tunnel is that, and it is properly described as a conduit or way for the passage of cars; but because the cars' run through it does not make it equipment. The real question is, what are these vitrified ducts, within the meaning of the statute and the contract thereunder? It is evident that the statute and
Upon what principle of law can it be held that the contractor owns under the terms of this contract a part of this structure, and how, if vested with such ownership, can the city have a fee therein? The conduit which conveys the motive power to run the railroad consists of lead tubes, lined with copper, in which run the electric wires; and the actual conductor of the power is drawn through the ducts from the manholes. Because the vitrified brick chambers are used as receptacles for this conduit does not make it a part of the equipment, any more than does the open space of the tunnel make it equipment because the cars run therein; and the ducts do not become any less a part of the solid wall because they are used for holding the conduits which carry the live electric wires. As we have before observed, the contract itself contemplated a severable interest of property rights, distinct and independent. No construction of it ought, therefore, to obtain, which makes such rights joint, instead of several, and which gives a part ownership in the fee of the tunnel, when the statute vests it absolutely in the city. It is to be borne in mind that at the expiration of the lease the city is to take and pay for the equipment, and intermediate that time it has a lien thereon. It must follow that if the city for any reason refuses to take and pay for the equipment upon the termination of the lease, the contractor will have the right to remove the same. He has title to the property, and is either entitled to be paid for the same, or have the right to take possession. This is his legal right, if he has title thereto. The city, upon its part, is authorized to enforce its lien against the property of the contractor, and is invested with all legal remedies in enforcement of the same in the event that the contractor is guilty of a breach of the contract. Suppose the city forecloses its lien, and sells the vitrified brick, which has become an integral part of the wall, what would it deliver to the purchaser, and how would the latter get possession of the property thus sold? A judgment of foreclosure would not provide for a destruction of the wall of the tunnel, as it would not be the appropriate relief in such an action, and a purchaser could take nothing unless he acquired the right to destroy a portion of the wall. Certainly, neither the statute nor the contract contemplated such a result. The presence of the vitrified brick does
It seems to me, therefore, that as the commissioners could have originally authorized the enlarged excavation and this method of constructing the wall for the purpose for which it is to be used, they possessed the same power after determination was made to use. electricity as the motive power, and they had then the same reserved power to direct the construction of both tunnel and wall in this manner as they had in the beginning. When the commissioners so determined, the contractor had no alternative but to obey and construct the tunnel and its walls in that particular manner. The engineer in charge of the work, and every one in authority, have placed this construction upon the statute and the contract, and determined what is the physical fact — dhat this vitrified brick was an integral, inseparable part of the wall. Being such, the city has the .absolute title to the whole structure, and it seems to me absurd to sqy that the contractor can have any ownership therein, or the city any.'■lien thereon. If this view obtains, it necessarily follows that the contractor became entitled to be paid for the items for which the warrant was directed to be drawn. There are some small items of steel, expanded metal, and cast iron, which thje record does not make clear whether they are a part of the structure. I do not understand, however, that there is any dispute but that the contractor is entitled to be allowed those items, as forming a part of the construction if our view obtains as to what constitutes equipment and what construction. If otherwise, as' to these items an alternative writ would be necessary.
VAN BRUNT, P. J., and McLAUGHLIN, J., concur.