Laing v. Pelton Water Wheel Co.
Opinion of the Court
This is ah action on an assigned claim by the Carroll-Porter Boiler and Tank Company to the plaintiff to recover a balance of $9,369.28, with interest, on a contract for the manufacture and sale of merchandise consisting of riveted steel pipes made and delivered by the plaintiff’s assignor to the defendant between the 3d day of June, 1898, and the 28th day of .August, 1900. The defense is the breach of an implied warranty that. the pipe in question, being a manufactured article, should be merchantable and reasonably adapted to the use for which if was intended, to wit, the carrying of water under high pressure for. the purpose of furnishing power for what are known as hydro-electric installations in the Republic of Mexico.
The defendant in its answer admits the sale of the merchandise in question but sets up as and by way of offset or counterclaim, that the defendant was compelled to lay out and expend large sums of money on the alteration and repair of the pipe and its accessories in order to make the same, as far as possible, answer .the purpose for which it was intended, and in replacing large portions thereof with new pipe where the pipe was so imperfect as to make it impossible to make the same water-tight; that the said defendant was thereby greatly hindered and delayed in the carrying out of contracts for the purpose of which said pipe and accessories had been ordered, all to the damage of the defendant in the sum of $11,500, which said sum the defendant offset and counterclaims against the alleged cause of action, in the complaint set forth.
They were two kinds of pipe contracted for, a flanged pipe for the bulk of the installments and a slip-joint pipe for an installation known as the San Miguel. So far'as the flanged pipe is concerned,we are satisfied with the conclusion of the learned referee. A dif
It- seems to me that, taking all of this testimony together there was a waiver of acceptance upon delivery, and that the time for inspection was postponed until the pipe should arrive in Mexico. After it reached Mexico there were renewed complaints of the condition of this pipe. On December 4, 1899, Ticer telegraphed “customer rejected Fourteen seventy-four,” the San Miguel job. On December 5, 1899, plaintiff’s assignor wrote : “ If the pipé is not yet in position they have no way-of telling what the leaks will amount to. * * * For a man to go on the ground as their superintendent has and condemn work without trying it is not very great proof of his supposed experience.” Thereafter' Mr. Porter of Carroll-Porter Company, plaintiff’s assignor, went personally to Mexico with an employee, and worked for some time installing this line. While he was there plaintiff’s assignor wrote to defendant January 5, 1900: “ There is no question in our mind but that this pipe will be made perfectly satisfactory and we can guarantee such results, such being the case, coupled with the fact that we are making shipments on your other contracts right along, we would ask that you as early as possible send us, if not settlements for old accounts, an amount which would be equivalent.” ■
The line nevér did hold water. Mew material had to be bought and substituted to some extent; and the defendant in making the line good, expended various sums of money. The referee l^as found that the difference between the value of the San Miguel line as it was and as it would have been if said defects had not existed "was $1,121.02. . '
It seems to me, taking all the facts together, that the plaintiff’s assignor waived acceptance upon delivery in Mew York and postponed inspection and insisted upon actual installation of the line; and that under these circumstances they are estopped from' claiming that the implied warranty of a manufacturer did not survive delivery
Under the facts as here developed, the judgment should be modified by reducing the amount thereof by $1,121.02, the sum found by the referee, and as so modified affirmed, without costs to either party.
Patterson, P. J., Ingraham, Laughlin and Scott, JJ., concurred.
Judgment modified as directed in opinion, and as modified affirmed, without costs to either party. Settle order on notice.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.