People ex rel. Sawyer v. Board of Railroad Commissioners
Opinion of the Court
It seems to us plain that the determination of thé Board of Bail-road Commissioners in granting the certificate to the respondent, the Buffalo, Lake Erie and Niagara Bailroad Company, in the proceedings now under review cannot be sustained as, in an' important respect, it is contrary to the decision of this court and of the Court of Appeals in reversing the determination granting the former certificate to the Niagara' Transfer Bail way Company. (103 App. Div. 123 ; 184 N. Y. 575.) That decision refused'sanction to a like certificate for that portion of the proposed road fronting the Niágara river between Buffalo and Tonawanda, and along the bank of the canal a short distance removed therefrom between such cities. The reasons for reversing the determination granting that certificate were given in the opinion, of this court on "rendering that decision and need not be here repeated. It is sufficient to state‘that the
Other important reasons also impel us to reverse this determination. It appears that the Federal government has entered- upon a plan of improving the channel of the Niagara river which .involves the construction of a ship canal about 400 feet wide and 23 feet deep to connect the waters of Lake Erie with the waters of the Niagara river below Black Bock, by going through the old Black Bock harbor, and which, in combination with the enlarged ' Erie canal, will give a waterway adequate for the largest lake vessels from Lake Erie to the deep and quiet waters below the upper rapids of the Niagara river and on down to Tonawanda. One effect of this will be to permit vessels, to avoid the rapid current.of the river, which at the present time is a serious menace to the navigation thereof and to the commercial interests centering upon it. Greatly increased harbor facilities will also be afforded and opportunities opened for much additional space for dockage. Several thousand acres of land will also be made available for manufacture ing purposes along the water front between Black Bock- and Tonawanda. This improvement will cost several millions of dol- • lars, and already Congress has. - made two appropriations, one of $800,000 and one of $700,000, a considerable portion of which has already been expended. The work will cover a large portion of the river along and near which said respondent proposes to fun two of its railroad lines. The testimony shows that if the lines are built they will-practically nullify all the benefits-sought-to .be accomplished by the government in making the improvement, and will , require the appropriation by such respondent to its uses of much of the lands which would otherwise be made available for manufacturing industries,, and will render the remainder of such lands altogether undesirable for. such purposes. These portions of the pro
There is also a motion here on the part - of said respondent to quash the- writ of certiorari obtained by the Buffalo Frontier. Terminal Railroad Company to review'the determination of the Board of Railroad Commissioners in granting the certificate in question.
In view of the conclusion we have reached in the foregoing discussion of the case on the merits, a decision of this motion cannot be of much consequence, nevertheless as the motion is here it must be disposed of. It is urged on behalf of said respondent that under the authority of People ex rel. Depew R. Co. v. Comrs. (4 App. Div. 259) and of People ex rel. Ticonderoga Union Terminal R. R. Co. v. Board of R. R. Comrs. (113 id. 894) it is entitled to have the writ quashed. Those cases are not authorities to that effect. In the Depew case the writ was sued out, the same as here, by a rival
The motion to quash such writ should be denied, without costs, and the determination of the Board of Bailroad Commissioners reversed on the law and on the facts, with fifty dollars costs and. disbursements to each relator.
All concurred.
Motion to quash , writ sued out by the Buffalo Frontier Terminal Bailroad Company denied, without costs, and the determination of. the Board of Bailroad Commissioners granting, certificate.to tlie-Buf. falo, Lake Erie and Niagara Bailroad Company reversed On law-, and facts, with fifty dollars costs and disbursements to each relator.