St. Goerge Contracting Co. v. City of New York
Opinion of the Court
On September 10, 1907, the defendant, the City of New York, entered into a written contract with one Engeman for the construction of reinforced concrete retaining walls on Jay and South streets, in the borough of Richmond, in connection with a public improvement known as the St. George Ferry Approach. This contract was based upon printed specifications and on plans and drawings which were intended to be co-operative, and all of which taken together defined the contractual rights and duties of the parties. The contract was awarded to the lowest bidder after advertisement, as provided by statute, and the bids submitted were required to be not in a lump sum for the work as an entirety, but based upon certain units which entered into the completion of the"work. These units were set forth in printed proposals for bids, and their amount stated, but stated to be approximate only, and all bidders were called upon to verify these approximations at their own risk. Among the units so stated approximately was one as follows: “ (3) 23000 cubic yards óf Excavation.” The plaintiff, being the lowest bidder, was awarded the contract above referred to. This contract" bound the city to pay the contractor “for excavation, per cubic yard, the sum of Three and 00/100 Dollars ($3.00).”
The specifications contained a clause as to excavations as follows: “ All excavation will be figured to the toe line in the front and to the heel of the wall ,at the back, in perpendicular lines; the contractor to do all the necessary shoring and to include the cost of same in price bid for excavation. All excavated rocks and boulders shall be carefully placed on the heel of the base of the wall and
The contract required the contractor to begin work when notified by the president of the borough of Richmond. A notice was given to begin such work on November 1, 1907, and the work was then begun. It happened, however, that the Baltimore and Ohio Railroad. Company owned some lands immediately ad joining the land of the defendant. The railroad company was engaged in carrying out certain improvements of its own which required considerable excavation, for which it used large steam shovels. Between the signing of the contract here in question and the beginning of work under it the railroad company, without the consent of either party to this contract and presumably by mistake, entered upon the land of the city and excavated and carried away some 1,175 cubic yards of the surface material. This matter so excavated is described in the testimony as mainly “hardpan.” It is testified- that the cost to the plaintiff of excavating and disposing of this material as provided in the specifications would have been about fifty cents a cubic yard. When the city came to make payments under its contract, it refused to pay the contractor for the material excavated and taken away by the railroad company. This action is brought by the plaintiff, which as assignee of the contract with Engerman carried out the work of erecting the retaining wall, to recover at the rate of three dollars a yard for the material so excavated and carried away by the railroad company. Its claim is that the act of the railroad company inured to the plaintiff’s advantage by its adoption thereof, and it claims thereby performance of its contractual duty as to this excavation. In other words, it claims that it is to be considered as having done
The plaintiff further insists that the question of performance was not at issue at the trial under the allegations of the complaint and the denials of the answer. It contends that it alleged full performance and the answer of the defendant did not deny the allegation of full performance, but in this contention we think the plaintiff is clearly in error. On the theory upon which the plaintiff came into court, namely, full performance as to the excavated material, it failed to make out its case. It now contends, however, that it has proved substantial performance and should be allowed the contract price for the excavation in controversy, less such damages as the defendant may have suffered by the carrying away of the- excavated
This ease is not without apparent equities in favor of the plaintiff, but we are unable to interfere with the judgment of the trial court on the record now before us.
The judgment should be affirmed, with costs.
Jenks, P. J., Burr, Thomas and Rich, JJ., concurred.
Judgment affirmed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.