Riley v. Durfey
Opinion of the Court
' The plaintiff instituted the above-entitled action to foreclose a mechanic’s lien. Patrick J. Egan was the general contractor and William J. Durfey and Lucretia D. Ash were the owners of the. premises, the remaining parties defendant being lienors subsequent to the plaintiff. It was stipulated’that, the amount due from the owners was $825, ££ and that the said sum of Eight hundred and twenty-five dollars is applicable to the payment of the Mechanic’s Liens filed by the plaintiffs and’.the defendant lienors above named which maybe adjudged'valid,” etc. It was also ,££ conceded by all parties appearing ón the trial of this action that the work, labor and services for which a claim against the defendant Patrick J. Egan, and an alleged lien
The ground of the decision of the court against the hen of the plaintiff is that the notice of lien alleged in the alternative that “The labor performed and to be performed, and the materials furnished and to be furnished, excavation for cellars and the furnishing of sand and gravel used in the erection of certain stores ⅜ * ⅜ Flatbúsh avenue, Brooklyn, and the agreed. price and value thereof is Fifteen Hundred and eighty-six -⅜⅝ dollars,” and that this failed to comply with the requirements of the law, as laid down in Finn v. Smith (186 N. Y. 465). There can be no serious question that if this was all that the notice contained • it would be fatally defective. (Felgenhauer v. Haas, 123 App. Div. 75, 77.) The notice, however, contained these additional averments: that “The amount unpaid to the lienor for such labor and materials is Four hundred and Fifty-six -⅜⅛ dollars,” and that the “ time when the first and last items of work were performed and materials furnished, is work began Oct. 29, 1908, ended March 31st, 1909.” There is not, as in Felgenhauer v. Haas (supra), any allegation that the work and materials were “Actually used and employed in the erection of buildings,” etc. The most that can be spelled out of the averments of the complaint is that the “ labor performed and to be performed, and the materials furnished and to be furnished” are of the “agreed price and value” of $1,586.56, and that the “ amount unpaid to the lienor for such labor and materials is” $456.56. There- is not in the aver-, ment that “the time when the first and last items of work were performed and materials furnished, is work began Oct. 2.9, 1908, ended March 31st, 1909,” any statement of the mate
This is a statutory matter, and while the statute is to ■ be liberally construed, we believe that no case will be found where the averments of the notice of. lieu have been permitted to be helped out by evidence upon the trial. Indeed, appellant concedes that this cannot be done, but he urges that the stipulation of the parties “that the work, labor and services for which a claim against the defendant Patrick J. Egan, and an alleged lien filed by them respectively against the property of the owners, the defendants Durfey and Ash, was done and performed to the satisfaction of the owners and contractor,” operated to supply the failure to aver that the work had been completed. It is to be observed, however, that' the stipulation makes no reference whatever to materials furnished; it merely has reference to the “work, labor and services,” which “was done and performed to the satisfaction of the owners,” etc., but this is far from showing that the plaintiff had furnished any materials, or that all of the labor and materials contemplated by his contract had been . made use of by the defendant owners.
The judgment appealed from should be affirmed, with costs, the costs to be paid by appellant personally, as the fund is not sufficient to, fully pay all of the claims, which rest upon valid liens.
Judgment affirmed, with costs, the costs to be paid by appellant personally, as the fund is not sufficient to fully pay all of the claims which rest upon valid liens. - .
Case-law data current through December 31, 2025. Source: CourtListener bulk data.