R. Young & Bros. v. Snedeker
Opinion of the Court
' The defendant had entered into a contract with one Sherwood, a contractor, for the erection of a dwelling house, in which he undertook to pay for -the work and material in five payments as the work progressed. After the second payment had been made, and before another installment became due, Sherwood gave to .plaintiffs (material men) an order on account of his contract for the payment of $1,376.26, as follows: “Six hundred ($600.00) Dollars when plastering is completed. Seven hundred seventy-six 26/100 ($776.26) Dollars when the trim is on, ” which was accepted by defendant. It appears that within a few days after the order was accepted, and before another payment became due under the contract, Sherwood abandoned the work and it became necessary for defendant to finish, the job himself. It also appears from evidence given upon the part of the defendant that the plastering was not completed and the trim was not on. The learned county judge treated the order and acceptance as an independent contract for the payment of money. In this I think he was in error. It seems clear that it was the intention of the parties that the order should be conditional .upon the contractor’s earning the amounts specified under his contract, and the question of fact ■ as to whether anything was due ought to have been submitted to the jury.
It follows, therefore, that the judgment and order must be reversed and a new trial ordered, costs to abide, the event.
Jenks, P. J., Thomas and Carr, . JJ., concurred; Woodward, J., read for affirmance.
Dissenting Opinion
(dissenting):
The complaint alleges in addition to the jurisdictional matters that on or about the 24th day' of February, 1908, one Frank B. Sherwood made and delivered to the plaintiff for a
“ Mr. Samuel E. Snedeker, White Plains, 1ST. Y.:
“Dear Sir.— Please pay to B. Young and Bros. Co. the sum of thirteen hundred and seventy-six 26/100 dollars ($1,376.26), and charge same to my account on your Oakwood Avenue job, to be paid as follows: Six hundred ($600.'00) Dollars when plastering is completed. Seven hundred seventy-six 26/100 ($776.26) Dollars when the trim is on.
“ Yours very truly,
“F.E.SHEBWOOD.”
. The complaint further alleges that “thereafter, and on or about the 24th day of February, 1908, the defendant for a good and valuable consideration duly accepted said order and promised to pay said sum to plaintiff, as in and by said order provided, by writing at the foot of said order: c Accepted February 24th, 1908, at 10:37 A. M.’ and subscribing his name thereto. That thereafter and prior to the commencement of this action, the plastering was fully completed and. the trim all put on the budding, as referred to in said order,” etc. • The defendant denied the material allegations of the complaint and set up several defenses, upon the theory that the contractor, F. E. Sherwood, had abandoned his contract before completion, and that no moneys were due him out of which this order could be paid. Upon the trial • of the action there was some evidence that the defendant had consented to accept the order in question upon the plaintiff agreeing to forbear filing a hen under the Mechanics’ Lien Law, and 'this the defendant practically admits in his testimony, where he says: “At the time I had the conversation with Mr. Young I did not want a lien filed and said so to Mr. Young; I don’t remember that was after Mr. Young had stated to me that he must have some security ; I stated the conversation as I remember it. ” There was no specific denial of the testimony of the plaintiff that he had demanded security, under threat of filing a lien, and that the defendant had agreed to accept the order for the purpose of avoiding this action, ■ Both parties asked for the
The judgment and order appealed from should be affirmed, with costs.
Judgment and .order of the County Court of Westchester county reversed, and new trial ordered, costs to abide the event.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.