Williams Engineering & Contracting Co. v. City of New York
Opinion of the Court
In December, 1903, the Williams Engineering and Contracting Company, a partnership composed of three men, John Williams, James H. Holmes and James F. Kennedy, bid for and obtained a contract for certain work on the Blackwell’s.
In June, 1904, the firm formed itself into a corporation under the same name and, it is claimed, assigned the contract to the corporation. It is further claimed that said assignment was approved by the commissioner of bridges. It proceeded with the work, but thereafter the bridge commissioner determined to change the plans by eliminating a very considerable portion of the work contemplated by the original contract, mainly consisting of elevators and power stations on the Blackwell’s Island piers. A’ controversy arose as to the amount of damages for the taking away of this portion of the work, and also a claim for damages for delay caused by the city.
On August 6, 1909, a supplemental agreement was entered into which, after reciting the contract, contained the following: “Whereas, the party of the first part is desirous of withdrawing from the performance of the said contract a large portion of the work called for thereunder, to wit, the erection of four elevator towers, two power houses and certain other work •which need not be specifically mentioned, and the party of the second part is rmwilling to allow the said work to be. withdrawn, and has protested against the withdrawal of the same, and claims damages therefor as well as other damages in connection with the said contract; and whereas, there remains unpaid under the. estimates on this work, including retained. percentages, the sum of $21,909.25, and additionally unpaid the amount of $6,500, covered by Commissioner's order of January 8, 1907, making a total amount of $28,409.25; and whereas, the parties hereto are desirous of avoiding delay in the prosecution of the work or unnecessary expense, of litiga
A summons and ■ complaint, verified on the 13th of October, 1909, was served, the 1st paragraph of which set forth that the plaintiff is a domestic corporation, and the 3d that heretofore and on or about the 31st day of December, 1903, the plaintiff
The amended answer to the complaint, verified March 14, 1910; - denied any knowledge or information as to the allegations of the 1st and 3d paragraphs of his complaint, mentioned above, and for a fourth and separate defense set up the making of the contract by the commissioner of bridges with the Williams Engineering and Contracting Company; that said Williams Engineering and Contracting Company was an unincorporated association or partnership between John Williams, James H. Holmes and James E. Kennedy, doing business under an assumed name in accordance with the certificate filed in the office of the county clerk December 18, 1903. It set up clause UU of the contract, that the contractor would not assign, transfer, dispose of or otherwise convey said contract without the previous consent of the commissioner; that. the plaintiff was a corporation organized the 1st day of June, 1904; that there has never been any assignment of the contract to the corporation; that the plaintiff herein has no right, title or interest in and' to said contract and is not the proper' party in interest. It also set up- that the supplemental con- • tract of August 9, 1909, was absolutely null and void, and for a counterclaim that it had paid to the plaintiff $194,134.11, no part of which was due or owing, ahd asked for judgment for said sum.
The plaintiff served an amended complaint, verified April 1, 1910, in which it set up in the 3d paragraph the composition of the firm and that it made the contract 'with the city; that in June it organized and incorporated under the same name and that by and with the consent of the commissioner of bridges the firm assigned to the corporation; that said assignment from said firm to this plaintiff was lost or mislaid and that on the 30th of December, 1909, the loss of said assignment having béen discovered, a written confirmation of said
So that by April the mutual ■ pleadings presented the precise questions which are now made the basis of the motion at bar. Nevertheless the hearings before the referee began on the 1st day of June, 1910, and continued to the 17th of March, 1911. About 800 pages of testimony were taken and the case of the plaintiff practically completed.
An action was begun by Emma G-, Williams against the city of New York, the plaintiff corporation, the partners of the original firm, James J. Frawley, Mary E. Frawley, .Edward F. Sheehy, Robert J. Rooney, L. Laflin Kellogg, Abram J. Rose and John Williams, the summons being dated February 21, 1911, and the complaint verified on that day, in which Mrs. Williams claimed, upon information and belief, that, as a matter of fact, whilst the said Williams Engineering and Contracting Company bid upon said contract as a firm, said copartnership was substantially and wholly owned by John Williams, the two remaining parties having- joined said copartnership for the purpose of aiding and assisting said John Williams in securing said contract, and with the distinct understanding and agreement between them that some nominal interest would thereafter be segregated to the said parties, but the said contract should be held by said firm as a copartnership and prosecuted and conducted and carried out for the benefit and interest of said John Williams and the plaintiff pursuant to a certain agreement theretofore made between the said John Williams and the plaintiff, a copy of which was annexed; that said equitable assignment referred to was made, executed and delivered to the plaintiff after the aforesaid contract was awarded to said copartnership, in consideration of the plaintiff having advanced large sums of money to the said John Williams, in expectation of receiving said contract, and that said assignment contemplated, and as a matter of fact it was distinctly agreed that the plaintiff should have a three-fourths
Thereafter an order to show cause was granted on March 22, 1911, upon the motion of the corporation counsel, for an order. joining Emma G-. Williams as a party defendant in this action, relieving the city from its stipulation consenting to a reference and directing that the ease be tried before a jury or staying the hearings before the referee pending the trial of the issues in the case of Emma Gr. Williams against the city. Mrs. Williams and her counsel protested against being made a party defendant in this action and the court has denied that part of the motion, but it granted the motion to relieve the city from the stipulation and directed that the case be put upon the day calendar of the Trial Term for trial upon the payment of costs and disbursements by the city amounting to $1,788.75. From the latter portion of the order the plaintiff appeals..
This case is now on trial before an able and experienced referee. Every matter now presented as a ground for this motion is set up in the pleadings and was so set up and at issue two months prior to the ■ first hearing before the referee. It is too late, under such circumstances, to set aside the stipulation. No
The order appealed from, so far as it sets aside the stipulation and order of reference and directs the case to be tried before the court, should be reversed, with ten dollars costs and disbursements to appellant.
Ingraham, P. J., McLaughlin, Scott and Dowling, JJ., concurred.
Order reversed to the extent stated in opinion, with ten dollars costs and disbursements. Order to be settled on notice.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.