Millard Construction Co. v. Deiches
Opinion of the Court
Prior to the 24th of September, 1907, the plaintiff had a contract to complete certain railroad construction in the State of .New Jersey and on that day made a contract with the. Balanced Cable Crane Company by which the crane company agreed to sell, deliver and erect on certain foundations and tracks located at the site of the works of the plaintiff in and about the construction of the railroad in Jersey City, State of New Jersey, and the said purchaser agreed to buy the machinery, apparatus, equipment and supplies specified. The machinery to be purchased by the plaintiff was “ Six (6) patented Balanced Cable Cranes complete with carriages,” and the contract with great particularity specifies the capacity of and work that these cranes were to do. The crane company guaranteed that, the said machinery specified should be well made, of good workmanship and material and capable of doing the work specified, and further agreed to repair the machinery, to furnish a similar part to replace any of the material which within one year after date is proven to have been defective. It further provided that if after the installation of the said cable cranes or any of them the purchaser should require the crane company to operate all or any of them in actual work that the plaintiff would pay said company $20 per day per crane for each and every day said crane was so operated. It was further agreed that one of the said cranes complete should be in place in proper running order and condition on or before October 8, 1907that within one week after the said crane was accepted by the plaintiff and the installment due therefor paid the second of said cranes should be similarly erected and placed in proper running order and condition for operation,
In pursuance of this last clause of the contract the crane company furnished a bond by which it and the defendant acknowledged themselves indebted to the plaintiff in the sum of $20,000! The bond then recited that the principal, the crane company, had entered into a written contract with the plaintiff, being the contract before mentioned, for the delivery and erection of six balanced cable cranes complete according to the terms and conditions of the said contract, a copy of which contract was made a part of the bond. The condition of the obligation was that if the principal should faithfully perform said contract according to the terms, covenants and conditions thereof, except as thereinafter provided, then the obligation should be void, otherwise to remain in full force and effect. It is then provided that “ This bond is executed by the
The complaint alleges that the crane company did not perform the said contract, and failed, refused and neglected to perform the same in certain particulars specified in the complaint: First, that it erected only four of said cranes, and failed to sell, deliver and erect the other two; second, that the crane company did not cause the first of said machines to be erected on or before October 8, 1907, but that the first crane was not erected until October 24, 1907; the second until November 11, 1907; the third until December 3, 1907; the fourth until December 28, 1907, and the fifth and sixth machines were never delivered or erected; third, that the cranes have failed in all respects to meet the terms, covenants and guaranties of the said contract, and the said machines were not well made, of good workmanship and material, and were not capable of doing the work specified in the said contract; that the plaintiff has duly kept and performed all the obligations to be performed on its part by the terms of the bond, and ha,s duly notified the defendant of the default, and has
The answer, after admitting the making of the bond and of the contract between the crane company and the plaintiff and denying the other material allegations of the complaint, sets up four separate defenses. The first is that the plaintiff at divers times agreed with the crane company to modifications in the terms and conditions of the contract without notice to and without the knowledge and consent of the defendant; second, that the plaintiff extended the time within which the crane company should perform or partly perform the contract without notice to or without the knowledge and consent of the defendant; third, that the failure of the crane company to complete the contract was due wholly and entirely to the wrongful neglect of the plaintiff; and fourth, that the plaintiff waived performance on the part of the crane company to perform the terms of the contract by extending the time of the crane company to perform the terms of the contract, by accepting performance after alleged default and by permitting the crane company to continue in the performance of the contract without notice to and without the knowledge and consent of the defendant. There was no affirmative defense that the-plaintiff failed to notify the surety of any act on behalf of the crane company which might involve a loss for which the said. surety was responsible, although the allegations of the complaint that the plaintiff had duly notified the defendant of the default of the crane company is denied upon information and belief. Coupled with that denial, however, is the allegation that contrary to the terms and conditions of the contract the plaintiff prevented said crane company from continuing to perform the terms and conditions of the said contract by it to be performed.
Upon the trial at the end of the plaintiff’s testimony the defendant moved to dismiss the complaint. After that motion was made the defendant rested, and asked the court to direct a verdict in favor of the defendant upon the grounds stated upon the motion to dismiss. The court directed such a verdict for the defendant, and from the judgment entered thereon the plaintiff appeals.
Nor do I think it can be said that the fact that the plaintiff paid to the defendant’s principal the contract price for these cranes when they were finally adjusted was a violation of any obligation of the plaintiff which discharged the surety. The payments were evidently made in good faith on the assumption that the cranes were in proper condition and would comply with the contract. The deficiencies that appeared were developed in the working of the cranes themselves and if the plaintiff in good faith supposed that the cranes were sufficient to comply with the contract and paid for them based upon such assumption caused by the assurance of the defendant’s principal that certainly was not itself such a violation of the contract as discharged the surety. I think the evidence discloses that the plaintiff performed its contract and did everything that was required of it; that there was at least a question for the jury as to whether the plaintiff did not notify the defendant of all acts which came to its knowledge which might involve a loss for which the surety was responsible, and that the direction of a verdict for the defendant was error.
Laugi-ilin and Miller, JJ., concurred; McLaughlin and Dowling, JJ., dissented.
Dissenting Opinion
On September 24, 1907, the plaintiff entered into a contract with the Balanced Cable Crane Company, by which the latter agreed, for the consideration of $31,629.94, to sell, deliver and erect for it six excavating cranes. Twenty-two thousand seven hundred and sixty-five dollars and eighty-eight cents of the consideration was paid at or prior to the timé the contract was executed and the balance agreed to be paid in six equal installments, one when each crane was “erected in place and in proper running order and condition and ready for operation.” By the contract the first crane was to he ready for operation on or before the 8th of October, 1907, when it was to he accepted and paid for and the second one week later, and so on until the six had been delivered. Simultaneously with thé execution of the contract the Balanced Cable Crane Company, as principal, and the AEtna Indemnity Company (now in the hands of a receiver), as surety, gave to the plaintiff a bond conditioned for the payment of $20,000, but upon the condition that the same should be void if the Balanced Cable Crane Company faithfully performed its contract. The bond provided: “This bond is executed by the Surety upon the following express conditions, which shall he conditions precedent to the right of the Obligee to recover hereunder. The said Surety shall be notified in writing of any act on the part of said Principal or its agents or employees which may involve a loss for which the said Surety is responsible hereunder, immediately after the occurrence of such act shall have come to the knowledge of said Obligee or to any representative duly authorized by him to oversee the performance of said contract; and a registered letter mailed to the President of said Surety at its office in New York City, N. Y., shall he the notice required within the meaning of this bond.” It also provided that if the principal abandoned the contract or for ■ good reason was compelled by
This action is brought upon the bond, the plaintiff alleging it has sustained damage to the extent of $20,000 by reason of the failure of the Balanced Cable Crane Company to perform its contract, for which sum judgment is demanded. The answer .put in issue the material allegations upon which a recovery is predicated except the making of the contract and the issuance of the bond, and alleged affirmatively that the plaintiff consented to the modifications of the contract, without notice to the indemnity company, and without its knowledge or consent; that it waived performance of the contract by extending the time, and accepting performance after default had occurred, without notice, and by reason thereof the indemnity company was relieved from liability. At the trial, after both parties had rested, the court directed a verdict in favor of the defendant. Judgment was accordingly entered dismissing the complaint, from which and an order denying a motion for a new trial plaintiff appeals.
The cranes to be delivered under the contract were guar-' anteed to lift at least five tons at the rate of 60 feet per minute and then carry such weight along a cable to the place where the same was to be dumped at the rate af 600 feet per minute. The fact is not disputed that the Balanced Gable Crane Company broke its contract in several respects. It failed to furnish two of the cranes , and those which it did furnish-were not within the time specified, nor would they do the work stipulated to be done, and were so defective that they were finally discarded. Notwithstanding such failures, it is insisted the judgment is right, because (1) the plaintiff did not comply with the condition of the bond by giving immediate notice of the failure to furnish the cranes and of their defects at the time and in the manner called for by the contract; and (2) the plaintiff paid the full contract price for the four cranes which were delivered.
The first crane; as already seen, was to be erected and ready for operation on or before October 8, 1901, but in fact
Irrespective of the time of delivery of the four cranes, they did not comply With the contract in many respects. Not one of them had a lifting power of more than 2,500 pounds, . although the contract called for five tons. They were defective in many other respects and to such an extent they finally had to be discarded as useless. Damage is claimed upon this ground and yet no notice whatever was given of these defects until January seventh and the fact is undisputed that the plaintiff had knowledge' of them as soon as the machines were delivered. The failure to give notice of the defects until the seventh of January precludes the plaintiff from maintaining this action.
I am also of the opinion that full payment by the plaintiff of
The judgment and order appealed from, therefore, should be affirmed, with costs.
Dowling, J., concurred.
Judgment and order reversed, new trial ordered, costs to appellant to abide event.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.