Uvalde Asphalt Paving Co. v. City of New York
Opinion of the Court
The plaintiff sties for damages measured by the value of work which he was required to do as an incident of his contract for repaving Cypress avenue in the borough of Queens. The value of the work done is not in dispute, the only question being as to his right to recover at all. The street to be repaved was an ancient road which had been worked for many years at its natural level, and had been first a plank road and after-wards a macadamized road. ' The repavement was rendered necessary because the macadam had fallen into disrepair. In the course of the work the contractor was required to partially regrade the street, which called for an amount of earth excavation. It is for this excavation that plaintiff has recovered. We think that it is quite clear that the grade of the street had never been legally changed when the contract was executed, and that" regrading was not called for by the contract and not within the contemplation of the parties when the contract was executed.
The bid, contract and specifications were evidently made upon printed forms intended to apply to cases of either original paving or repaving. They are entitled “bid” or “contract” or “specifications,” as the case maybe, for “regulating, grading, curbing and repaving,” etc., and in each of them are a large number of items of various kinds of work such as might be encountered either in laying an original pavement or in repaving. The printed description of the work in the specifi
The only items .upon which bids were asked were (a) for completed asphalt pavement, (b) for concrete, and (c) for furnishing and setting new concrete curbstones. The items for “ earth excavation ” and “ earth filling, ” for which spaces were provided in the printed forms, were left blank, no bids, being either asked or given as to them. The contract, in its printed part, referred to “ the plan now on file in the Bureau of Highways.” There was no such plan on file in that bureau, but there was on file in the county clerk’s office a somewhat incomplete plan which had been made by the borough president in 1903 and approved by the board of estimate and apportionment. This plan purported to show the natural grade of the street, and also an altered grade, and the work for which plaintiff now seeks compensation consists in bringing the natural grade to the altered grade shown on this map.
From the circumstances above detailed we think that it clearly appears that it was not contemplated by either of the parties when the contract was made that the work would include a substantial amount of earth excavation of which no estimate was .made and for which no bid was asked, and the necessity for which excavation was not shown on any map or plan on file in the bureau of highways. ■ The defendant insists that it was the duty of the contractor to consult the map on' file in the county clerk’s office before making his bid. We do not so consider. In view of the facts that the street was already paved; that the contract was only for repaving; that no item was specified in the proposal or specification which would be appropriate to regrading, and that there was no plan on file in the borough president’s office, the contractor was quite justified in assuming that the street was to be repaved at its then existing grade and to make his bid accordingly. It is at least open to question whether the map' or plan, signed by the president of the borough in 1903 and approved by the board of estimate and apportionment was effectual to change the grade of Cypress' avenue, which was an ancient street or road laid out and worked at the natural grade. ''Section 441 of the charter
It was shown that the work of regrading was ordered by the engineer and executed under protest on behalf of the contractor that it was in excess of the requirements of the contract.
Upon these facts we are of opinion that the plaintiff is entitled to recover upon the rule laid down in Borough Const. Co. v. City of New York (200 N. Y. 149). In that case, as in this, the contractor claimed compensation, by way of damages, for a breach of his contract in that he was required to do work not covered by the contract. The Court of Appeals said: “ The learned counsel for the appellant with considerable insistence advances arguments applicable to an action brought to recover on contract for extra services and materials and leading to the conclusion that such recovery cannot be permitted because such materials and work were not called for or authorized in the manner prescribed by the contract. Of course on the premises formulated by counsel on this theory his conclusions are unimpeachable, but the answer to the entire argument is that this action does not rest on any claim for extra services or materials under the contract, but on an alleged breach of the contract by the city and its representatives whereby the respondent has suffered damages, and the question is whether the action can be maintained on that line.
“ I regard it as settled that it may; that within certain limits a contractor who is ordered by the proper representatives of the municipality to furnish materials or do work as covered by*116 his contract which the former thinks are not called for by such contract may under protest do as directed and subsequently recover damages because he has been so required, even though it should turn out that the contractor was right and that the official had no right to call on him to furnish such materials and do such labor. Decisions of this court have so conclusively established the principle that under such circumstances the contractor may treat the' conduct of the municipality acting through its representative as a breach of contract and recover damages, that it is only necessary to summarize these without argument.”
The court cited in support of its view Gearty v. Mayor, etc. (171 N. Y. 61); Lentilhon v. City of New York (102 App. Div. 548; affd., 185 N. Y. 549); People ex rel. Powers & Mansfield Co. v. Schneider (191 id. 523). The defendant places much reliance upon Dunn v. City of New York (205 N. Y. 342, adopting' the dissenting opinion of Ingraham, P. J., in 141 App. Div. 280). In that case a contractor for regulating and paving ¡Eleventh avenue in the city of New York had expressly contracted to remove, where necessary, the sub-grade rock, and was warned by the terms of the proposal that the engineer’s estimate of the amount of rock to be removed was only tentative, and that the bidder must satisfy himself upon that point. . It turned out that there was more rock to be removed than had been estimated either by the engineer or the contractor. The latter sought to recover the amount of the expense incurred in removing the unexpected rock. It was held that he could not recover. That case differed from the present in. two important respects. In the first place the contractor sued as for work done under the contract, and in the second place he had expressly contracted to remove whatever rock was necessary, and had been compelled to do more than he expected only because he had failed to take effective steps to inform himself before bidding as to how much rock he would be called upon to excavate.
The judgment and order appealed from must be affirmed, with costs.
Laughlin, Clarke and Miller, JJ., concurred; Ingraham, P. J., dissented. .
Dissenting Opinion
On the 23d of October, 1906, the plaintiff made a contract with the defendant whereby- it agreed to furnish all labor and materials at its own cost and expense necessary or proper for the purpose and in good, substantial workmanlike manner and in strict accordance with the specifications therein contained or attached, regulate, grade and pave or repave with asphalt pavement on the designated foundation and roadway of Cypress avenue from Grates avenue to borough line in the second ward in the borough of Queens and set and reset such ' curbstones, heading stones, etc., as may be necessary, and maintain said pavement for five years from the final completion and acceptance thereof. The contract also provided that to prevent all disputes and litigation the engineer shall in all cases determine the amount or the quality of the several kinds of work and material which are to be paid under this contract and shall determine all questions in relation to the work and materials and construction thereof, and he shall in all cases decide every question which may arise relative to the execution of this contract on the part of the contractor. His estimate and decision shall be final and conclusive and such estimate and decision, in case any question shall arise, shall be a condition precedent to the right of the contractor to receive any money under this contract. It was also provided that the contractor should receive certain specific prices as full compensation- for furnishing all the material and performing all the labor which may be required in the prosecution of the whole work, and in all respects performing and completing the same; that “incase the grade of the street shall be changed during the progress of the work the contractor will conform to the altered grade at the prices specified herein as far as they are applicable; and for any work the price of which is not specified in this contract the provisions heretofore contained in relation to the work not provided for in this contract shall apply ” By the specifications it was provided that the work should consist of regulating and grading the entire street, or if the street is already paved, removing or readjusting the old pavement, setting and resetting curbs and laying sidewalks whereever required and laying asphalt pavement; that all
It was admitted on the trial that the plaintiff performed the contract and completed the work, and the same was certified by defendant’s engineer by a final certificate; and that the plaintiff has received the full compensation provided for by the contract. At the completion of the contract the plaintiff duly presented to the defendant a claim for additional compensation for earth excavation, which claim was rejected by the engineer, the borough president and the corporation counsel. This contract was executed October 23, 1906.
The plaintiff called the engineer for the city, who produced a plan and profile of Cypress avenue dated May 13,1907, although the engineer did not assume charge of the work until September, 1907. That map showed what was claimed to be the official grade of Cypress avenue. It seems that there had been no profile of this street filed in the office of the borough president prior to the execution of the contract. There had been, how-, ever, a map of this avenue made by the president of the borough of Queens and filed in the office of the county clerk of Queens county in 1903, and this profile map made in 1907 appears to conform to that map which was the only map showing the profile of this Cypress avenue, and then to be paved, and the, profile on that map was formally adopted by the board of estimate and apportionment in 1903. The lines on the original profile map. adopted by the board of estimate and apportionment in 1903 and filed in the county clerk’s office were in some respects different from the actual, grade of the street as it had been in use before that time for many years. ' The engineer
There was here a map which had been approved by the board of estimate and apportionment establishing the grade of this avenue, and it was the only map in existence that had any connection with the grade. To properly bring this avenue to-the grade some excavation was necessary, and that the city engineer held was the grade at which the plaintiff was required under his contract to lay the pavement. The corporation counsel so directed and plaintiff obeyed such direction. As extra work it seems to be conceded that the plaintiff cannot recover. (Dunn v. City of New York, 141 App. Div. 280; 205 N. Y. 342.) The contract in that case was substantially similar, to that in this case, and I think in this contract as under the contract in the Dunn case plaintiff was required to remove any earth that was necessary to bring this avenue to the grade at which the pavement was to be'" laid. The prevailing opinion is based upon the case of Borough Const. Co. v. City of New York (200 N. Y. 149). That case involved the construction of a sewer, and the opinion in that case examined the previous-cases in the Court of Appeals and laid down the rule which was to apply in actions of this character. After discussing the question, the court said: “ The underlying justice of the principle is that where a municipal representative, having authority to speak for it and supposed to be familiar with such matters, in apparent good faith and with a show of reason requires a contractor to do certain things as covered by his contract, the contractor, although protesting against the requirement, ought not to be compelled to refuse obedience and incur -the hazard of becoming a defaulter on his contract even though it shall subsequently turn out that .he was right and the municipal representative wrong in the dispute. The theory involves the idea that the requirement of the municipal representative finds some reasonable basis in the contract and that the question whether his demand is proper or improper is one which may be the subject of some doubt and debate and in respect of which "the contractor might prove to be mistaken if he should refuse to do what was required of him, and there is no justification for
It seems to me, therefore, that the case as presented was not one which justified the contractor in going and doing the work and thereafter recovering as for extra work under the guise of a breach of the contract, and I do not think, therefore, the judgment should be sustained.
Judgment and order affirmed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.