Schloss v. Troman
Opinion of the Court
On the 11th day of August, 1910, the plaintiffs, who' owned the premises situate at the southeasterly corner of Two Hundred and Twenty-ninth street and Bronxwood avenue, borough of the Bronx, New York, contracted in writing with the defendant Joseph Treman for the erection of a two-story factory building thereon, for which they agreed to pay $17,775, and on the twenty-third day of the same month they ordered extra work in connection therewith, for which they agreed to pay $350, making the total contract price of the work $18,125. The lien filed by the Mount Vernon Company was for material furnished to Troman and used in the building. Traman sublet
The lienors having failed to commence an action to foreclose their liens, the plaintiff s, instead of calling upon them to do so, brought this action on February 1,1911, for a judicial determination with respect to the amount due from them to Troman, and for the distribution of the fund and cancellation of the liens. The action was tried as if it were one brought by a lienor for the foreclosure of his lien, and no question with respect to the form of the action is presented.
Before the liens were filed, plaintiffs paid to Troman on account of the contract price of the work the sum of $12,000, leaving a balance of $6,125 unpaid at that time and when the action was commenced. The contract required Troman to complete the building on or, before September 29, 1910, or within seven weeks, and it was therein provided that time was to be of the essence of the contract and that the contractor was to receive $50 for each day of completion prior to September 29, 1910, and to pay as liquidated damages $50 for each day required to complete the contract after September 29, 1910. On the day Troman was required by the contract to have the factory building completed he had not substantially performed; but the plaintiffs took possession to such extent as they could and installed and operated certain machines for the manufacture of lace. Troman continued the work under the contract, at least, until after the middle of December, 1910, and on January 11,1911, the architect for plaintiffs employed Staker, the sub-contractor for the carpenter work, to complete certain remaining items of work required by the contract. There is a conflict in the evidence both with respect to the work left uncompleted by' Troman, and the reasonable cost thereof. The trial court determined that the reasonable cost of com
No extended argument is required to sustain the trial court with respect to two of the liens. The evidence warranted a finding that the Marcus Company was induced to furnish materials on the agreement of plaintiffs that they would not claim liquidated damages. The argument that the agreement, at most, only precludes plaintiffs from enforcing the liquidated damages with respect to the materials subsequently furnished is untenable. Furnishing any materials constituted a sufficient consideration for the agreement to waive the right to assert damages, not only as against the claim for materials to be furnished, but also for those theretofore furnished. The Willson & Adams Company does not base its claim upon estoppel or contract made between it and the plaintiffs. It relies upon evidence showing that before it furnished all of the materials to Staker, the plaintiffs had agreed with him that if he would fully perform his contract with Troman, the liqui
The Mount Vernon Company delivered all of the materials, on account of which it asserts a lien, before the occurrences upon which it bases its right to recover. This lienor claims that after furnishing and delivering the materials it was induced by plaintiffs to refrain from filing a lien therefor, and thereby it lost the priority it would have had over the other lienors, whose liens had not then been filed. The evidence sustains that contention. On the theory of estoppel, however, the lienor would only be entitled to such benefits as would have followed the filing of its lien at the time it was induced to refrain from so doing. That would necessarily involve a ■ determination with respect to the amount of the liquidated damages, provided the plaintiffs would be entitled to deduct liquidated damages from the amount unpaid on the contract price, for in no other manner could it be ascertained what amount, if any, remained due and owing from the plaintiffs to Troman and applicable to the payment of mechanics’ hens. If the evidence showed an agreement on the part of the plaintiffs with this lienor that they would waive, or would not claim, liquidated damages if it refrained for the time being from filing a lien, and it, relying thereon, refrained from filing a lien, which would have preserved its rights as they then existed, that would constitute a sufficient consideration, and it
It follows, therefore, that the judgment should be affirmed, with costs.
Ingraham, P. J., McLaughlin, Miller and Dowling, JJ., concurred:
Judgment affirmed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.