Borough Development Co. v. Harmon
Opinion of the Court
The defendants, composing a firm engaged in the business of improving and selling suburban property, owned certain farm land in the borough of Brooklyn, designated by them as “Flat-bush Hardens,” which they desired to sell in building lots, after opening certain streets through the property.
The plaintiff, a domestic corporation, had a contract with the city of New York to remove and dispose of the street sweepings from the borough of Brooklyn. The plaintiff and defendants entered into a contract in the latter part of the year 1908, evidenced by certain letters interchanged and not by formal contract, whereby the plaintiff agreed to fill in such streets on the defendants’ property as they should designate, with ashes, earth and street sweepings, as delivered to it by the street cleaning department of the city of New York, and to deliver an approximate minimum average of three hundred cubic working yards of material per day; and whereby the defendants agreed to pay the plaintiff fifteen cents per cubic yard for the material so delivered. Deliveries were to commence December 9, 1908, but they did not commence until March of the following year, and they then were made in a less amount than specified in the correspondence. These deviations from the contract, however, were ■ waived by the defendants, who accepted the deliveries as made..
About the 12th day of July, 1909, the defendants refused to receive any further material, whereupon this action was instituted by the plaintiff. The complaint contains two causes of action; the first a cause of action to recover the contract price for the material already delivered and unpaid for, and the
The issues were submitted to the jury after a trial lasting several days, during which considerable conflicting evidence was adduced on either side, and the submission resulted in a verdict dismissing the counterclaim and awarding the plaintiff the contract price of the material furnished by it up to the time of the breach of the contract, together with damages for such breach. The defendants have appealed from the judgment entered thereon and from the order denying their motion for a new trial made upon the minutes. The judgment is not against the weight of evidence, and it must be affirmed unless some error of law necessitates a new trial.
The appellants urge the improper admission of evidence and the adoption of an erroneous measure of damages as grounds for a reversal.
During the trial the appellants’ counsel offered testimony that oral representations were made to the appellants on behalf of the respondent prior to and at the time the contract was executed, to the effect that the street sweepings would come from a particular part of Brooklyn, where such sweepings were unusually clean. This testimony was excluded as tending to vary or contradict a written contract. I am inclined to think that the ruling was correct. The written offer signed by the respondent, and which was accepted by the appellants, used this language: “The material to be used is ashes, earth and street sweepings, as delivered to us by the Street Cleaning Department.” That clause related exclusively to the quality of the material, and specifically provided that such quality need only be of the grade furnished by the street cleaning depart
The appellants further claim that the learned trial court erred in- excluding a lengthy letter written by the general manager of the respondent to the appellants after the breach of the contract. This letter, among other things, contained statements tó the effect that the respondent never stated that the material would be free from rubbish; that the contract had been carefully analyzed in detail prior to its execution; that appellants had intended to cover the material with earth; that any delay in deliveries had been acquiesced in; that respondent had disposed of the rejected material elsewhere at an increased price, and concluded with a plea for payment based on the ground that the entire transaction had been unprofitable to the respondent and the material supplied at a loss. Manifestly, most of
The appellants contend that an improper measure of damages was adopted by the learned trial court. The respondent did not attempt to prove any loss of profits. It did prove that in order to perform the contract a corduroy road was necessarily constructed, and it recovered the reasonable' expense thereof. Upon the facts in this case I do not think that such recovery was error. Expenditures necessarily made in anticipation of performing a contract may in many instances be recovered as an element of damage sustained after performance has been wrongfully prevented. (Long Island C. & S. Co. v. City of New York, 204 N. Y. 73; United States v. Behan, 110 U. S. 338; Phillips, etc., Const. Co. v. Seymour, 91 id. 646.)
It may be that a recovery for both the prospective profits and the preliminary expenditures could not be, sustained. (See Mackey v. Olssen, 12 Oreg. 429.) Assuming, however, that the contract was being- conducted by the respondent at a loss, it would have been entitled to recover nominal damages at least for the breach; and I see no reason why in such instance it cannot also recover incidental expenditures necessarily made in anticipation of performance. It maybe that-the respondent could have been required to deduct from the cost of the road the value of its use in the performance of so much of the contract as had been completed at "the time of the breach, but no such question was raised at the trial and such an apportionment cannot be made upon appeal.
The judgment and order should be affirmed, with costs.
Jenks, P. J., Woodward and Rioh, JJ., concurred; Burr, J., dissented upon the ground that plaintiff was not entitled to recover the costs or any portion of the costs of constructing the corduroy road.
Judgment and order affirmed, with costs.