Tisdale v. Geo. W. Jackson, Inc.
Opinion of the Court
This is a common-law action by servant against master for failure to adopt and to enforce a proper method of doing work. The defendant, a contractor for aqueduct work, was blasting a tunnel from the base of a shaft. First an upper section of the tunnel was removed for some distance, and then the corresponding lower section. After a blast, the debris was taken away (called “ mucking ”), and then the usual method of doing this kind of work was to sound and to test the walls and roof to discover any “loose stone” partly dislodged by the blast. This is called “scaling.” The work was constant and was doing by three shifts of men laboring for 8 hours respectively. The plaintiff went to work for the first time in a shift at 4 p. M. of October 20, 1910. The shift was made up of Foreman Gordon, 4 drillers and 4 helpers. The plaintiff testifies that a blast had been fired before his shift went down the shaft, that after it went down, “mucking” was done 'by the shift for some hours, and thereafter drilling was begun between 8 and 9 P. M. He testifies that he was directed by Gordon to work at drilling in a certain place, and just after he had begun his task a stone that had been loosened by the blast fell from the roof of the tunnel and injured him. The plaintiff contends that there had been no “ scaling ” done. There was absolutely contradictory testimony upon this issue. The learned court in its instructions to the jury limited the defendant’s negligence to its duty of establishing a reasonably safe method of work and a reasonably vigilant oversight in maintenance thereof, and submitted the specific question — what degree of “scaling,” if any, was required, and if not exercised, was such failure the proximate cause of the accident ? I shall not discuss the question whether the proof was sufficient to justify a finding upon the issue of “scaling” in favor of the plaintiff.
The plaintiff, 30 years old, had labored at tunnel work for 15
Labatt on Master and Servant says (2d ed. § 1375): “ The effect of the servant’s knowledge where his assumption of the risk is relied upon is open to no doubt. If that knowledge is imperfect, and excusably so, the action is, upon general principles, not barred. But an assurance that appliances are in good condition manifestly cannot prevent the operation of a defense which is regarded as completely made out, when it has been proved that the risk was known to and comprehended by the servant.” (See Crown v. Orr, 140 N. Y. 450; Graves v. Brewer, 4 App. Div. 327; McCarthy v. Washburn, 42 id. 252.)
The judgment and order must be reversed and a new trial must be granted, costs to abide the event.
Putnam, J., concurred; Thomas, J., concurred upon the grounds stated in the opinion, and also upon the further ground that no negligence on the part of defendant on the occasion in question is shown, and that plaintiff assumed the risk of any danger that arose from the method of carrying on the work; Burr and Carr, JJ., dissented.
Judgment and order reversed and new trial granted, costs to abide the event.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.