Smith v. Cary
Opinion of the Court
This action was brought for the foreclosure of a mecnamc’s lien. The amended complaint sets out a builder’s contract in which the defendant Thomas H. Gary agreed to pay a certain sum as follows: “One-third when the roofing is completed; one-third when all the materials are on the premises; one-third when the job is completed and accepted by the architect.” The complaint further alleges that the plaintiff did the work and furnished the materials and “has duly performed all the conditions of the said contract on his part.” Section 533 of the Code provides: “In pleading the performance of a condition precedent in a contract, it is not necessary
The appellant relies on the Fox case, already mentioned, and Vandegrift v. Bertron (83 App. Div. 548). In the Fox case which was in the Second Department, the supervision and assent of certain parties were necessary and there was an allegation that the plaintiff and the contractor had duly performed all the conditions of the contract. It was held, upon the authority of the Weeks case that this was a sufficient averment of the performance of the conditions precedent, and the judgment of the Special Term overruling a demurrer to the complaint was affirmed. The opinion refers with approval to the pleading given in 1 Abbott’s Forms of Pleading (p. 196), where the note reads: “If the contract provides that plaintiff shall procure an architect’s certificate before defendant shall make payment, this general allegation of performance [i. e., in the wording of the Code] is held sufficient and no special allegation that such certificate was obtained is necessary.” The author cites several cases from other States on this proposition and also the Weeks case. The Vandegrift case was in the Fourth Department, and also holds upon demurrer as regards the condition of an engineer’s acceptance that the plaintiff may allege generally that he has performed all conditions of the contract in the wording of section 533. Neither
The respondents argue that section 533 of the Code refers only to conditions which the appellant may duly perform, and. that acceptance by the architect is a condition precedent to be performed by some one else. This seems a most technical distinction. Generally speaking all the conditions of a contract, precedent or otherwise, are to he performed by, or their performance is to he secured by, one party or the other to the contract. One of the two parties to the contract in every case must be specially interested in obtaining the performance of any condition that may in any way be within the power of an outside party to perform. I do not think that the Code provision mentioned intends to allow a party to a contract to allege generally performance when he is the one who actually performs the condition, and not to allow him to plead performance in the same manner when he is vitally interested in obtaining the performance by another, even though the outside party may perform the act. It is commonly said that in builders’ contracts the obtaining or securing of an architect’s acceptance is a condition precedent to payment. At all events it is the builder who is interested in obtaining, and who does obtain when he can, such an acceptance, and consequently it seems to me that the securing of such an acceptance is really a condition precedent to be performed by the builder “on his part,” and so within the fair meaning of section 533 of the Code. I accordingly am of the opinion that paragraph 3 of. the complaint in this action was broad enough to cover, and would fairly be understood as covering, the requirement of the contract as to the architect’s acceptance.
The judgment sustaining the demurrer should be reversed, with costs.
All concurred.
Interlocutory judgment reversed, with costs, and demurrer overruled, with costs, with leave to defendants to withdraw demurrer and answer upon payment of costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.