Moran v. Mayor
Opinion of the Court
On the 15th of June, 1894, the city of New York entered into a contract with Collins & G-illis, by which the latter agreed to curb, grade and flag a portion of One Hundred and Sixty-eighth street. Some time thereafter Collins & Gillis sublet a portion of the work to the plaintiff who, having fully performed his contract and not having been paid therefor, on the 17th of
The city appeals from the judgment and but two questions are presented: (a) Whether plaintiff was entitled to any interest whatever; and (b) whether he was entitled to costs.
I am of the opinion that the plaintiff, by reason of express provisions of the statute in force at the time the notice of lien was filed and the action commenced, was not entitled to interest either upon the amount found due by the referee from the time the same became due, or from the date of the referee’s report to the entry of the judgment, or to costs. The statute then in force was the New York City Consolidation Act (Laws of 1882, chap. 410). Section 1824 of this act is to the effect that a sub-contractor can have a lien for the value of labor performed or materials furnished by him upon moneys in the control of the city “to the extent of the amount due or to grow
A quite similar question was passed upon in Rockland Lake Co. v. Port Chester (102 App. Div. 360; affd., 185 N. Y. 590). It was there held that a judgment could not be rendered against a municipal corporation for a sum including principal, interest and costs in excess of the amount due from it to the contractor. The court said: “We think that the referee was bound by the provisions of section 3418 of the Code of Civil Procedure, which provides that in an action to foreclose a lien on account of a public improvement, if the court finds that the lien is established
It is true that section 1235 of the Code of Civil Procedure provides that where final judgment is rendered for a sum of money awarded by a report, interest upon the sum awarded from the date of the report to the time of entering judgment must be computed by the clerk, added to the sum awarded and included in the amount of the judgment; and section 53 of the Lien Law leaves the granting of costs in an action to foreclose a lien to the discretion of the court. But these provisions must be considered subject to the express limitations contained in the Consolidation Act and subsequent enactments relating to liens against municipal corporations to the effect that in no case shall judgment be entered against them for more than the amount due to the contractor. The right to file a lien at all comes from the statute and only such rights as are there given can be obtained. The plaintiff has only himself to blame for the loss of interest on the amount found due by the referee from the date of his report to the entry of judgment because he could have entered judgment upon the report had he seen fit to do so, in which case the judgment would have drawn interest.
The city’s liability was practically conceded at the close of plaintiff’s case, when a motion was made that judgment be allowed against the city for the amount that it had on hand belonging to the contractor, viz., $1,861.05.
The judgment is, therefore, modified by reducing it to $1,861.05, and as thus modified affirmed, without costs to either party.
Ingraham, P. J., Laughlin, Clarke and Scott, JJ., concurred.
Judgment modified as stated in opinion, and as modified affirmed, without costs. Order to be settled on notice.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.