dissents, as to the claim for extra work, on the ground that there was no order in writing given by the general contractor to the plaintiff for such extra work as required by the second article of the contract between the plaintiff and the general contractor. See, also, 151 N. Y. Supp. 1150.
Opinion of the Court
Judgment affirmed, with costs. Order filed.