Federal Terra Cotta Co. v. Potterton Bros.
Opinion of the Court
Action to recover under a written contract $1,875 damages alleged to have been sustained by defendant’s failure to accept terra cotta manufactured for it by plaintiff. At the close of plaintiff’s case defendant moved for the dismissal of the complaint. The motion was denied. At the close of the whole case the plaintiff moved for the direction of a verdict, which was denied, and defendant then renewed its motion to dismiss the complaint, which was granted. Plaintiff duly excepted to these rulings and the exceptions were ordered to be heard in the first instance at the Appellate Division.
There is substantially no dispute as to the material facts involved. On April 15,1913, the parties entered into a written contract, dated April 11, 1913, by which the plaintiff agreed to manufacture certain terra, cotta according to plans and
The plaintiff urges that inasmuch as defendant did not approve and return the shop drawings until April eighteenth,
I am unable to appreciate the force of this contention. The fallacy of it, as it seems to me, lies in the assumption that plaintiff’s obligation to make the first delivery within fifty-six days was contingent upon defendant’s furnishing all information called for prior to April sixteenth. The contract contains no such provision. Under its terms the only significance of this date is that prior thereto defendant was to furnish such information as would enable plaintiff to prepare its shop drawings. The defendant did not agree to approve and return these drawings at any particular time. It merely agreed to supply the original drawings before April sixteenth, and there is no evidence that it did not do so. As to the selection of the surface, it is perfectly obvious that this was not a part of the information necessary for the preparation of the shop drawings, for they were made by plaintiff and returned, approved by defendant, at least a week before the surface was chosen.
But even if it be assumed that defendant was bound to furnish all information called for prior to April sixteenth, its failure to do so until April twenty-fifth did not excuse plaintiff’s delay or default in thereafter completing the contract within the specified time. Under the contract the plaintiff agreed to make delivery of the first installment of terra cotta, not within fifty-six days from April sixteenth, but within fifty-six days from the receipt of its approved shop drawings and other necessary information. It was not relieved from this obligation by the fact that it saw fit, before the drawings and necessary information were received, to take other work which prevented its performing its contract with the defendant. If it had desired to be relieved upon that ground, then such a pro
As already indicated, a fair construction of the contract required the plaintiff to deliver the first installment on'June twentieth. On June fourteenth plaintiff advised defendant, by letter, that it expected “ to start shipments ” about June twenty-eighth. On receipt of this letter, the defendant wrote the plaintiff, insisting that it make the shipments as required by the contract, and at the same time informed it that “We are under penalty for completion of this work and shall hold you responsible for any damage caused by your delay.” Plaintiff answered on June nineteenth, reiterating that the earliest delivery of the first shipment it could make would be on June twenty-eighth. On June twenty-third a partial strike occurred at plaintiff’s factory, which became general on the following day, and defendant was so advised by letter dated June twenty-fifth, in which notice was given that plaintiff would claim an extension of the time of shipments under the strike provision in the' contract. This letter was not received by defendant until June twenty-eighth, on which day it answered, calling attention to the fact that plaintiff had been in default for several days before the strike occurred. This letter, as well as the defendant’s letter of June sixteenth, clearly indicates that defendant intended to stand upon the strict terms of the contract, and there is nothing in either of them which supports the contention of the plaintiff that defendant waived performance on the part of the plaintiff. There is no evidence of a waiver by defendant of the time within which the terra cotta had to be delivered, unless it be found in the testimony of George A. Potterton, defendant’s treasurer, in which he stated that if the terra cotta had been received at any time prior to July first, it could have been used; or in the two letters written by defendant to plaintiff on July first and third respectively. In the first letter defendant offered to accept the terra cotta if shipped before “ Wednesday of this week ” and expressed the hope that plaintiff might “ find a way to ship at once terra cotta on hand.” To this letter plaintiff replied on July second, stating that it was not in default and relied upon the strike clause in
I do not think this evidence would have justified a finding that there was a rescission of the contract or a waiver of the time within which the terra cotta had to be delivered. The most that can be said is that there was an offer to waive the time on condition that delivery be made on July fifth. The plaintiff did not accept the condition imposed; on the contrary, insisted it was not in default, and that it had a reasonable time after the termination of the strike in which to make a delivery. It would be a forced, and I think unreasonable, construction under such circumstances to hold that defendant’s offer amounted to a rescission of the contract. (Wittwer v. Hurwitz, 216 N. Y. 259.) If the plaintiff had changed its position, or been prejudiced in any way by the offers thus made, a different question would be presented, but it affirmatively appears this was not the case, for by reason of the strike no work at all was done at all by plaintiff on defendant’s order from June twenty-fourth until July seventeenth — several days after the defendant notified the plaintiff it would not accept the terra cotta.
It is perfectly obvious that the time of delivery was the essence of the contract. The defendant, as plaintiff knew, was engaged in the construction of a building and had to have the terra cotta — otherwise the work could not proceed — and if not completed within a certain time, penalties would be imposed. The defendant neither prevented performance nor waived the time within which the contract had to be performed
My conclusion is that the exceptions should be overruled, with costs, and judgment ordered for defendant dismissing the complaint, with costs.
Clarke, P. J., Laughlesi, Scott and Page, JJ., concurred.
Exceptions overruled, with costs, and judgment ordered for defendant dismissing the complaint, with costs. Order to be settled on notice.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.