George Colon & Co. v. Smith
Dissenting Opinion
(dissenting):
The plaintiff is a subcontractor who performed work in excavating for a building to be erected upon the defendant’s premises in the city of New York.
It was shown that there was a balance due to the plaintiff’s contractor at the time of the filing of the lien of $3,536.30 and the amount of work done by the plaintiff was $3,939.80, for which payment has not been made. The learned justice at the trial, however, dismissed the complaint, upon the ground that
In the case at bar the removal of the stones from the cellar and the fixing of the sidewalk are shown to have been done in answer to the defendant’s demands, and in my opinion the notice of lien was sufficient if filed within ninety days of January 7,1914. A sidewalk has been held to be an appurtenance of the premises within the meaning of the Lien Law, and work done upon it is, in contemplation of law, work done upon the premises. (Kenney v. Apgar, 93 N. Y. 539.)
The judgment should be reversed and judgment granted for the plaintiff, with costs.
Smith, J., concurred.
Judgment affirmed, with costs.
Since amd. by Laws of 1916, chap. 507. —[Rep.
Opinion of the Court
I am of opinion that the judgment in favor of the respondent is right and should be affirmed. The respondent Smith was the owner of premises on the southeast corner of Merriam avenue and University avenue (formerly Aqueduct avenue), borough of The Bronx, New York city. In the month of March, 1913, she entered into a verbal contract with the defendant Fitzgerald for the excavation of the lot with a view
He entered upon and continued in the performance of the. work until the 22d of April, 1913, at which time,- by a contract resting in parol, he sublet the remaining work to the plaintiff at the same rate, but for an additional consideration.
The owner paid Fitzgerald $1,900 on account of the work which he claims covered the work performed prior to the subletting. The president of the plaintiff testified that his company “ continued excavating the premises until the work was complete. ” On completion the further sum of $3,536.30 became due and owing from the owner to Fitzgerald, and from him to the plaintiff for this work, no part of which has been paid. The plaintiff, however, claims that the work performed by Fitzgerald before subletting the unfinished work to it would not amount to $1,900, and on that theory the plaintiff’s claim was for more than the balance owing from the owner. Plaintiff’s Hen was filed on the 4th of April, 1914.
The complaint was dismissed on the ground that the lien was not filed “within ninety days after the completion of the contract, or the final performance of the work, or the final furnishing of the materials, dating from the last item of work performed or materials furnished,” as required by.section 10 of the Lien Law. (Consol. Laws, chap. 33; Laws of 1909, chap. 38).
One Hess, who was employed and caUed by the plaintiff, testified in answer to a question asked by the court, that the plaintiff considered that it had finished this excavation work in the spring of 1913.
It appears that on the 23d of May, 1913, the owner entered
The work claimed to have been done within ninety days ®f the filing of the hen relates to certain work done on the 'Tth of January, 1914, consisting of the removal of rock which when excavated was placed on adjoining premises, and to the restoration of the sidewalks, and to the removal of some loose stones from the cellar. The president of the plaintiff testified that when his company entered upon the performance of the work of excavating the earth and rock it continued in the performance of that work until it was completed; and thereupon the court asked when the excavation was completed, and he answered that it was completed in January; whereupon the court, evidently in view of the fact that all of the
As already observed, the only evidence with respect to what was embraced within the excavation contract is the testimony of Fitzgerald, who expressly states that there was no agreement between him and the owner with respect to the sidewalk. Aside from claims made by the owner, by letters and verbally, that it was the duty of both Fitzgerald and the plaintiff, under the respective contracts, the one for the excavation and the other for the construction of the foundation, to restore the sidewalk, there is no other evidence on the subject; but it appears by a letter written by the owner to Hess, intended for the plaintiff, on the 5th of June, 1913, that she claimed to have deposited $250 with the city authorities as security for the restoration of the sidewalk by Fitzgerald; and she testified that she did this to enable Fitzgerald to obtain a permit to haul the excavated material over the sidewalk, and that he, as a condition of obtaining the license, promised and agreed to restore the sidewalk to the condition it then was in; and that in the month of September she considered the sidewalk properly restored and was satisfied with it; but that the city inspector was not, and that, therefore, the city authorities did not return the money so deposited and which she testified was deposited by Fitzgerald, but thereafter admitted that it was probably deposited by her as stated in said letter. There is no direct evidence with respect to any injury or damage to or interfer
The evidence concerning what was done with respect to the sidewalk on the 7th of January, 1914, is altogether too indefinite to require a finding that it was any part of the work which Fitzgerald was obligated to do, either under his contract for excavating the lot or pursuant to the arrangement by which he obtained a permit to use the sidewalk and the owner deposited the money required by the city therefor; but in any event, at most, it relates to some work which it was the duty of Fitzgerald, under the conditions of the permit and under his agreement with the owner with respect to furnishing the security for the permit, to perform, and constituted no part of the- excavation work.
Although there was an obligation flowing from Fitzgerald to the owner to restore the' sidewalk, which obligation arose either oht of his interference with the sidewalk or by virtue of his agreement at the time the owner furnished the security for the permit, there is upon no theory any evidence of an agreement on the part of the plaintiff to perform such obligation on the part of Fitzgerald to the owner. It is
As I view the case, therefore, whatever work was done with respect to the sidewalk on the seventh day of January was exacted by the owner as a performance of Fitzgerald’s obligation to her, arising on an implied duty or out of the agreement made at the time she deposited the money for the permit, and it constituted no part of the work of excavation for which a valid mechanic’s lien could be filed, either by the contractor or by a subcontractor. The work for which a lien may be filed is the work the contractor is engaged to perform in improving the premises. The authorities upon which the learned counsel for the appellant relies holding that a mechanic’s lien may be filed for constructing a sidewalk in connection with the improvement of real estate (Mosher v. Lewis, 14 App. Div. 565; Kenney v. Apgar, 93 N. Y. 539, 549; Moran v. Chase, 52 id. 346) have no application here where the contract was merely to excavate and the interference with the walk was for the convenience of the contractor and, therefore, the duty to restore the walk, whether implied or expressed, constituted no part of the improvement made upon the land for the benefit of the owner for which a hen could be filed either by the contractor or by a subcontractor. (See Lien Law, § 3.)
The judgment should be affirmed, with costs.
Scott and Shearn, JJ., concurred; Smith and Page, JJ., dissented.
Since amd. by Laws of 1916, chap. 507.— [Rep.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.