Bailey v. Casualty Co. of America
Opinion of the Court
The contractor for excavating, Corcoran, having entered on a portion of the premises and begun the work of excavation, under a contract with plaintiff, before the work of demolition had proceeded for seventeen days, the defendant claims that the obligation for the penalty was annulled. Upon this point the learned court charged the jury that the occupation by the contractor for excavation of a part of the premises did not defeat plaintiff’s .claim unless “ such entry was at the solicitation, invitation, request or direction of the plaintiff, and you find the evidence establishes that this sub-contractor was responsible for the delays for which the plaintiff is now seeking compensation.” This charge was an application of the doctrine of Mosler Safe Co. v. Maiden Lane S. D. Co. (199 N. Y. 479), which holds that where the owner is responsible for delays because of which the date fixed for the completion of the contract is passed, the obligation for liquidated damages for delay is annulled and the owner remitted to a cause of action for damages actually sustained. The law of the charge was correct, but does not meet the claim of appellant’s
But we think it was error for the court to decide as matter of law that plaintiff was entitled to recover for fourteen days’ penalty or nothing; and that this point was properly covered by exception. The learned court was led into this error by sustaining the claim of plaintiff that the work was to be completed within.seventeen days from the time it was begun. This was not the contract. The contract provided that the seventeen days were to begin from “ the date that the owner gives the building to the contractor.” This means the whole and every part of the building, and this was not given to the Wrecking Company until midnight, June 30, 1915, for one Healy had a lease of a small part of the building to be demolished, and retained possession under his lease until that time. The defendant, a surety, guaranteed only the
The building was given to the contractor on the midnight of June thirtieth, and the computation for the penalty should have been made from that time. As, against the objection and exception of defendant, it was computed from June twenty-first, the day when work began, the judgment cannot stand. We think, however, that plaintiff should be given the privilege of holding the judgment for the amount for which he was entitled on the record to recover; and, therefore, reverse the judgment and order and grant a new trial, costs to abide the event, unless the plaintiff shall, within twenty days, stipulate to reduce the verdict to $1,350, with interest from August 2, 1915, and modify the judgment accordingly; in which case the judgment, as so modified and the order are affirmed, without costs.
Jenks, P. J., Thomas, Mills and Putnam, JJ., concurred.
Judgment and order reversed and new trial granted, costs to abide the event, unless within twenty days plaintiff stipulate to reduce the verdict to $1,350, with interest from August 2, 1915, and modify the judgment accordingly; in which event the judgment, as so modified, and the order are unanimously affirmed, without costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.