Massachusetts Bonding & Insurance v. Thomson
Opinion of the Court
This is an action to recover premiums on three policies issued by the plaintiff to the decedent Thomson who died after the trial and pending the appeal.
On the 27th day of May, 1912, the Hicks-Johnson Con- • struction Company entered into a contract with the city of New York for the construction of a sewer in Central avenue in the borough of Queens. The contract contained no provision requiring the contractor to carry liability insurance. The contractor gave a bond to the city in the penalty of $50,000 for the faithful performance of the contract, and the plaintiff and the United States Fidelity and Guaranty Company were sureties on the bond. The contract was assigned to the Arch Engineering Company, Inc., on the 19th day of September, 1912, and plaintiff and the city consented thereto. On the 12th day of November, 1913, the contract was assigned to Thomson with the consent of the plaintiff and with the approval of the city. On the same day a contract in writing was made between Thomson and the two surety companies reciting the making of the original contract for the construction of the sewer, that the surety companies became sureties on the bond of the contractor, the first assignment of the contract, and that Thomson was about to take an assignment thereof and desired the consent of the sureties; and Thomson agreed to complete the contract work to the satisfaction of the city for the money remaining unpaid on the contract and to satisfy all hens and assignments against the contract, and that he would indemnify and save the surety companies harmless from liability as sureties on the original contract; and the surety companies agreed that in the event that the cost of completion should exceed the amount unpaid by the city on the contract they would pay to him the excess not exceeding $5,000, but it was expressly provided that they should in no event be obligated to Thomson for more than $5,000. Two of the policies on which the action is brought were transmitted to Thomson by an insurance broker on the 9th day of December, 1913, with a letter stating that they were dated on the thirtieth of September that year in order to avoid taking an assignment of existing policies issued by plaintiff to the first assignee running until December thirty-
Over the objections and exceptions duly taken by the plaintiff the court received parol evidence offered by the defendant, in support of a defense pleaded, with respect to a parol agreement claimed to have been made between Thomson and the plaintiff long prior to the said agreement of November 12, 1913, between him and the plaintiff and the other surety company. The objections to this evidence were that it was immaterial and incompetent and constituted an attempt to vary the terms of said agreement of November twelfth. Objection was not specifically taken that it was an attempt to vary the terms of the policies. The court, however, received the evidence subject to a motion to strike it out. A motion was subsequently made to strike out the evidence thus received on the ground that it tended to vary the terms of a written instrument. The court denied the motion on the ground that the contract of November twelfth constituted a limitation of liability of the two surety companies to $5,000 and since it did not limit the liability of the plaintiff alone to that amount it would not preclude the admission of parol evidence with respect to the agreement for the three policies. The parol evidence received in behalf of the defendant tended to show that while Thomson was negotiating for the assignment of the sewer contract the assistant manager of the plaintiff stated to him that if he took the assignment the plaintiff would expect to carry the liability insurance, and that he replied that he would expect the plaintiff to do so without expense, w'hereupon plaintiff’s assistant manager replied that it would not do that; but that shortly thereafter arid before he took the assignment plaintiff’s manager agreed that it would furnish the liability insurance without expense
Clarke, P. J., Scott, Page and Shearn, JJ., concurred.
Judgment and order reversed, new trial ordered, costs to appellant to abide event.