Sigmund Ullman Co. v. J. L. Mott Iron Works
Opinion of the Court
Appeal by defendant from a judgment entered on the verdict of a jury upon a complaint alleging two breaches of contract.
The first contract was in writing and therein the plaintiff agreed to purchase from the defendant for the sum of $1,197 a steam jacketed iron kettle of certain size and dimensions and in conformity with certain specifications furnished by the plaintiff to the defendant, “ Delivery three to five weeks barring labor troubles.” The contract contained this provision, “ Kettle to be tested to 100 lbs. Hydraulic test.”
A second and precisely similar contract for another kettle was made on February 7, 1917, the price being $1,160, delivery to be within four weeks.
The purchaser not only prescribed the dimensions, etc., but selected a style of kettle from a plate in defendant’s catalogue. The purchaser was engaged in manufacturing inks and the use to which it intended to put the kettle, which was huge in size and had to have elaborate concrete, brick and other foundations, was that of boiling varnish. The kettle may be compared in a way to a huge chafing dish, the boiler part being surrounded by a jacket, steam being introduced in the space between the jacket and the bottom of the boiler, thus producing heat to boil the varnish which was placed in the boiler or kettle. The purchaser attended to the setting and completion of the foundations. The kettles had to be specially manufactured and the work was done in the factory of defendant’s subcontractor, the Gibson Iron Works. There was long delay in getting out the first kettle owing to labor troubles, but it was finally delivered in May, 1917, and was installed by a contractor, employed by the purchaser, who,
The second kettle was due in March but it had not been delivered up to the time of the explosion. The testimony of defendant’s witness Home is uncontradicted that the plaintiff called on the defendant for delivery of the second kettle after the delivery of the first kettle, which is long after the date on which it should have been delivered. There is no testimony that at any time thereafter the plaintiff put the defendant in default. There is testimony that after the explosion the plaintiff notified the defendant that it did not want the second kettle, which testimony is denied by the plaintiff. The court first directed a verdict in favor of the plaintiff on the second cause of action but afterwards, at the request of plaintiff’s counsel, withdrew this direction and submitted this question to the jury in a charge that was practically tantamount to an instruction that plaintiff was entitled to
The main conflict on the trial centered about the first cause of action. The plaintiff insists that, notwithstanding the testimony of the Gibson superintendent, the kettle was not tested as required by the contract. Gibson’s superintendent had such an interest in testifying that he did make the test as to make his credibility a matter for the jury. As tending to show that there was no test, the plaintiff relies first upon the fact that the explosion occurred under eighty-five pounds pressure and under conditions showing that the steam had been properly let into the jacket. The defendant claims and introduced testimony to show that it does not follow at all that a vessel which has withstood a hundred pounds test will not explode when subjected to what is called a working pressure of eighty to eighty-five pounds. It claims that the working pressure should certainly not be over half the test pressure, as there is much greater strain when the pressure is long continued, as under working conditions. Whether this is so was for the jury to determine. The second point relied upon to show that the kettle had not been tested was scientific testimony to the effect that a flat bottom kettle such as this, the bottom of which was no thicker than proved, would not stand a pressure of more than fourteen pounds. This scientific testimony, however, is practically worthless in view of the uncontradicted fact that when this kettle was first tested by an independent contractor, who set it up for the plaintiff, it withstood eighty to eighty-five pounds pressure and it was under that pressure long before the explosion. Much complaint is made by the defendant of the fact that the court received this testimony about the shape of the kettle, and received testimony that a kettle with a conical bottom would much better
The judgment and order should be reversed and a new trial ordered, with costs to appellant to abide the event.
Clarke, P. J., Dowling, Smith and Page, JJ., concurred.
Judgment and order reversed and new trial ordered, with costs to appellant to abide event.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.