George Colon & Co. v. Hassenpflug
Opinion of the Court
Michael J. Fitzgerald had a contract with Sarah B. Smith, since deceased, to excavate rock and earth for the foundation for an apartment house to be erected on a triangular parcel of land at the corner of Merriam avenue and University, formerly Aqueduct, avenue. He partly completed the work and then sublet the contract to the plaintiff which completed the work. The plaintiff also had a contract with Sarah B. Smith to put in the foundation for the building. The excavation contract provided that the rock taken out should be used in the foundation, any excess to belong to the contractor, and when plaintiff took over that contract it became the owner of the rock and used what was nepessary in building the foundation under the other contract. There is no question about the full performance by both parties of the foundation contract. While Fitzgerald was working on the excavation contract, he found it necessary to obtain from the city a permit to drive across the sidewalk- to enable his teams to be used in the work and he asked the owner to put up the necessary $250 security by way of a bond or cash. She put up the $250 in cash as security that the contractor would leave the sidewalk in good condition. The excavation contract was oral and concerning its terms Sarah B. Smith said in a letter of June 5, 1913: “ My contract made with Mr. Fitzgerald is as follows: That upon the completion of the excavating of rock and dirt according to the plans filed with the Building Department, he is to receive one-half of
“ I do not think it advisable to cart any more rock away until foundation walls are completed, as architects looking at the work do not think sufficient rock has been left for all the walls that are to be built.” . •
There was some extra excavation done by the plaintiff so that when that contract was completed there was unpaid on it $3,793.40. At this time there was due from Sarah B. Smith on the original excavation contract $3,500.30, as found by the trial judge. When the plaintiff considered that it had completed the excavation contract and made a request for payment it was met by the statement from Sarah B. Smith that there was dirt and rock on the premises which must be carted away and that the sidewalk had not been repaired or replaced to the satisfaction of the inspector of the city and that this must be done by the contractor. There is some evidence that the original contractor, Fitzgerald, did some work on the sidewalk in November, and there is also evidence undisputed that the plaintiff did work January 5, 6 and 7, 1914, in repairing the sidewalk and in breaking up large rocks and removing rock and rubbish from the premises. While the plaintiff claimed that it had fully completed the work on the excavation contract, it acquiesced in the claim of Sarah B. Smith that the contract was no.t fully performed and did the work January 5, 6 and 7, 1914, to comply with the interpretation of Sarah B. Smith.
We, therefore, reverse the findings 2d, 4th, 5th and 9th and find the facts proposed by the plaintiff in its proposed findings numbered 5th, 7th, 15th, 17th, 20th and 22d in addition t© those found and allowed by the trial judge and we make the conclusions of law proposed by the plaintiff except that the amount due on the Fitzgerald contract shall be fixed at $3,500.30 and the judgment hereinbefore entered is reversed, with costs of this appeal to the plaintiff, and judgment ordered in plaintiff’s favor, with costs.
Page and Gbeenbaum, JJ., concur; Clarke, P. J., and Dowling, J., dissent.
Judgment reversed, with costs, and judgment ordered in plaintiff’s favor, with costs. Settle order on notice.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.