John Johnson Construction Co. v. State
Opinion of the Court
In August, 1916, this claimant was awarded a contract by the State Commissioner of Highways for improving a public highway in the city of Jamestown. The claimant signed the contract August twenty-fifth, but it was not executed on the part of the State until December 5, 1916. The contract provided that the work done thereunder should be completed by November 15, 1916, but this provision was disregarded. The city of Jamestown was laying sewer, gas and water mains in the street in question, and, through a resolution of its board of aldermen, the city agreed to have this work completed prior to the date of the award of the contract to this claimant. The city failed to complete its work on time and retained possession of the street for that purpose until along in the spring of 1917. Because of such delay by the city of Jamestown, plaintiff could not proceed under its contract. In fact, it was stipulated in this action that the claimant was not permitted by the State thus to proceed, but was directed by the State’s Division Engineer not to commence any work upon said street until late in the summer of 1917. Such directions of the Division Engineer were the acts and directions of the State. (Ryder Building Co. v. City of Albany, 187 App. Div. 868.) The claimant was ready to commence work within about three weeks after it had executed the contract and remained so in readiness until the work was started about July 1, 1917. This all appears in the findings and is substantiated by testimony. It further appears that the condition of the street was such that brick and other building materials could not be delivered and deposited on the site of the contract between the time the contract was executed in behalf of the State and July 1, 1917. It also has been found that the brick necessary to be used in performing this work would have cost $6,362.60 more at market price on July 1, 1917, than it would have cost in the fall of 1916 and the winter following.
The claimant asks to be recompensed for increased material cost, for rentals and for increased interest, overhead expenses, traveling
The State is held hable for hindering and delaying the plaintiff three months in commencing the work, viz., from April 1 to July 1, 1917. It appears that the claimant could not go on in time with his work in 1916, after the State had signed the contract, because of weather conditions. The city was laying. the mains in the street with the consent of the State Commissioner of Highways. And since the claimant was not permitted by defendant to proceed under its contract until July 1, 1917, the State is responsible for the delay to the extent not only of damages fairly within the contemplation of the parties, but of all damages which naturally flow from the breach. (Niblo v. Binsse, 1 Keyes, 476; Del Genovese v. Third Ave. R. Co., 13 App. Div. 412; affd., 162 N. Y. 614; Schunnemunk Construction Co. v. State, 116 Misc. 770.)
Belmar Contracting Co. v. State (233 N. Y. 189), cited by defendant, is obviously not in point. In the instant case the State’s liability as found accrued after the execution of the contract by both parties; the situation was otherwise in the Belmar case. The defendant cites two cases upon which it mainly relies, viz., Connolly Co. v. State (120 Misc. 854) and Montgomery v. Mayor (151 N. Y. 249). In the Connolly case unfinished work by the city was being carried on to the knowledge of claimant before his contract was signed by the State Commissioner. In fact, the claimant urged the Commissioner to sign with such knowledge. In our case the city by its resolutions promised to have its work finished before the contract with the claimant should be executed by the State. Furthermore, in the Connolly case the claimant consented to the granting of the permit to the city. The Montgomery case is not an authority for the State. It simply holds that a contractor has no cause of action against a city because an inspector (whose certificate of inspection and approval was necessary under the agreement of the parties) delayed work by rejecting materials. The appeal of the State in the instant ease must fail.
We disagree with the court below in its finding that the delay beyond the spring of 1917 in beginning the work was due to claimant's failure to procure brick in the fall and winter of 1916, and that no allowance should be made to claimant for increased cost of brick. Under the testimony there seems to be no doubt that in the fall of 1916 and the winter of 1917 claimant could have procured sufficient brick at eighty cents per square yard delivered on the site; also, that because of the_condition of the_street during that
There is direct authority for our holding that the State is hable for this item of loss to the contractor. Allamon v. City of Albany (43 Barb. 33) states the correct rule, which has never been questioned, but often cited with approval, namely, the rule that a recovery may be had under such circumstances for increased cost of material. (Bates & Rogers Const. Co. v. Board of Com’rs, 274 Fed. 659, 661; Sheldon Breck Const. Co. v. Regents of the University of Michigan, Id. 985; 2 Sedg. Dam. [9th ed.] § 642; 3 Suth. Dam. [4th ed.] § 714.)
The same rule is also laid down in Kelly v. U. S. (31 U. S. C. C. 361). United States Steel Co. v. Casey (262 Fed. 889) and Louisville & N. R. Co. v. Hollerbach (105 Ind. 137) recognize the same general principle.
Findings of fact Nos. 24 and 25 should be disapproved and reversed, the former as incomplete and the latter as erroneous,
Judgment modified by increasing the amount of the award to the sum of $8,720.77, and as so modified affirmed, with costs to claimant. Findings of fact Nos. 24 and 26 disapproved and reversed and a new finding of fact and conclusion of law made.