Tisdale Lumber Co. v. Medtradco Realty Co.
Opinion of the Court
This action was brought to foreclose a mechanic’s lien. The plaintiff under a contract with the defendants furnished lumber for the erection of two houses erected by the defendants on their lands. The contract between the parties is evidenced by several writings, but it is agreed that they constitute one contract. It is provided in the writings in relation to the rough lumber that payments are to be made as follows: “ As building progresses 50% when Rough enclosed is $567.50 and extras 50% when Brown plaster is $567.50 and extras. Extra material to be paid for with each payment.” Pursuant to said contract the plaintiff furnished materials to the value of $1,158.46, and then disagreements occurred. The plaintiff claims that it had furnished the necessary materials to bring the buildings to the rough inclosure stage and that it was entitled to be paid $567.50. The defendants dispute this and claim that the plaintiff had failed to furnish the necessary materials. The dispute centered about the actual furnishing of materials. The defendants did not pay and the plaintiff would not furnish material until paid. Thereupon plaintiff filed a mechanic’s hen and this suit is brought to foreclose the same. The defendants pleaded a counterclaim for an alleged excess in the cost of the lumber purchased to complete the buildings, but upon the trial this was abandoned. The only controverted question was, did the plaintiff furnish the necessary material to entitle it to the first payment? This question was decided in favor of the defendants and judgment entered dismissing the complaint.
Naturally, upon a contract like this, all the lumber was not delivered at one time. It would have been impossible for plaintiff to do so and equally impossible for defendants to care for it if delivered. It was undoubtedly the desire of both parties that the materials should be delivered as the exigencies of the work required. The materials that were first needed were to be delivered first. Apparently the plaintiff did not deliver materials as rapidly as the defendants desired, and interviews were had and correspondence passed between the parties in relation thereto. On May 11, 1922, the defendants wrote the plaintiff, “ the amount of 3x8 beams that are needed to complete the roof tier is forty-seven (47). 2x6 28-12. The bridging, furring, pine facia, soffit, bed moulding and sufficient roofers to cover roofs.” This letter was written by Mr. Martin, the secretary of the Medtradco Realty Company,
Now, to take up the question of whether the building had reached the “ rough enclosed ” stage. On June 10, 1922, the defendant company wrote the plaintiff: “ Several times we have requested you to inform us as to what credit we are entitled to receive for the material you have failed to deliver. We again make that request; you will please inform us by return mail how much credit we are entitled to receive for the materials you have failed to deliver. Owing to the fact that you have welched on your agreement, the sooner you give us this statement, itemized in detail, the quicker you get your money. Your money is waiting for you, all that is required is the proper adjustment.” On June 20, 1922, said defendant’s secretary had an interview with Mr. Tisdale of the plaintiff corporation. Mr. Tisdale testified that Mr. Martin told him the buildings were rough inclosed but declined to pay him the amount specified in the contract. Mr. Martin offered him $389 with some deductions. A Mr. Bossier, in plaintiff’s employ, says Mr. Martin said the building was rough inclosed but declined to pay $567.50; said he would pay only fifty per cent of the amount of the lumber delivered, less some claims for credits. Mr. Martin, interrogated by the court, testified that he offered Mr. Tisdale one-half of $785 (the amount of lumber then delivered), but he refused to accept it. Martin demanded a guaranty that the contract would be completed without delay. Tisdale declined to give it. Mr. Martin continues: “ So I asked him what assurance would he give me that if I gave bim his money he would carry out his contract, and he said, ‘ None.’ He said he wouldn’t talk until he had received $567.50. I said: 1 If I give you $567.50, what will you do? ’ He said: £ I refuse to talk to you until I get $567.50.’ I said: ‘ I will pay you $567.50 if you will give me an assurance that you will carry through your contract without delay to me.’ So he refused, and I left his office.” Under the guidance of counsel he says he believes he told Mr. Tisdale the buildings were not rough inclosed. This is entirely out of harmony with the testimony quoted above. To corroborate him Mr. Rosenzweig was called and he says Mr. Martin told Mr. Tisdale “ he was willing to pay him the money if
Findings of fact 6, 7, 8 and 9 should be reversed as contrary to the evidence, and the conclusion of law annulled. This court should make proper findings to sustain a judgment in favor of the plaintiff. The judgment should be reversed on the facts, with costs, and judgment entered in favor of the plaintiff, with costs.
Kelly, P. J., Rich, Kelby and Young, JJ., concur.
Judgment reversed on the facts as contrary to the evidence, with costs, and judgment directed for plaintiff, for the relief demanded in the complaint, with costs. Settle order and findings in accordance with opinion, on notice.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.